AIC Mines Limited (A1M) Earnings Call Transcript & Summary
April 16, 2026
Earnings Call Speaker Segments
Aaron Colleran
executiveThank you, Ashley. Despite some major hurdles, the Eloise team turned in a really strong March quarter. Rain was heavy: 396 mils fell in February by itself, following a 571 mil drenching in December, which we believe makes it the wettest wet season Eloise has ever seen. Even so, the team still came through with a great result. Saying we finished on a wet sail would be putting it mildly. We nonetheless turned out 3,432 tonnes of copper and 1,692 ounces of gold in concentrate, at an all-in sustaining cost of Aussie $4.18 a pound and an all-in cost of Aussie $4.49 a pound, which means we met, and here actually beat, guidance for the eleventh quarter in a row. That is remarkable, and hardly any companies can claim a record like it. What the quarterly doesn't show is how much effort the site team put in to get this quarter across the line. The rain made it a really hard quarter. We were contending with hot, humid conditions, dams at capacity, water releases, closed roads, supply chain problems, a smaller ROM pad area, a smaller concentrate pad area, and plenty of construction work. Thank you to the Eloise team. Importantly, the underground mine development we finished during the quarter is positioning us well for a solid June quarter. We remain on track to exceed the top end of production guidance and perhaps the lower end of cost guidance, diesel permitting. Eloise brought in $27.7 million of net mine cash flow and had $8.3 million of concentrate remaining on site when the quarter ended; that material has since been sold. Eloise generated $27.7 million in the quarter. I may be repeating myself a little, but that exceeds what it generated across the whole of FY25. Eloise is producing strong cash flow, sufficient cash flow, together with the Trafigura debt, to cover everything we need and want to do over the coming 12 months; for anyone unable to read between the lines, and there seem to be a few, let me be clear: no additional capital is needed from us to finish the 1.1 million-tonne-per-annum expansion or to advance the potential 1.5 million-tonne-per-annum expansion. Copper prices are very strong right now; however, yes, the diesel price is somewhat worrying. Let's turn straight to that. So far, Eloise has kept receiving its full contracted diesel allocation, and has heard nothing from Chevron, our supplier, suggesting that will change. Diesel costs have climbed substantially; we all know that. Chevron has told us that April diesel costs are 50% higher than the average net price we have paid year-to-date. That increase works out to an extra $1 million in April versus our average month. May looks set to be higher still, since current prices are running 20% above the April price. We estimate that could mean an additional $1.5 to $1.6 million in May versus the average month. We figure higher diesel costs might push AISC and AIC up by roughly AUD 0.40 to AUD 0.50 per pound during the June 2026 quarter, and by about AUD 0.12 to AUD 0.15 per pound Aussie over FY 2026. That covers only the direct piece. Indirect cost increases exist too, though pinning down their likely size across the full quarter is really hard right now. Even so, the strong copper, gold and silver prices we are getting are protecting us nicely at present. At Jericho we are running ahead of schedule. Commissioning of the Eloise expansion project is still slated for the December quarter. Spend on both projects is basically tracking the plan. Still, the numbers are becoming difficult to square. Our CFO, John Callagher, is on the call with me. He can field those questions, since I tend to muddle them. At Jericho we are so far ahead that we are now looking at speeding the ramp-up to 1.5 million tonnes per annum. We will not hold development back to fit a budget that is already out of date, particularly since Eloise is throwing off considerably more cash than we had anticipated. The Eloise expansion project, run by GR Engineering, is on budget. This quarter brought good news on the expansion schedule and budget. Equally important, perhaps more so, are three de-risking events I want to flag. The Jericho access drive has cut through the J1 lens, which confirms the mineralization style and geotechnical conditions match the Jericho geological model. Have a look at the diagram on page 11 of the quarterly. That now cuts mining and ramp-up risk materially. The new ball mill reached site after the quarter closed. It is the key critical path item for the expansion project schedule, and having it on site early is great. On the ROM pad we hold 12,000 tonnes of Jericho development ore. A three-day batch processing trial of that material is set for late April to validate the metallurgical characteristics of the Jericho ore. We have already slipped some small parcels of Jericho ore through the plant, and it has responded beautifully. Once the data is compiled, we will update you on the batch trial. The next critical job at Jericho is installing the JS3 ventilation shaft. Surface works are finished and the raisebore crew is on site, ready to start the pilot hole next week. Having the vent shaft operational by the end of June remains on track. During the quarter we released the Eloise and Jericho Mineral Resource and Ore Reserve updates. Combined Eloise project Mineral Resources rose 10%. At Jericho, we added 63,900 tonnes of copper to resources. That was done at a cost of AUD 33 per ton, or AUD 0.015 per pound, Aussie dollars, AUD 0.015 a pound, we are adding copper to the resource. It's a phenomenal deposit, and the exploration team there is excellent. Ore Reserves at the combined Eloise project rose 14%. That's a terrific result. The Eloise processing plant now has access to the biggest resource base it has ever had in its 30-year history. Let me slow down a bit here; I want to emphasize something. It's really remarkable. Back in 2021 we acquired an asset whose mine plan covered two years and produced 12,500 tonnes of copper; today we hold an asset with an outlook beyond 10 years, with expansion under way toward 25,000 tonnes per annum of copper. The market seems to be waking up to this transformation right in front of it, slowly, very slowly. Regionally, we are back out in the field exploring, Godspeed. 12 targets will be drill tested this year. Having the team back in the field is great. Our ground holding is strong, structures are pervasive and geophysical targets look good. Time will tell. Moving to financial performance, did I mention Eloise produced good cash? During the quarter Eloise generated $72 million in metal sales after TCRC reductions. Deductions during the quarter. Surely a record, though one we hope to beat soon. Cash flow I've already covered, but capital expenditure deserves some explanation.
Aaron Colleran
executiveAt this point we're 75% through the year, so our capex guidance should likewise be 75% consumed. Every quarter I walk you through this. A handful of key items have run over, the same ones flagged three months ago. Let's review them so analysts don't panic and conclude capex has slipped out of our control. That is definitely not what's happening. In certain key areas we've spent more because it's justified, usually pulling capital forward to make the mine plan bulletproof. Elsewhere, we hadn't budgeted for certain items or activities that are now included, essentially gated capital. We've generated extra cash and used that chance to do more. To be specific, underground mine development already sits at 105% of full-year guidance. As in earlier quarters of this financial year, underground capital development costs have come in above budget because a greater share of mining activities is being charged to capital. That higher underground capital development cost is offset by lower mine operating costs. Resource definition drilling stands at 100%. It was gated at $2.5 million versus a planned $3 million, and we've now passed that gate as we firm up resources in the lower levels before mining. Long-term mine development is at 100%; it's at the same stage described above for underground mine development, with a greater share of mining activities charged to capital. Non-plant infrastructure is at 82%; that reflects a mix of overspend from higher costs and a larger owner's team than budgeted, plus some added costs as we finish the full engineering studies for the upgrades. The power upgrade is the main driver there. Corporate is at 85%, slightly over as well; we've taken a couple of swings this year, and obviously a swing and a miss, since there's been no news on the acquisition front. Rest assured, we stay disciplined on that front. Right now, the best value we can create for shareholders is delivering the Eloise expansion on time and on budget, and that's our major focus; that wraps up my review. I'll ask the operator, Ashley, if you're still there, to open the lines for questions. Thank you.
Dan Morgan
analystHello, Aaron and the team. I'd like to ask about the project and how it ties in with the resource reserve you recently released. Essentially, you're running ahead on Jericho's development, the mill appears to be progressing as planned, and you've expanded the resource reserve base. Oh, and clearly your cash flow has improved thanks to the commodity price environment as well as the production upgrade. What would you need to see in order to formally move past the 1.1? Does it have to be delivered first, or is that already something you're considering? Thank you.
Aaron Colleran
executiveYeah. Sorry, Dan. This 1.1 1.5 situation is somewhat troublesome. Duncan is sitting fairly near me and serves as our stand-in for the JORC police, so I'll watch my words. Dan, what we need is to finish our life-of-mine plan and give you a long-term outlook covering 3 years, 4 years, 5 years, and once we've run it through JORC, we're permitted to tell you that we're building a 1.5 million-tonne-per-annum plant and that we're ramping up underground at Jericho to the 1.5 million-tonne-per-annum rate. Until we've brought that to the market, and that will likely come with our FY27 guidance, we'll deliver in July. That life-of-mine plan is coming together now. We wanted to get it to you alongside the MROR, but we didn't; that life-of-mine plan actually takes quite a few iterations to get right; we want it spot on; we're doing that now. We'll deliver it to you, unfortunately as late as it is, but in July. We will have run it through. Then we won't need to beat around the bush. We won't need to put out these statements that carry disclaimers, and I won't need to use potential and aspirational and all that language everywhere. Dan, I hope that is clear. That work is underway, remember, the plant we're building at the moment, the expansion at the moment, $77.6 million, that was roughly $15 million over, well, $17.6 million over our $60 million original estimate. That's because we did include upgraded components. The crushing system we're installing now is a 1.5 million-tonne-per-annum crusher; it'll need a new ball mill, though, to get it to 1.5. We can do that out of cash flow. We'll do that, as and when required. Some people have asked, namely my chairman, whether we've ordered that long-lead-time item. Sure, we're hearing that the long lead on mills is starting to push out beyond the sort of normal 12 months. This one is fairly straightforward, what we need, to the point where we can bring on one of our idled mills if needs be; it's not on a critical path. Even the long lead, even the order isn't critical path at the moment; it's underground development that's the real piece. Right now we are working out what that will cost, and whether we ramp to 1.5 fast, very fast, or very, very fast; it largely hinges on how many jumbos you have and how much money you put behind it; we have to weigh that against reality. As you have watched us do with this project from the start. We are forever running to keep pace with it, but we are running. A bit of rambling there, Dan, but I hope that answers what you asked. Was there anything else you needed?
Dan Morgan
analystNo, I appreciate that context. Perhaps I'll ask something separate. From your comments, I gathered that you're putting more money into projects, and part of the reason is that the Jericho development is going really well — so why would you slow that down? I understand that, and you have the cash and improved cash flow to support it, but could you perhaps make it simpler to separate what represents discretionary additional spending you've been doing from what reflects inflation or items that have become more expensive? Do you see what I'm getting at?
Aaron Colleran
executiveYes, I do. That's a reasonable question. That's genuinely tough to answer right now — I doubt we're tracking that closely. The reality is you saw the cost overrun at Jericho, really JS1 last year. That's behind us. Looking just at mining, the vent shafts we've installed have come in on budget, and nothing there has been discretionary or extra. Going back to your creep point — we haven't seen any creep there. Let's set diesel aside and what's ahead of us, put that to one side for now. We'll bring an additional jumbo, an additional drill rig to Jericho. That will be discretionary. We can lay that out for you very plainly. Dan, my sense is that really applies starting with the June quarter; after that, for GR's, it's EPC, quite simple. Whatever you sign for should be exactly what you receive. December is when we'll know. Far, quite solid. Far, nothing creeping in there, no disputes, and just a few small claims filed from time to time, but nothing problematic. A few of the cost overruns we've seen at offices and a camp run into the hundreds of thousands of dollars, Dan. We don't regard that as material. As for the NPI overrun I mentioned — needing additional power earlier — one could make the case that it's discretionary. You could make the case that our original budget was too low once we got into the full engineering work. We ended up needing a larger upgrade to power, and we needed it sooner than we had first anticipated. That's likely true for much of what we're doing, since, as I mentioned, we're running to keep up. We brought on a fairly large owner's team, which was what we required. We didn't budget enough for them. We're beginning to let some members there go, which is unfortunate, but that's how these things happen. I'd like to keep these guys forever. I want another project to put them onto. We're working hard to do that. Another topic, sorry, I wander easily. Let me scan the room quickly to check whether there's anything more you need. If you'd like, we can follow up separately with you and John Callagher. I realize I've mostly given context rather than the percentages and figures you were probably after. Those amounts are fairly minor. Compared with what we're investing in development and EPC at Jericho through the GR's, they're pretty inconsequential.
Dan Morgan
analystThanks for that. Maybe we can dig into this further after the call. Just one final thing. Given all the rainfall that's been widely reported in the area, I was somewhat taken aback. Clearly, conditions have been quite difficult for mining companies. It surprised me a little that your operational figures came out so strong this quarter. Delayed effects are possible, which means you could see impacts in the June quarter that aren't apparent to us on either the operations or the projects. Is there anything at all worth flagging on that front?
Aaron Colleran
executiveYeah, great point — that's a legitimate question, and I've definitely worked with assets in the past where one solid quarter is followed by a painful one right after, which is exactly why I raised it. I believe it's in the quarterly, but in the notes I read, and importantly, the underground mine development that got completed during the quarter is positioning us well for a strong June quarter. We're on track, yes. No, nothing I can see will make June difficult for us. June might be — well, not a repeat of March, but along the lines of March. Looking at the TKM diagram we included, February stands out as truly dreadful—I have no desire to go through anything like that again. As you'll notice, we pushed a great deal of high-grade material through during March. Coming into the June quarter, we were sitting on substantial stockpiles, plenty of material on the ROM pad, and a lot on the cons pad as well. Much of that has since been cleared, which should give the June quarter a boost. What I was building toward is this: I expect we'll keep pulling higher-grade material out of the underground, from the Deeps, and mix it with those fairly sizeable lower-grade stockpiles sitting on that ROM pad. That's the kind of granularity that doesn't come through when we put out our quarterly report, Dan. It's a reasonable question, and yes, my expectation is that the coming three months will shake out as another solid quarter.
Dan Morgan
analystFine, I appreciate hearing everyone's points of view.
Aaron Colleran
executiveNot a problem at all, those come at no cost and you can get them whenever you like. Take care.
Hayden Bairstow
analystMorning, Aaron. That's a solid result. I just wanted to talk a bit about TCRCs. They're clearly bouncing around quite a lot. I'd like to understand your exposure and how it could shift over time given what's happening in the spot market compared with what you're receiving.
Aaron Colleran
executiveI'm going to ask John shortly what our TCRCs actually are, since otherwise I'd only be guessing; we have a contracted Eloise life-of-mine offtake with Trafigura. The benchmark TCRCs come to us, and those get set every November. We sell nothing into spot. John, what's the TCRC at the moment?
John Callagher
executiveCorrect. The baseline TCRCs have been locked in for this calendar year at zero?.
Aaron Colleran
executiveAt zero?
John Callagher
executiveYeah. Yeah.
Aaron Colleran
executiveFree treatment. Zero? Yeah. Whoo! I'm glad I asked. Zero, Hayden.
Hayden Bairstow
analystThat's a solid figure; so looking ahead to next year then, John, do we see benchmarks extending sort of past the calendar year — they are definitely all comfortably negative. Should that be our assumption as we head into 20 into '27? It's
John Callagher
executivehard to say. For the calendar year, certainly, this is where we stand, but beyond that we also have that $10 charge sitting there as part of our finance facility arrangement as well.
Aaron Colleran
executiveRegarding Jericho.
John Callagher
executiveAs for Eloise, that will effectively span two years of production. That is what I am currently viewing as the baseline.
Hayden Bairstow
analystfor
John Callagher
executivethe near- to medium-term outlook.
Aaron Colleran
executiveIt's difficult to say, Hayden. Given how strong sulfuric acid prices are, you could reasonably anticipate that TCRCs would stay low. That's quite possible. It would surprise me. Then
Hayden Bairstow
analystTurning to capex, Aaron, clearly you're putting $40 million into Jericho during that quarter, but could you break that out between mine development and what's happening at the mill? How uneven does that look across the remainder of the calendar year?
Aaron Colleran
executiveYou mean for Jericho?
Hayden Bairstow
analystYeah.
Aaron Colleran
executiveIt should be flat.
Hayden Bairstow
analystSo what's the total capex still remaining for the mill expansion from this point? Oh.
Aaron Colleran
executiveThe mill expansion,
John Callagher
executiveWe will return to that.
Aaron Colleran
executiveWe'll circle back to you on it; we're only partway through that.
Hayden Bairstow
analystSo we should figure on roughly $40 million each quarter through the remainder of the year, give or take?
Aaron Colleran
executiveThat's right, on the whole.
Hayden Bairstow
analystAlright then, great, appreciate it, everyone.
Aaron Colleran
executiveSure thing, thank you, Hayden.
Daniel Roden
analystHello Aaron and John. I appreciate you taking my call. First, I'd like to revisit the 1.5 expansion, if I could. Perhaps clarify a bit—could you lay out precisely, I suppose, what's required to reach that 1.5? I know you've described the ball mill, and what the capital expectations are, I guess, for that? You've sort of hinted at this already, too, but the timeline for possibly getting that online. Is there still perhaps a 12-month lead time before you sort of achieve that? I'm just trying to attach a few metrics to it, I guess, if that's okay.
Aaron Colleran
executiveBall mill, a bigger rougher cell, Aussie $15 million in the plant. I'll turn it over to Ben to talk about Jericho specifically — how the ramp-up is shaping up on the underground equipment and development side. On the timeline, Dan, that's something I can't answer. If we had it, it would be a standalone announcement; that work is underway right now. I realize we owe you that, and that you've been waiting on it — July is when we'll get it to you. Ben, anything to add about the Jericho ramp-up? Ventilation is what's holding us back from hitting that higher output level at Jericho. Once those two remaining ventilation shafts at Matilda are finished, we can bring in one more jumbo, which lifts the development pace to 750 meters per month; after that, it takes only one to two years before we can move to the higher production level. All told, reaching that rate will take roughly three to four years from today. Yeah. Thanks. Thanks, Dan. Yep,
Daniel Roden
analystYeah. No, thanks. I just wanted to flag that you've got, I suppose, 12,000 t of ore from Jericho sitting in your stockpiles and getting processed during the June quarter. From a cost standpoint, is that being capitalized? And then, as a follow-up, I guess what are
Aaron Colleran
executivethe—you're the only one who's raised that. That's—yeah, I'll pass it to John. Good question. I think we're still working out ourselves what to do with that. No, John may have the answer. I don't. Go
John Callagher
executiveContinuing. From where I sit, I would definitely put that into the project as capital. Regarding the mine, I realize we have to examine the accounting rules that apply there. If we're talking about how we handle it on an internal basis, then yes, that would be the response, but after that comes the audit and statutory element from a technical standpoint, which could affect how it gets treated in the stat accounts. There's a chance we'll be pushed toward treating it as revenue.
Daniel Roden
analystYeah. Yeah, understood.
Aaron Colleran
executiveDan, we’re going to take real care in the June quarterly to make sure we lay it out separately or break it out for you; honestly, it’s de minimis. We’ll break it out for you so it won’t complicate the way you’re modeling Eloise.
Daniel Roden
analystYeah, no, I can't wait to read that special note about me in the June quarter. But just to follow up on that, and I guess ahead of the 1.1 mill expansion at year end, do you figure you'll build up some working capital inventory during the quarters before then? Since you're ramping into Jericho right now, that 12,000 t, I take that to mean you'll run a batch treatment just to see how it floats and how it moves through the mill. So what quantity of inventory do you expect to build up before the 1.1 mill gets commissioned?
Aaron Colleran
executiveOh, that depends. Ben, do you want to take that one? It's a difficult one. Dan, our estimate is that it will come in under 50,000 tonnes. We'll get started, and we'll return to mining at Jolly — not on a just-in-time basis, but since we now have the development heading toward Matilda and the development preparing Jolly, we'll open Jolly up whenever we need it. Some of our earlier work involved building a fairly large stockpile, which is beneficial from a de-risking perspective but not beneficial for cash flow. Really, the optimal approach is to deliver ore to the mill as needed. Of course, that makes sense. You understand that. Get the jumbos working on development and put that behind us. Ben's response seems exactly right to me. We're certainly aiming for that Goldilocks inventory level of about 50,000 tonnes—not oversized, not undersized. That's right.
Daniel Roden
analystYeah, no, perfect. Perhaps I just wanted to pose one final question, I suppose, to try to get a bit of color on diesel. I think your disclosures on this have been fantastic, by the way. Just noting that in the June quarter, there's a bit more leverage from the Deeps, which is increasing the TKM. If you had a crystal ball, I don't know whether it would have changed it or not, but and it's incredibly hard to change near-term mine schedules, of course. If diesel stays pricey through year-end, how do you weigh that trade-off between heading into Deeps and working higher Eloise Macy plus some of the higher, shallower parts of the ore body that could carry a lower TKM cost-wise? Is that on your radar at all, and, I don't know, just, yeah, a little color on
Aaron Colleran
executivethinking about
Daniel Roden
analystThat's a benefit.
Aaron Colleran
executiveWe're thinking about it all the time. Dan, honestly, there's no simple answer here, so we'll respond as things develop. There isn't much we can do ahead of time. As best we can, we're preparing ourselves on site, but we're a small company with a single asset and we're a big diesel consumer. On price, I believe price is rising. We need protection from the copper price, and really from gold and silver too, and that I can see coming. Price doesn't worry me. Until I got up this morning, supply didn't worry me either, but that was the maintenance crew at Viva Energy having some fun today. A terrible accident, and I'm very relieved to hear nobody was seriously hurt. Awful, but yes, perhaps we're back to worrying about diesel turning up. We held a war room, for lack of a better phrase, and I'm sure a better phrase exists, to work out what we'd do if we got 10% less, 20% less, or half our diesel. It's fairly easy to work out the scenario if we get none at all. Those scenarios aren't good. We have a response ready for each one. We'll handle it much like crisis management, reacting if and when it happens and for whatever stretch it happens. It's very hard to do much right now, Dan, since some of those responses are fairly harsh, not good if we were getting half our fuel allocation. There's no simple answer to that. If we're down 10%, well, sure, perhaps there is. One upside is that we're going into winter. I'm not sure Queensland really has a winter, but let's call it the cooler, drier season. We aren't running the chillers as much. Chillers draw a lot of power. That gives us a bit of help. You're right. It'll focus on TKM, of course. Campaign milling, all those kinds of things are possible, but the outcomes aren't pretty. We'll handle it if we have to.
Daniel Roden
analystYeah, yeah. No, that makes sense. Perhaps the second part of what you said is somewhat redundant, but maybe from my own standpoint I'm personally a bit less concerned about supply than I am about costs. I suppose, but looking at it from a cost angle, do you notice much of a gap between the shallower, lower-grade tonnes and the deeper, higher-grade tonnes coming out of the mine when it comes to NSI? If so,
Aaron Colleran
executiveNot really. Not really. I believe you've gone over some of that with us previously. The grade in the Deeps is simply excellent.
Daniel Roden
analystYes. Right. No, that makes sense.
Aaron Colleran
executiveHold on, I’ll let Ben provide a bit of color. To give you a sense of diesel usage, mobile equipment accounts for 15% of the diesel we use on site. Any tactical change in trucking doesn’t really move the needle. Yeah. Yeah. Thanks, Dan.
Daniel Roden
analystGreat. Yeah. No, appreciate it, everyone.
Aaron Colleran
executiveThat's all from Daniel Roden, thanks.
Daniel Roden
analystThanks a lot, buddy. Here we are. I really appreciate it. Thanks for making the time. It's always great to talk with you.
Aaron Colleran
executiveHi there, Belinda.
Belinda Humphries
analystI’m just here for a few small points around the edges. Clearly, most of it has already been addressed to some degree. With that really strong quarter of 27.7 million, and then you have the stockpile there, and obviously you wouldn’t be expecting as many weather disruptions this quarter, would you expect an even better financial result, or are there other factors at play?
Aaron Colleran
executiveThe key factor in play is the copper price. We're observing it trading somewhere in the range of $17,000 to $18,000 per tonne in Aussie dollars. That $1,000 per tonne genuinely makes a meaningful difference, as you can see, multiply that across 3,000 tonnes for the quarter, 1,000 bucks either way begins to matter. The gold price matters to us as well. The exchange rate matters too. Belinda, if we return to just tonnes and grade, the coming quarter is positioned to be a strong one, of course, all else being equal, we ought to have similar cash. We entered the quarter holding fairly large stockpiles. We cleared them out. We came into this quarter with a big stockpile. We cleared it out, and then we rebuilt it. That was down to weather, down to trucking. Moving into this dry quarter now, we'll touch wood, a clean pad by quarter's end; that remains to be seen, probably Oh, well, should that happen, we'll see sales exceed production, and another solid revenue quarter. Where we stand at the start of the quarter today, or where we began the quarter, at roughly $18,000 a tonne, if this price holds, or improves, through the whole quarter, then certainly, the June revenue, the June cash will look stronger than March, but we'll see.
Belinda Humphries
analystYou also said something fairly low-key about possible acquisitions. Clearly, the cash is there. Could you expand on that a little bit more?
Aaron Colleran
executiveI couldn't hear you, Belinda. Can you repeat the question? You're very very faint.
Belinda Humphries
analystYour remark on possible acquisitions was pretty understated. Clearly, the cash is sitting there. Could you expand a little on what you intend to do on that front?
Aaron Colleran
executiveApologies. Look, yes, I realize it was understated, likely on purpose. I appreciate you pointing that out, Belinda. You won't be getting a question next quarter. No, we are an acquisitive company; that's in every presentation we give, and anyone familiar with me basically knows my history and, naturally, what we're attempting to accomplish at AIC, building a mining company, a multi-asset company. We keep watching for the next project. I really want to retain that construction team and the expertise we're developing right now. I want to deploy it as fast as possible while new projects are already behind schedule on securing that project. Duncan Bristow, who handles business development here and investor relations, is assisting me; we're reviewing many opportunities. Sometimes you don't budget for that, and naturally you don't budget for M&A failure, because examining an asset and performing due diligence is costly; then when nothing materializes, you absorb that cost and shareholders say, "Oh, jeez. Why is corporate cost 8 million bucks, not the 7.5 million that they expected?" We've made that point today to say, well, we've had a swing and a miss, and earlier in the year we were in defense mode; that isn't cheap. We've emerged from that; we're back on the hustings. We'd love to buy another asset. It isn't easy. I kept it understated, Belinda, because I also want to make it clear that we're not about to blow our brains out on buying something. I think shareholders are often worried about that. Please show me the respect of what we've achieved over the 7 years here, if not the last 20 at Evolution and AIC. We remain very disciplined. We're seeking an asset of better quality than Eloise. That's not hard. Sorry, sorry, that's not easy. I was going to say that is very hard at the moment. We're seeking something that equates to good value, that is value accretive. Again, that's not easy at the moment when we're comparing asset quality to Eloise and value accretion to where we are, pre ramp-up, pre the valuation that we expect to be at, you know, the 1st of January if you know when we deliver the current upgrade. Sorry, I hope that answers the question. Is that clear, Belinda?
Belinda Humphries
analystYes, it does. Just one more brief one.
Aaron Colleran
executiveYeah.
Belinda Humphries
analystSo you mentioned the heavy rainfall, and obviously there was a small uncontrolled discharge of mine-affected water. Could the regulator take any action over that, and do you feel any mitigation measures are needed at the site, or has it actually held up quite well, all things considered? It
Aaron Colleran
executiveIt came through quite well, all things considered. Maybe, though probably not. There isn’t any actual harm. We had plenty of water. When you get that much rain, whatever falls on the northern part of our tenement finishes up at the southern end. Strictly speaking, that is mine-affected water departing the site, and that is a problem. We made every effort to avoid it; this year it was nearly impossible. We obtained temporary permits, and we brought water cannons onto the site. We did all we could to prevent it. I wanted to stress that the team on site performed brilliantly, and this was not the straightforward quarter it appears to be when you look through our high production and low AISC. It was a demanding quarter, and we were doing everything possible. Also very transparent. Certainly, we will see where we land regarding that one omission, but I don’t anticipate anything with a material impact. Those are always difficult to predict, difficult to tell, Belinda.
Belinda Humphries
analystMany thanks.
David Coates
analystThanks. Good morning, Aaron and team, and well done on a solid quarter. Honestly, most of what I wanted to ask has already been covered quite thoroughly. If it's alright, I'd just like to dig into a few specifics.
Aaron Colleran
executiveI
David Coates
analystI know you made a few comments in the quarterly, and I did just miss the first few minutes of the call. Mined and processed tonnes came in lower this quarter, and the grade was higher. You've said that the June quarter looks pretty good for grade. I guess one of the natural questions that might come out of that is how sustainable those grades are in the context of, I guess, the broader mine plan and?
Aaron Colleran
executiveWe're definitely in a high-grade zone at the moment. You saw that in March, and you'll see it in April. David, the sustainable grade to be modeling — and I'm not telling you how to suck eggs — but you know the sustainable grade to be modeling is our reserve grade. Be sure, Dave, we'll head back towards reserve grade. I think there's a paragraph in there that references those development headings being, what was it, Ben, 6% or 7% copper. That's not sustainable, but you've seen Eloise. She produces those headings, but sure. No, we haven't turned a corner to find something that's completely different to anything we've ever seen before.
David Coates
analystNo, cool. That's simply the natural ebb and flow of the mine plan?
Aaron Colleran
executiveYes, it was, actually. I realize that pulling out high-grade in March looks suspicious. We had to. It was there; it also happened to be there.
David Coates
analystNo, cool. Once more, like the other folks on this call, I definitely appreciate what you've shared about the wider fuel supply picture. What I was asking was, I guess, a bit of a gossipy question. In chatting with other producers and people around the place, one remark that has kind of risen to the surface is that Trafigura has been able to lend a hand on the fuel supply side, thanks to their global trading network. Does that give you guys a little extra reassurance on your fuel supply, or is it basically a furphy?
Aaron Colleran
executiveThat's not an easy question to answer, David.
David Coates
analystI've used up every one of my simple ones, mate.
Aaron Colleran
executiveWhat I'd say is it's been great having two partners right now: Trafigura and THIESS. Both of them have honestly come to us and said, "Look, we want to back our partners as much as we possibly can." Pybar realized that if we run out of fuel, they run out of fuel, and that hits their business harder than it hits ours, frankly. Same with Trafigura. Trafigura doesn't see any sense in us running out of fuel, only for them to be left with nothing to trade. That's a general answer. As things stand today, David, a general answer is all I can offer, since neither of those partners has actually delivered one extra liter of fuel to us or given us fuel a cent cheaper than what we'd otherwise get, because we haven't needed that. Chevron has done precisely what the contract calls for so far. Yes, those partnerships always are, and here their network, their contacts, their capability, their vision, what they're able to see, could prove very helpful. We've had early-stage talks on that. It does give us a bit of comfort. David, we're out there operating in circumstances we've never faced before. Who knows? Who knows how this will unfold? I think, as one of the earlier Dans — Dan or Dan, I can't recall which — put it, "Yeah, not really so worried about supply anymore." Price will fix supply, but where does price go? We don't know. Yeah. I hope that answers. I hope that gives you some color. I think that other comment you got about trap may have been overplayed, but let's see.
David Coates
analystThat's exactly why I'm putting the question to you — I want a direct answer.
Aaron Colleran
executiveOn me, mate. Sadly, completely honest.
David Coates
analystYeah. Sounds like you guys have been running through your contingency plans, and
Aaron Colleran
executiveI guess
David Coates
analystYou likely don't have the same number of levers at your disposal as larger firms with broader operations and that kind of thing, and that's simply how it is.
Aaron Colleran
executiveIt's reassuring, or
David Coates
analystIt's reassuring to hear that you all are, at the very least, working your way through those. I guess it's about controlling whatever's within your control.
Aaron Colleran
executiveYeah. That's right. Yep.
David Coates
analystI'll leave it there, mate. Thanks.
Aaron Colleran
executiveThank you, David.
Richard Michael Adams
analystHey Aaron, fantastic results — nicely done.
Aaron Colleran
executiveThank you, Richard, and I appreciate your hanging on the call this long. There have been plenty of questions today, but
Richard Michael Adams
analystI meant to mention this during the past two calls—I think my timing on the buzzer was a little off.
Aaron Colleran
executiveNext time you'll be ready for it.
Richard Michael Adams
analystDan
Aaron Colleran
operatorMorgan doesn't waste any time. He reacts fast. The moment he calls in, he's likely hitting star one right away. That's right.
Richard Michael Adams
analystYes, I figured that hanging back might mean everyone else would put my questions forward. Look, I really just have a couple of questions.
Aaron Colleran
executiveFirst of all,
Richard Michael Adams
analystI was looking at the quarter before last — not the one that just ended — and you spent, I believe, 700,000, and then in this quarter you spent 900,000 on truck deposits. I think it said the combined total you've put down as deposits for trucks was 1.6 million. So I was wondering whether that's for Eloise, or whether it's in anticipation of Jericho?
Aaron Colleran
executiveWell, lead times are long right now, and the trucks get ordered a good 9 months ahead of delivery to site, and these are mostly for Jericho.
Richard Michael Adams
analystAll right. Through 1.7 — 1.6 million of deposits, how many trucks do we expect?
Aaron Colleran
executive3. 3. That I can verify, though my belief is 3.
Richard Michael Adams
analystOkay.
Aaron Colleran
executiveIt's normally about 300,000 a yeah.
Richard Michael Adams
analystAll right. Those would be loaders, specifically 60 t loaders, or
Aaron Colleran
executiveNo, they are the
John Callagher
executiveSixty-ton dump trucks.
Aaron Colleran
executiveDump trucks. Yes, dump trucks.
Richard Michael Adams
analystDump trucks, right. Okay. Then the second thing — there's been a fair amount of chatter about CopperString, and about Eva Harmony too, and about what's happening there, sort of fresh thinking around solar or wind for their new copper operation. CopperString really isn't, or at least doesn't sound like it's going to get anywhere close anytime soon. Would you consider perhaps something along the lines of what Eva is doing up north? Have you looked at that?
Aaron Colleran
executiveRichard, look, solar and batteries keep getting cheaper, potentially. Even so, it's not cheap yet, and financing it isn't easy either. CopperString — that's very hard. Absolutely, there are a lot of rumors going around that it will be delayed. There is no truth to that. CopperString is going to be fantastic. We need it. I think everybody in the region has a solid grasp of what CopperString offers and why it's necessary. CopperString is required in order to install these solar plants, since it also provides long-term offtake. As we all know, solar plants produce only in daylight; for us, the step change in costs is CopperString. Solar is what helps on the margin and with our greenhouse gas emissions. Yes, that's something we are examining. It is steadily looking more and more economic. Two years back we examined this, and again twelve months ago; back then it was simple to conclude that the figures simply didn't add up. At present, they're approaching viability—nearing the point of being positive. Right now we have a decent amount of capital in front of us even without factoring solar into that. The reason is that for a modest portion of your load, the capital expense of these systems unfortunately can't beat bringing a new diesel generator to site. Over the longer term, it's certainly something we'll examine more carefully. Take care when interpreting or comparing the power draw for Eva and Eloise. Eva is—what, not 10 times, but 6 5 6 times the scale. When it comes to power, those are next-level problems. Yeah. Yeah.
Richard Michael Adams
analystNo, I understand. No, I understand. If you could spare one more moment, near the end of your presentation, half an hour ago, you brought up the figure 25,000 tonnes per annum instead of 20 or 30. And 1.1 sounds like, sorry, a 1.1 plant sounds like 20, 21, 22, and a 1.5 sounds closer to 28 to 30. You said 25, so were you just hedging your bets, or why 25 rather than 28 to 30 or 18 to 22?
Aaron Colleran
executiveRichard, if you only knew the trouble this answer could land me in. I might
Richard Michael Adams
analystAll right. No, no, no,
Aaron Colleran
executiveRichard, I'm just teasing, since this topic gives us plenty of headaches. Whether you believe it or not, JORC complicates things a great deal when we try to give forward-looking production targets and production comments, because that can potentially land in capital P, capital T, production target territory. You have to jump through a whole lot of hoops before you can provide a capital P, capital T. That's where I'll begin. We don't have the JORC work ready for you, so we shouldn't be making those statements. Such statements are aspirational and might not come off. If we say 1.5 million tonnes, until we've released to you everything JORC requires us to release, that is purely an aspirational target. Yes, your numbers, multiplying out our current average grade, are correct. My figure sits lower than that since I run a lower grade through. As we increase the amount of dirt we're moving, that means we're increasing the amount of Jericho we're putting through. Jericho carries a relatively lower grade than Eloise. If you look closely, and I'm not trying to be smart, Richard, but if you look at our Reserve Statement, you'll see that today, of course, it's weighted towards Deeps and Lens 6. Roll that forward 3, 4, 5 years, and it won't be. It'll be weighted towards Jericho. Deeps and Lens 6, there's 2.4%, 2.6%, 2.8%, and Jericho 1.8%. That'll be the delta between the numbers I aspire to and the numbers that you've calculated, I think.
Richard Michael Adams
analystI suppose there's another distinction: most miners of your scale, if you have any comparisons, typically refer to copper equivalent, with silver and gold credits included, whereas you don't.
Aaron Colleran
executiveCall it stubbornness; it doesn't do us any favors, I suppose, but my view is that gold and silver are byproduct credits, and gold and silver are accounted for in our AISC. Were we to provide a copper-equivalent production figure, we should then provide a copper-equivalent AISC. That's just me being a pedant. Two things we do: we discuss only copper, and we always discuss estimated true width. A number of our flashier peers in the industry routinely emphasize copper-equivalent figures, and they inflate those numbers using methods that amount to pure trickery. They also never disclose the estimated true width of the intersections they drill. I could go on about this at length. Thanks, Richard.
Richard Michael Adams
analystNo, I believe one of those ran into a bit of trouble around 9:30 this morning, but regardless, I won't get into that either.
Aaron Colleran
executiveYeah, it's been a rough day for some people.
Richard Michael Adams
analystThanks once more. Enjoy a solid quarter. Thanks, Aaron.
Aaron Colleran
executiveCheers, Richard.
Aaron Colleran
executiveGoodness, Ashley, I hadn't even planned to deliver closing remarks myself. We've gotten through a handful of questions in half the time. This has been the lengthiest call we've ever had. Today we set a few records: revenue, plus our CEO rambling on. The March quarter was yet another strong one despite tough operating conditions. Eloise has a fantastic ore body and a fantastic crew running it; that much was obvious. Calendar year 2026 marks a transformative period for AIC Mines; our team is in place, our funding is in place, we've grown resources and reserves, and we're steadily de-risking Jericho. Copper, gold, and silver prices are supportive, to put it mildly. 2026 will be an excellent year for AIC Mines. There's no such thing as holding too much stock in AIC Mines. Thanks for joining us — that brings the call to a close.
Operator
operatorThat wraps up today's conference. We appreciate your participation. You can go ahead and disconnect now.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete AIC Mines Limited transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →This call discussed
For developers and AI pipelines
Programmatic access to AIC Mines Limited earnings transcripts and 132,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research