Applied Digital Corporation (APLD) Earnings Call Transcript & Summary
October 9, 2023
Earnings Call Speaker Segments
Alex Kovtun
executiveThank you very much, operator. Good morning to all of you, and thanks for joining Applied Digital's conference call for the first fiscal quarter of 2024. Before management delivers its prepared comments, we want to remind each of you that certain things we say today could be treated as forward-looking statements under securities laws, and those carry a range of risks and uncertainties. Consequently, we caution that numerous factors exist — many outside our control — that might lead actual outcomes and events to differ materially from what those forward-looking statements describe. For a more detailed picture of the risks, uncertainties, and assumptions tied to our forward-looking statements, please review the disclosures in our earnings release and in the public filings we make with the Securities and Exchange Commission. We disclaim any obligation or undertaking to update forward-looking statements so they reflect circumstances or events occurring after the date such statements are made, except as required by law; we will also discuss non-GAAP financial metrics, and we encourage you to read our disclosures and the reconciliation tables to applicable GAAP measures in our earnings release carefully as you consider these metrics. We point you to our filings with the Securities and Exchange Commission for detailed disclosures and descriptions of our business, along with uncertainties and other variable circumstances, including, but not limited to, the risks and uncertainties identified under the caption Risk Factors in our quarterly report on Form 10-Q. You can obtain Applied Digital's Securities and Exchange Commission filing at no cost by visiting the SEC website at www.sec.gov. I also want to remind everyone that this call is being recorded and will be available for replay through a link posted in the Investor Relations section of Applied Digital's website. Now I'll hand the call over to Applied Digital's Chairman and CEO, Wes Cummins. Wes?
Wes Cummins
executiveThanks, Alex, and good morning, everyone. I appreciate you all joining our conference call for fiscal first quarter 2024. First, I'd like to express gratitude to our employees for the hard work and service they continue to deliver in pursuit of our mission — supplying digital infrastructure solutions to the fast-expanding high-performance computing sector. Before I hand things to our CFO, David Rench, who will walk through our financial results in detail, I want to touch briefly on some recent developments in our business. Let's begin with the blockchain hosting operations we already have. Our goal is for all three blockchain hosting facilities to be fully online before long, delivering high reliability and performance for customers. Our 100-megawatt Jamestown facility is still performing as expected, running at full capacity with consistent uptime across the quarter. That makes the fourth quarter in a row the Jamestown facilities have run at full capacity. Our 180-MW Ellendale facility in North Dakota was fully energized and became fully operational in the first quarter of fiscal year 2024, and it contributed to our results this quarter. That facility is fully online and running with consistent uptime during the second quarter, which brings total hosting capacity to 280 MW across our North Dakota facilities — all contracted to customers on multi-year terms. In September, we signed a facilities extension agreement with Oncor covering transmission and metering of power for our Garden City, Texas, facility. With that agreement in place, metering and telemetry equipment owned by the power provider will be installed, and once that work is done, the site will be energized. Completion of this installation is expected by October 23rd. When our Garden City facility is fully energized, we will have roughly 500 MW of hosting capacity across our three facilities. We expect the three sites to generate about $300 million in revenue and $100 million in EBITDA on an annualized basis. Having all three facilities operational with high uptime will give us consistent cash flow, which supports our capital requirements for building out our HPC data centers and buying GPUs to serve our AI cloud customers. Now let's turn to our AI cloud services, launched this calendar year to deliver accelerated computing power for AI applications. Our AI cloud service keeps ramping up as we make further progress supporting existing contracts and chase additional opportunities in our pipeline. In July, we activated the first cluster of GPUs for Character.AI, and since then we have made meaningful progress, receiving our second cluster of GPUs in September, with additional GPUs expected to arrive this month. Since our last earnings announcement, we have added two additional AI cloud customers. Both have an established user base and are growing quickly. These customer agreements have a similar structure to our first two; they also include significant prepayments that fund a large portion of the capital requirements for purchasing the GPUs. That brings our total annual contract value of AI cloud services contracts at full capacity to approximately $378 million. Beyond the sizable prepayments that come in from customers, we're drawing on vendor financing and are actively looking into additional financing arrangements tailored to our needs, all to meet the capital needs tied to the 34,000 GPUs we've ordered in support of our cloud service. Delivery of most of those GPUs is still expected by April of next year. Through our existing relationships with top OEMs such as Supermicro, Hewlett Packard Enterprise, and Dell, together with the Elite partner status we recently obtained in NVIDIA's partner network, we gain visibility into the delivery schedule, which ensures we receive these GPUs on time. As noted earlier, we'll initially deliver this service out of our 9-megawatt HPC Jamestown facility, plus third-party colocation space, while we keep moving forward on executing the element of our dedicated next-gen HPC data centers. The opportunity pipeline for our AI cloud service business continues to be strong. We're eager to capitalize further on this opportunity and to share more updates about our newly signed customers as we move ahead. Finally, a brief update on our purpose-built HPC data centers: we have 300 MW of capacity under development and have started initial groundwork at our Ellendale facility. To move ahead with construction of these facilities and to obtain the financing required, we are in the process of securing a credit-rated anchor tenant. We've been actively holding ongoing discussions with multiple potential anchor tenants for our Ellendale and Utah facilities. As with our new customers for our AI cloud service, we'll share more information once it's available. Our goal is to secure an anchor tenant customer for each facility and to have those facilities fully energized and operational within the next 24 months. With that, I'll now hand the call over to our CFO, David Rench, to walk you through our financials and give an update on guidance before I provide my closing remarks. David?
David Rench
executiveThanks, Wes, and good morning to all of you. Revenue in the fiscal first quarter of 2024 came in at $36.3 million, versus $6.9 million in the fiscal first quarter of 2023. Growth in hosting revenues resulted from added online capacity, since our Ellendale, North Dakota, site is now operational, along with revenue from the company's first AI cloud service contract, which started during the three months ended August 31, 2023. Cost of revenues in the fiscal first quarter of 2024 was $24.4 million, versus $6.1 million in the fiscal first quarter of 2023. Higher costs reflected greater energy costs used to produce hosting revenues, depreciation, amortization expense, and personnel expenses for employees working directly at our Jamestown and Ellendale hosting facilities. Operating expenses in the fiscal first quarter of 2024 totaled $17.1 million, versus $5 million in the comparable prior-year period. That rise came mainly from personnel-related costs driven by higher headcount, together with an increase in depreciation. Net loss in the fiscal first quarter of 2024 was $9.6 million, or a loss of $0.10 per basic and diluted share, on a weighted average share count for the quarter of roughly 100.5 million; that compares with a net loss of $4.7 million, or a loss of $0.05 per basic and diluted share in the fiscal first quarter of 2023, on a weighted average share count for the quarter of roughly 93.1 million. Adjusted net income, a non-GAAP measure, for the fiscal first quarter of 2024 was $0.1 million, or adjusted net income per basic and diluted share of less than $0.01, on a weighted average share count for the quarter of roughly 100.5 million. That compares with an adjusted net loss, a non-GAAP measure, of $3.4 million, or a loss of $0.04 per basic and diluted share for the fiscal first quarter of 2023, on a weighted average share count for the quarter of roughly 93.1 million. Adjusted EBITDA, a non-GAAP measure, for the fiscal first quarter of 2024 was $10 million, versus an adjusted EBITDA loss of $1.9 million in the fiscal first quarter of 2023. Finally, on the balance sheet, we closed the fiscal first quarter with $31.2 million in cash, cash equivalents, and restricted cash, plus $44 million in debt. In the fiscal first quarter of 2024, we collected $39.5 million in customer payments, reflecting how our commercial arrangements with customers are structured, with upfront deposits and prepayments. Under certain contracts, those prepayments are amortized back to the customer across the first year of their contract, with no effect on revenue recognition; however, the cash flow timing, with cash coming to us upfront, is a major benefit for the company and supports our CapEx funding needs as we build out our data centers. Since the quarter ended, we've received another $15 million in customer prepayments, and we expect a further $23 million this week. Now, moving to guidance for the full year of fiscal 2024, we're reaffirming our expectations for revenue in the range of $385 million-$405 million, and Adjusted EBITDA in the range of $195 million-$205 million. Now I'll hand the call over to Wes for closing remarks.
Wes Cummins
executiveThanks, David. Looking forward, our confidence stays strong in the competitive edges and distinct capabilities we bring to satisfying the complex, rigorous needs of businesses and enterprises running AI workloads along with other emerging HPC applications. I continue to feel optimistic about what lies ahead for Applied Digital as we strengthen our position as a leader in next-generation digital infrastructure serving both blockchain and non-blockchain HPC use cases throughout this period of digital transformation. I want to express appreciation to every one of our team members for the commitment that has made Applied what it is today, and to our shareholders for placing their trust in our mission and in how we execute. At this point we're glad to take questions. Operator?
Rob Brown
analystGood morning.
Wes Cummins
executiveGood morning, Rob.
Rob Brown
analystMy first question concerns what you're doing with anchor customers in the AI business. I realize you can't share too much detail, but perhaps some sense of how big the center is. Do they have to fill an entire center before you begin? And how does that scope out before you actually reach the decision to start a data center build?
Wes Cummins
executiveYes. So, I believe we've discussed this previously, and nothing has changed: we figure we must contract approximately 70% of the capacity. It doesn't need to be a single customer, but we believe we have to contract that on a sensible, let's say, 8 — you know, 7 to 10-year contracts, with renewals, in order to start construction, and we're currently in the process of securing that. But Rob, the way I look at these is starting roughly 100 MW in North Dakota soon, then following with a 100 in Utah, and then returning, you know, around mid-next year for the second 100 in North Dakota.
Rob Brown
analystAll right, great. Great. And then when it comes to ramping the AI business, it hinges on getting the GPUs, you know, delivered. How do you see that ramp-up of the GPUs you've ordered? How do you see those arriving, in terms of your ability to scale up that business?
Wes Cummins
executiveYeah. We — I think at this point, we have pretty good visibility into delivery schedules. It's improved since our last call. As I said in the prepared remarks, we got our second cluster in September. We expect more this month and really expect to begin receiving large volumes in November, December, and January.
Rob Brown
analystAll right, that's great. Thanks. I'll hand it over.
Analyst
analystMorning, everyone. Adam here, filling in for George. Wes, to begin with Garden City, could you give us some added color on how quickly energization will proceed after Oncor finishes installing its equipment?
Wes Cummins
executiveYeah, absolutely. The date referenced in our prepared remarks and in the press release is when we expect everything to be set for energization. Energizing should begin that day, and from there the ramp ought to move more quickly than what we saw at our North Dakota facilities, where we kept finishing buildings and bringing them online. It will still take weeks to energize, though it won't stretch into the months we experienced at both Jamestown and Ellendale, since all the construction is done, the miners are racked and set to switch on, so the process should be considerably quicker; as a result, sometime around November — mid- to late November — it should be fully online, following that late October start on the 23rd.
Analyst
analystGreat, thanks. I've got one more follow-up question. Regarding the construction work currently underway, are there any milestones you must reach before you run into harsher weather?
Wes Cummins
executiveYes, in North Dakota, we've begun the groundwork there, and it's fairly similar to what we did last year — it'll be a bit of a scramble to get the foundations poured so we can keep working through the winter, get the facility enclosed, and continue through the winter there. So that's what we're focused on at the moment.
John Todaro
analystGreat, thanks for taking my question, guys. I've got one here about the Sai Computing business, and I'm just trying to understand — first off, congrats on adding a few more contracts. So what kind of capacity is out there? Can we add more contracts right now, or are you looking to get those HPC sites on and anchor tenants there? I'm just kind of wondering how much capacity there really is, and whether we can expect any more contracts to come online.
Wes Cummins
executiveYes, we do have additional capacity available — though not a great deal — until such time as we begin bringing our own facilities online. Okay, John, let's go through the math for the site compute business. Roughly speaking, each 1,000 GPUs brings in about $1.5 million in monthly revenue. We've discussed before getting to 26,000 by April, and that takes you to what you could call a $460 million-plus annual revenue business. From April onward, we'll be aiming to place capacity in our own facilities; so during that April ramp, we have our Jamestown facility, and we've also secured third-party colo to support the ramp, and after that we're looking to put additional deployments into our own facilities.
John Todaro
analystUnderstood. All right, that's helpful, thanks. Then I suppose it's also about the timeline — when you raised the count from 26,000 to 34,000 GPUs, was there any signal from the suppliers? Did it look clearly achievable, or, you know, how hard is it to secure that? I know you've said you're tracking it, but more detail there would be useful.
Wes Cummins
executiveYes. We expect those to be deployed after April of next year. We included them because, again, of the demand pipeline we're seeing. You should think of them as coming in after April. The 26 we discussed on the prior call get added through April, and then the extra, you know, 8 get added afterward. I'd, you know, keep thinking of it as — it's 8 at present, but we'll see how demand comes through. Should we need to expand that, our own data center capacity ought to be coming online to support it.
Darren Aftahi
analystAlright, understood. Thanks for that. I appreciate it.
Wes Cummins
executiveYep.
Lucas Pipes
analystMuch appreciated, operator. Morning to all of you. I'll start with guidance: given the holdups at Garden City, ought we to view the EBITDA and revenue contribution as having moved over to AI Cloud to a greater degree? Thanks a lot for taking me through those changes.
Wes Cummins
executiveYes. Lucas, thank you for that question. So, taking into account what I just mentioned regarding the AI cloud, you can sort of trace how GPUs get deployed and how that increases over the course of the year—though it will be a reasonably sharp ramp, particularly in our final two quarters as those units come online. We will receive the deliveries. We had a September delivery, additional ones arrive in October, and then deliveries, I believe, really accelerate for us in November and December, plus somewhat into January. So as those become operational, you will observe a quite steep revenue ramp in the cloud business over the rest of the year, which ought to compensate for the delay we have experienced in Garden City.
Lucas Pipes
analystThanks, Wes. Regarding HPC, since a lot of the planning is done from what I understand, could you take us through the capital intensity? On financing, what debt-to-equity targets do you have right now? Would project financing cover most of the capital needs? I'd appreciate your thoughts on that. Thank you.
Wes Cummins
executiveYes, absolutely — and regarding the data center business, we'll cover that thoroughly on Thursday, but I believe many of you have already seen it, so we redesigned the data center using what we know today. What we constructed in Jamestown — the first build we discussed — was single level and horizontal, since that approach costs the least. We have lots of land in North Dakota, so the plan was simply to extend it horizontally as far as we liked. Now that we understand how these workloads operate and that they need to be much denser and positioned nearer the network core, we changed our design to a three-story structure with a network core running down the center, allowing far greater density, particularly for training and to some degree for inference. With this new design, you should be thinking — we previously mentioned roughly $4 million-$4.5 million. We're now looking at closer to $6 million-$6 million per megawatt to construct those facilities. We believe that, given the work completed, we can reach approximately 80% loan to cost for construction; it resembles a data center much more closely now. So once we secure that tenant or tenants with credit ratings, we can arrange the construction financing. There is also an equity piece, though we refer to it as site-level equity, and you can bring in financing partners for that equity portion too — we've devoted considerable time to conversations with them. In the data center sector, it's typically termed equity financing. Again, it's at the site level, but I view it more as what the capital markets would call mezz debt. So we're working through every element of the capital structure to finalize things and begin the first build in North Dakota. I suppose, technically, Lucas, it isn't our first build; it's the first build of this particular design.
Lucas Pipes
analystGot it. Got it. Thanks so much, Wes. I'll attempt to fit in one more. Regarding the 34,000 GPUs now compared with 26,000 GPUs before, would those tie to the extra two customers you announced, or are there other factors at play?
Wes Cummins
executiveThere are also some other elements in play here. It really ties more to the demand that we keep seeing. Demand in this area has not slowed for us. I think if you, you know, take a look across the industry, capital raising hasn't slowed down either. There was, you know, a sizable deal, I believe, that was announced with Anthropic last week involving AWS. But we're still seeing, you know, a robust funding environment for the companies that will become customers of ours. We see solid demand, really powerful demand in our pipeline, and so it's really just a call made on the basis of what we're observing from a demand standpoint.
Lucas Pipes
analystAll right, that's really useful. Thanks for that, and I want to wish you and the team the very best of luck.
Wes Cummins
executiveThanks, Lucas.
Darren Aftahi
analystMorning, all. Appreciate you taking my questions. Wes, I'd like a bit more detail on the timing of the GPU orders, if you don't mind. Just curious. You referred to month by month for September and October — are those numbers higher than that first 1,000 order? And what makes the ramp climb so sharply into November, December, and January, going by what you said? Is it purely a backlog situation? And how sure are you that it won't slip further into 2024?
Wes Cummins
executiveYeah, fair question, Darren. In September, our second cluster of 1,024 GPUs was delivered. Come October, we expect that figure to double, then grow considerably larger across November, December, and into January. This all stems from orders we placed around May that are now starting to arrive. Deliveries come in small batches, following the schedule we've been provided for when they'll land—essentially between now and the close of the calendar year. That's the basis for our confidence in these deliveries. Could some of it slip? Sure, it could still occur, I guess. But it looks like—let me try to recall the timing—perhaps around three weeks back, or maybe a bit more than that, our suppliers gave us a somewhat more solid delivery timeline. So we feel fairly confident about our deliveries. I think it mostly comes down to when we placed those orders and when they’re going out, plus how that pace picks up across the coming three months. I’m not sure. Whether the industry overall has better supply, or if this is something specific to us — that's not really for me to judge, and I honestly don't know.
Darren Aftahi
analystThat's useful. Thanks; and then only one more from me. Regarding the anchor tenant with HPC, are there several tenants you're in talks with? And I suppose when it comes to fitting people in, I mean, how near are we to North Dakota compared with Utah? And then I'd assume your data center financing probably follows right after that, based on what you said earlier. So if you could just sort of go through... I'm only trying to get a sense of anchor tenant demand versus the capacity you have, and then the longer-term plans. Thanks.
Wes Cummins
executiveSure; so we're seeing plenty of interest; these conversations have been going on for a few months now, and then in the first week, at the end of the first week of September, our design was finalized; and so from that point until now we've been in what I'd describe as a formal marketing process. And we'll take that into an LOI stage and after that into a contracting stage over the next, you know, few weeks or month; so that's what we expect, but that's roughly how it has come together — it really began a formal process in, call it, mid-September, and we're hoping to wrap that up, you know, in the coming weeks. But interest is high, and we'll cover this in more detail on Thursday; but, you know, it's demand for this style of data center at this type of density, because we've been both out securing colocation space for ourselves on the cloud side and then speaking with potential customers on this, on the data center side, about building our own. We're seeing, you know, an enormous amount of demand, and really demand for power that is available and capacity that can come online, you know, over the next 24 to 36 months.
Darren Aftahi
analystThanks.
Mike Grondahl
analystHi, guys. Appreciate it. I've got a couple of questions. First one is about possible anchor tenants. Would you say the potential anchor you plan to announce in the near term is still pretty much wide open — meaning there are still multiple 5, 6, 7 big potential anchors out there that you're talking to? Or have one or two sort of moved way down the funnel, and you're just finalizing who it might be from a very small group?
Wes Cummins
executiveSo, Mike, I'd say we're right in the, I'd say, middle of the two scenarios you described. So the funnel has gotten smaller, but we're not right at the end yet. Does that... If that makes sense.
Mike Grondahl
analystUnderstood. Yeah, I'm just trying to get a clearer picture. Then regarding the prepayment, you said $39.5 million for the August quarter, and then I believe a $15 million prepayment plus a $23 million prepayment that you expect this week. Could you clarify whether the $15 and the $23 come from customer 3 and 4, or do they tie back to customer 1 and 2?
Wes Cummins
executiveBoth. Those prepayments cover both. The ones we've already received that we discussed, and then the one—or ones—we expect to get this week.
Mike Grondahl
analystUnderstood. Understood; and then last of all, those 1,024 GPUs in August that you put into service — did every one of them go to customer one?
Wes Cummins
executiveActually, Mike, those arrived in September, and they belong to Customer One.
Mike Grondahl
analystOkay. Hey, thanks, guys.
Wes Cummins
executiveYep.
Kevin Dede
analystHey Wes, thanks for fielding this. So I wonder if you could walk me through a bit more how you see AI cloud compared with AI host, and how each of those plays into your thinking—your construction calculus.
Wes Cummins
executiveWhat do you mean by that, Kevin?
Kevin Dede
analystSo I suppose my question is this: whenever you're searching for your anchor tenants, do you consider them strictly through a cloud customer lens, or do you maybe consider them through a host lens, in which they supply their own GPUs?
Wes Cummins
executiveYeah, yeah; so for us, anchor tenants are definitely a hosting business, and they'll bring their own equipment. For us, it's simply a data center hosting business. When you think about anchor tenants and for these data centers, you know, we've discussed the concept being, you know, 70% goes toward the colocation hosting style business, and then, you know, we retain 30% for our own cloud capacity.
Kevin Dede
analystYou mentioned you're at ease pursuing the colocation capacity required to back the 26,000 to 34,000 GPUs that are on the way. How do you plan to relocate them from that colocation into your own facilities once those are ready?
Wes Cummins
executiveWe will never relocate those installations. From a cloud service standpoint, the way I look at it is that much of that colocation sits in what I'd describe as traditional cloud regions; and as we scale capacity up in North Dakota, that capacity is genuinely being constructed for very large training clusters. So in my mind, the training part of the business that's being deployed in smaller training clusters across those cloud regions shifts onto the infrastructure that gets stood up in North Dakota, and then the smaller clusters we're building out right now get used for inferencing. Which, I think, is how this market divides: there'll be training and batch inference, and then a certain amount of inferencing happening in these large facilities such as the ones we're building in North Dakota. And then much of the inference share of the market will sit more in what I'd call traditional cloud regions; so over time it suits our cloud business well to have that kind of architecture, simply being spread across more cloud regions for the inferencing side of the business, while a great deal of the training migrates into North Dakota.
Kevin Dede
analystAlright. Wes, that redesign you carried out in September for the new Ellendale facility — did latency have to be rethought, or was power backup the bigger concern on those? Or do you figure you can still run things under the same conditions you built for in Jamestown?
Wes Cummins
executiveNo, so it's, it isn't really about latency or power backup as such; it's about... It was redesigned specifically with density in mind; the idea is basically to take a network core and run it through multiple floors and place all of the GPUs. So the design for this new North Dakota facility really centers on, you know, kind of this magic number of, I call it 30 meters, that being the magic number for how far, you know, a rack can sit from the network core and still be, you know, in the same cluster, same spine for networking. Technically, Kevin, you can go out to 50 meters from the network core, but then you have to use a single-mode transceiver on optics rather than multi-mode, so it becomes more expensive, a little harder. So it's, it's really built around how many racks and how many servers we can fit within 30 meters of the network core, and, and that's the reason it goes through multiple levels in the building instead of the single level. That's the main piece of the redesign.
Kevin Dede
analystBut what about the heat side of things — if you've got several racks stacked together, right, and heat naturally rises?
Wes Cummins
executiveYes, so this is a liquid-cooled facility. That's the other piece of the redesign; the original was air-cooled. In our view, you can realistically use air cooling up to roughly 50 kW per rack, you know, call it about that. Once you go beyond that point, though, a liquid cooling approach is really what you need. So the new facility is built for liquid cooling. The new facility will reach 150 kW per rack. It still, it still has enough floor space to run at 45 kW, which is what we're doing in Jamestown. But, but we've — this one will be constructed for liquid cooling.
Kevin Dede
analystAll right. Thank you, Wes. I appreciate that. Thanks for the thoroughness.
Wes Cummins
executiveYes. Of course.
Wes Cummins
executiveAppreciate it, operator, and thank you all for being with us today. We're looking forward to talking with you this Thursday at our Investor Day, set to take place in Midtown Manhattan. Once more, our thanks go out to every one of our employees for what they contributed during the previous quarter and through this quarter so far. We look forward to connecting with you on the following quarterly call.
Operator
operatorThanks. Appreciate everyone being here today for Applied Digital's conference call. You can go ahead and disconnect now.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Applied Digital Corporation transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →This call discussed
For developers and AI pipelines
Programmatic access to Applied Digital Corporation earnings transcripts and 132,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Applied Digital Corporation or any ticker on your watchlist.
StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.