executiveOperator, thank you. Greetings to all, and thank you for joining Applied Digital's conference call for the second quarter of fiscal 2024. Ahead of the formal remarks from management, we'd like to note for everyone that some of what we say today may qualify as forward-looking statements under securities laws, and those come with various risks and uncertainties. Because of that, we advise you that there are numerous factors—many beyond our influence—that might cause actual results and events to diverge significantly from the descriptions in those forward-looking statements. If you want a fuller picture of the risks, uncertainties, and assumptions tied to what we've said about future results, you can find them laid out in our earnings release and in the documents we file publicly with the Securities and Exchange Commission. We're not taking on any duty, and we're not committing, to revise those forward-looking statements if things change or events happen after the date they were made — unless the law says we have to. We'll also be going over non-GAAP financial measures, so when you're weighing those numbers, please take a close look at our disclosures and the reconciliation tables, along with the corresponding GAAP figures in our earnings release. For in-depth information about our operations, plus the various unknowns and shifting conditions we face—among them, though not exclusively, the hazards and ambiguities laid out in the Risk Factors section of our Form 10-Q quarterly report—we point you toward the documents we file with the Securities and Exchange Commission. Anyone can obtain Applied Digital's SEC submissions at no cost through the agency's site, www.sec.gov. A further note: this call is being captured and a recording will be accessible through a replay link posted in the Investor Relations area of Applied Digital's website. At this point, I'll hand things over to Applied Digital's Chairman and CEO, Wes Cummins. Wes?
Wes Cummins
executiveThanks, Alex, and good morning to all of you. I appreciate everyone joining us for the fiscal second quarter 2024 conference call. First, I'd like to express gratitude to our team members for the continued dedication and effort they bring to advancing our mission — delivering digital infrastructure solutions to the fast-expanding high-performance computing sector. Before I hand things over to David Rench, our CFO, who will walk through our financial results in detail, I want to cover a few recent items from across the business. Let's begin with data center hosting. Our Jamestown facility, at 100 megawatts, is still performing the way we anticipated, running at full capacity with steady uptime all quarter long. That makes it the fifth quarter in a row that Jamestown has run at full capacity. Our Ellendale facility — 180 megawatts, located in North Dakota — likewise ran at full capacity with steady uptime during the quarter, which brings total hosting capacity at our North Dakota sites to 280 megawatts. Multiyear contracts cover both of those facilities with our customers. During the quarter, we shared news of the initial energization at our Garden City facility in Texas, which is 200 megawatts; that represents an important milestone for Applied Digital as we work to satisfy rising demand for scalable, low cost digital infrastructure. Garden City contributed a modest amount to our results this quarter and currently runs at roughly 132 megawatts, while the rest of its capacity should come online over the next several months. As we brought the facility up, we identified additional infrastructure improvements the grid required. Those improvements should be completed by no later than April. Customers keep sending miners to the site, and we are installing them actively. With bitcoin's price rising, we're seeing demand for hosting services climb substantially. Keep in mind that fixed prices fully cover our Garden City facility, so crypto market swings ahead of this year's halving event don't affect us. When Garden City reaches full energization, hosting capacity across our three data center hosting facilities will total roughly 500 megawatts. We anticipate those three sites generating as much as $300 million in revenue and $100 million of adjusted EBITDA on an annualized basis. Operating cash flow from data center hosting services will increase considerably in March, since most of our prepayments burn off in February. Now let's turn to cloud services, which deliver high-performance computing power mainly for AI applications. That segment is expanding rapidly as we continue supporting existing contracts and chase further pipeline opportunities. Since we last reported earnings, we've signed one more cloud customer, taking our total annual contract value of cloud service contracts at full capacity to around $398 million. We structure our agreements around each customer, so that — as they raise money, we can exercise options embedded in the contract to deploy GPUs and ramp-up hosting capacity over time. Historically, the bulk of demand for our cloud offering has come from venture capital-funded private firms, but we're now witnessing robust interest from enterprise buyers seeking substantial GPU compute resources. This growing appetite from such a key market segment has us enthusiastic, and we intend to bring on sales personnel to strengthen our outreach; meanwhile, we keep locking in GPU supply, though certain installation setbacks have occurred because networking component shipments are still pending; our view is that it makes sense to accept GPU shipments only once every related piece of equipment has arrived on-site and is prepared for setup, which mirrors how we handle customer deposits. In addition, we're persistently investigating vendor financing along with other customized financing arrangements to meet the capital needs tied to the 34,000 H100 GPUs we've ordered to serve existing client demand. As of now, 4 clusters of 1,024 units each are up and running, and we plan to deliver another 4 within the coming fortnight. In their present configuration, these clusters place us among an elite group of next-generation supercomputers when measured by raw compute power, or petaflops, for the toughest AI tasks. We anticipate hitting at least 10 prior to the close of the fiscal year, with the Jamestown cluster presenting the chance to rank us within the top 10 supercomputers for AI workloads. Once fully operational, the clusters should produce more than $200 million in annualized revenue. Finally, an update on our purpose-built HPC data centers. This quarter, we commenced construction on our inaugural 100-megawatt high-performance compute site in Ellendale, North Dakota. This site is set to provide inexpensive, highly efficient liquid-cooled infrastructure tailored for HPC uses. Building is moving forward on schedule. Our distinctive proprietary architecture and design approach, combined with positioning the Ellendale site close to plentiful renewable energy sources, will deliver scalable infrastructure for these workloads. It will bring considerable cost savings to our clients and achieve top-tier performance that optimizes high power density computing. We think this edge is maintainable within this nascent market for data centers built specifically to run AI workloads. Our secured power and adjacent land at our sites are poised to turn into precious assets within the coming 18 months. We anticipate a notable shortage in power supply across the data center sector. Demand for our data centers has already proven strong, surpassing our original projections thanks to the expanding AI sector. We're confident we'll hold a robust competitive stance to meet this demand. As a quick note, we have 400 megawatts under development spanning North Dakota and Utah; that figure leaves out the existing 9 megawatts at our standalone Jamestown site serving cloud service clients. Now that we're moving into the latter portion of fiscal 2024, we're set up nicely to take advantage of the demand we see in both our cloud service and HPC data center operations, and we'll keep directing our capital in the right way toward the best risk-adjusted returns so shareholder value is maximized. With that said, I'll hand things over now to our CFO, David Rench, so he can take you through our financials and give an update on guidance. David?
David Rench
executiveAppreciate that, Wes, and hello everybody on this morning's call. Revenue for the second quarter of fiscal 2024 reached $42.2 million, compared with $12.3 million during the same period in fiscal 2023. The increase was driven largely by a complete quarter of revenue production from Ellendale, Garden City beginning to bring in revenue in Q2 of fiscal 2024, and additional revenue at Jamestown resulting from better uptime. Beyond those factors, the company also recorded a full quarter's worth of revenue in Q2 of fiscal 2024 from its first cloud service contract. For the second quarter of fiscal 2024, cost of revenues came in at $29.2 million, up from $11.8 million in the same quarter of fiscal 2023. The increase was driven by greater energy expenses tied to producing hosting revenues, along with depreciation and amortization, plus added personnel costs, reflecting expansion of the business and the energizing of additional facilities. Selling, general, and administrative expenses totaled $21.1 million in the fiscal second quarter of 2024, versus $27.2 million a year earlier. The decline was mainly due to reduced stock-based compensation expense, though it was partly offset by higher depreciation, amortization, and personnel costs. For Q2 of fiscal 2024, we recorded a net loss of $10.5 million. That works out to a loss of $0.10 per basic and diluted share, with roughly 109.7 million shares as the weighted average count for the quarter. In last year's fiscal second quarter, which ended in 2023, the net loss came to $26.8 million, equal to $0.28 per basic and diluted share, when the weighted average share count was about 93.4 million. Turning to adjusted net loss, which is a non-GAAP figure: for this year's fiscal second quarter it reached $5.2 million, or an adjusted net loss of $0.05 per basic and diluted share, again using a weighted average share count of approximately 109.7 million for the quarter. During the second fiscal quarter of 2023, our adjusted net loss came to $3.8 million, equal to $0.04 for both basic and diluted shares, with roughly 93.4 million shares as the weighted average count for that period. In the second fiscal quarter of 2024, one notable obstacle involved amortization plus occupancy costs tied to leases for computing equipment and data center space that the company has accessed yet which do not generate revenue at this time. Expenses from leases at colocation sites that aren't producing revenue amounted to $1.5 million, and those figures were excluded from adjusted EBITDA as well as adjusted earnings. Depreciation on graphics processors that weren't generating any revenue came to $3.7 million, and that figure wasn't included when we calculated adjusted earnings. As we work through supply chain holdups and get complete computing clusters up and running that do bring in revenue, we anticipate this effect will shrink in upcoming quarters. For the fiscal second quarter of 2024, adjusted EBITDA — a non-GAAP metric — reached $10.6 million, whereas the same quarter in fiscal 2023 saw an adjusted EBITDA loss of $2.2 million. To finish on the balance sheet: when our fiscal second quarter ended, cash, cash equivalents, and restricted cash came to $34.6 million, and our debt was $42.8 million. Across the opening two quarters of 2024, customer payments came in at $81.8 million, which stems from how our commercial agreements are structured, including upfront deposits and prepayments. Under some contracts, those prepayments get credited back to customers across the contract term. Revenue recognition is unaffected by this, yet the upfront cash flow represents a significant advantage for the company, since it supports our CapEx funding as we continue building out our data centers. Following the quarter's end, we've brought in another $11.1 million in customer prepayments along with $23.1 million in net proceeds from the ATM offering. That ATM offering has now wrapped up. Moving to guidance: because delivery of certain networking components for our GPU clusters was delayed, we now anticipate revenue and EBITDA landing beneath the low end of the range we previously guided for fiscal year 2024. Deliveries of network components have picked up over recent weeks, though the timing of commissioning clusters — and therefore our revenue and EBITDA — took a meaningful hit. For fiscal year 2024, we now expect to exit at an annual revenue run rate of roughly $500 million, with an annualized adjusted EBITDA run rate of $250 million. At this point, I'll hand the call to Wes for closing remarks.
Wes Cummins
executiveAppreciate that, David. We're set up nicely to take advantage of the expanding opportunities throughout our business, and we're eager to keep building on our momentum as we move through the second half of the year. I want to express my gratitude to every one of our team members for the commitment they've shown in shaping Applied into what it is today, as well as to our shareholders for the confidence you keep placing in our mission and in how we execute. At this point we're glad to open things up for questions. Operator?
Lucas Pipes
analystThanks a lot, operator. Morning, everybody. My first question concerns the HPC hosting side, that conditional agreement you announced, and a handful of others. To start, regarding the overall value you mention there, should we basically be thinking about $220 million of revenue each year? And then, on the capital cost side, are your margin expectations for the segment still near 40%? I've been using the $5 million per megawatt assumption. I was curious whether that remains a solid figure to apply. Many thanks for your details.
Wes Cummins
executiveMorning, Lucas. Thanks; so beyond what we announced, there isn't much additional detail I can provide, but let's discuss the cost. I believe we mentioned during our shareholder — at Analyst Day, and the Shareholder Day, that cost is heading toward $6 million to $7 million per megawatt rather than the $5 million as we've progressed through the new design. So that $5 million applied more to the earlier design, whereas this is the three story design we're currently working on. So that's where we stand. As for economics, though, this aligns with the economics we've discussed before, correct, which is roughly $2 million per megawatt in revenue and $1 million of EBITDA per megawatt.
Lucas Pipes
analystUnderstood. That helps a lot, thanks. Now, if we look at guidance briefly — regarding those components that got pushed back, what was the actual source of the hold-up? Can you give us a bit more detail there? Also, I believe you gave some information earlier about GPUs online for the typical physical Q3 and Q4. I think you touched on it during your prepared remarks, but I was jotting things down and fell behind, so if you could share an outlook regarding Q3 and Q4 GPUs, I'd welcome the detail on all of that. Thanks.
Wes Cummins
executiveOf course. The components causing the delivery problem aren't the GPUs. They're particular networking components tied to the InfiniBand networking portion of the cluster. I've discussed this a number of times now, and this has been the constraint, I'd say, across roughly the past 3 or 4 months. Deliveries of those are coming in. The trick is ensuring every single component arrives, since you require all of them to stand up the cluster, commission it, and get it running for customers. So we're seeing progress on InfiniBand deliveries. The issue has been specifically on the transceiver side of the InfiniBand deployments. We had 1 cluster up and running last quarter. We now have 4 deployed. As I mentioned in my prepared remarks, we anticipate receiving another 4. And regarding the cluster — just to remind you, Luke, that's the cluster for us. I realize it can be somewhat confusing, but we refer to it as 1,024 GPUs per cluster. So our expectation is that we'll receive another 4 within the next 2 weeks. Also, consider where pricing has moved for us on these clusters. You should think of it as $20 million in annual revenue for each cluster deployed. So our problem is really just a matter of a few weeks, since at present, let's say we're running roughly 8 weeks behind what we originally expected. But if you consider the revenue ramp and how revenue is generated week by week, we move from 1 cluster — so we're producing $20 million in revenue per year from that cluster — to our business reaching 4 clusters, which equals $80 million in revenue per year; and then within a few weeks, our business reaches 8 clusters, which equals $160 million in revenue per year. So in looking at our guidance, we're simply assuming 10 clusters deployed by the close of our fiscal year, which is May, roughly 4.5 months from now. And so those 10 clusters plus our blockchain hosting solutions get us to that $500 million run rate. I believe we can exceed that, but that's the figure I consider a very conservative one for us to reach by the end of the year.
Lucas Pipes
analystThat's quite useful. Thanks, Wes, for all the detail. Just one quick thing — the $45.8 million spent year-to-date on property, equipment and other assets: can you break that figure down between HPC and GPUs? Thank you.
Wes Cummins
executiveSorry, Lucas, which figure do you mean? The year-to-date purchases?
Lucas Pipes
analystRight, that figure reflects the property and equipment acquired up to now.
Wes Cummins
executiveMost of that is allocated toward HPC. Consequently, if you check our balance sheet — when reviewing our balance sheet, the GPUs appear there, given the way we finance those GPUs, as the lease asset, the right to use asset.
Lucas Pipes
analystAll right.
Wes Cummins
executiveMoving on, on the liability side a capital lease will show up. Something I'd point out here is that regarding the leases, when we deploy the GPUs, the whole right to use asset lands in long-term assets, but the lease liability gets divided roughly 50/50 between long-term liabilities and short-term liabilities. So as you look through the balance sheet, the leases at present — since what we're doing is what I've always called equipment finance — these are capital leases. That's the way we're financing the GPUs. So looking through CapEx, most of what shows up is CapEx on equipment, meaning the HPC facility, the data center. And then the GPUs appear in the lease right to use, the capital leases, and the liabilities.
Lucas Pipes
analystThat's quite useful. Wes, I appreciate all the detail, and I wish you the best of luck.
Wes Cummins
executiveSure thing. Thank you, Lucas.
George Sutton
analystThanks. It's wonderful to see the conditional agreement. I was just curious whether you might take us through the financing side at the project level and how, in your thinking, these pieces ultimately fit together? Does it involve a mix of construction loan financing plus project financing? And do you have any read on the market dynamics there that we ought to be aware of?
Wes Cummins
executiveYes. Appreciate it, George. I've discussed this in public previously. So the manner in which these agreements work — we've been marketing this since the middle of September. And as you consider this, you ought to consider marketing. Our potential customers do considerable due diligence on the site. You respond to a large number of questions, host site visits, everything else you'd anticipate during due diligence. After that you'll usually enter a ROFR period, a right of first refusal period, during which one party receives exclusivity such that you won't sell it to anybody else. I'm not discussing our particular agreement right now, I'm merely describing how we've seen this operate. Then you push toward a contract. Once the contract is in place, you move to project level finance. We are in discussions with several parties regarding the project level finance side. We have been for some time. We haven't — we're not sitting around waiting. We weren't sitting around waiting for an agreement before going to project level finance. But regarding project level finance, you'll receive roughly 65% to 80% loan to cost at the project level. So this won't be at the corporate level. It happens down at the site level, exactly as we've done across all of our Bitcoin sites. After that comes what we term the equity component, which, as I always view it while we work through this, is more of a — folks in our industry would call it like mezz debt; so you've got the construction finance, and that debt carries roughly a 7.5% to 8% type cost range. Then you've got the mezz piece, the equity piece. Then you've got our contribution, and with our contribution, we can continue construction — we broke ground and continued construction at the Ellendale site, and we've already invested a substantial amount of money there; so I believe we're near where we'll need to be regarding the equity portion of that. The rest will arrive from project level finance and then this mezz debt piece, where typically a party will receive roughly a high — mid to high teens return on their capital, and it's typically first money out and then perhaps keeps a small ownership stake, say 4%, 5% — 3%, 5% in the site itself. So that's the process we're currently in.
George Sutton
analystI was hoping you might take us through those 400 megawatts you're eventually taking to market — and clearly, 100 megawatts of that is now effectively claimed. It's quite obvious to us that on the demand side, this equation is going to be fairly substantial. I'm just wondering what you're seeing as you head out to market with that remaining 300 megawatts of opportunity.
Wes Cummins
executiveYes — demand was strong; we had 2 parties in very deep diligence last year. Based on what we've observed, which has been interesting in January, as we got the year underway, several additional parties have appeared, 3 more within the past week. And it almost feels like a sort of panic around finding capacity just over the last couple of weeks. So a great deal of interest is coming our way, and the parties involved would easily absorb more than what we have available. So it's good to get the first one nearly across the finish line, but my expectation is that within the next 1 or 2 months, all 400 will be booked out. And as a reminder, when we think about this, the largest issue we confront — which is a good problem to have — is how much we set aside for ourselves, since we want to reserve some of this for our own cloud solution. And I think that's really the open question: what's the highest and best value for these, for our assets, because we want to set some aside for ourselves, yet we have an enormous amount of demand for the capacity we hold. And, George, the reason that demand exists is that the 400 megawatts we have are 400 megawatts that could come online within the next 18 months. Right? The power is available, the land is there, permitting, we're in a really good position in a market that is already short capacity and I think it's going to get worse over the next few months.
George Sutton
analystAlright, my final question concerns the Sai Computing segment. We clearly grasp the difficulty on the supply chain front. Setting that aside, I'm simply wondering about the demand picture. You said there are four additional clusters that might be delivered shortly. Are you observing any issue with demand, has anything shifted in that area, or is it purely a constraint coming from the supply chain?
Wes Cummins
executiveRegarding demand, the sole shift we've witnessed there is the arrival of a fresh group entering the marketplace, which I referenced during my prepared remarks. Demand continues to be incredibly strong from companies backed by venture capital. What we're noticing in the market, though, is what we label enterprise customers. Let me define enterprise customers — these are businesses that are generally quite large, usually publicly traded, usually with a market cap above $50 billion, and they possess an existing business. They already operate a business. To me, it now seems they've been developing their AI plans, they've settled on what they intend to do with AI, and at this point they're seeking substantial GPU capacity. That's a new factor for us. One such customer has been engaged with us for roughly two months, and they've progressed into what we all term a proof of concept — essentially a trial run of our infrastructure. I believe we might get that customer under contract within the coming two to three weeks; yet that's the only shift, meaning greater demand, but originating from a distinct market segment. How I've viewed this market is that it resembles a barbell, correct? On one end sit the hyperscalers — that was the situation last year — hyperscalers on one end, VC startups on the other end, and there was essentially nothing in between, and now that middle portion is beginning to emerge.
George Sutton
analystThat's great, I appreciate the specifics.
Wes Cummins
executiveOf course. Appreciate it, George.
Darren Aftahi
analystHey there, good morning. I appreciate you taking my questions. Just a couple, if I could. If I understood you right, it seems like pricing on the GPU side has increased. Wes, I believe you mentioned that on an annualized basis, with the 10,000, it would exceed $200 million. I'm just a bit curious. At the Analyst Day, which wasn't that long ago, you mentioned the $1.5 million monthly run rate. So what has changed, I suppose? And regarding the GPU side, I know your target is 10,000 by the close of your fiscal year. Given that some component factors are outside your control, how confident are you in reaching that 10,000 figure?
Wes Cummins
executiveSure. Yeah, Darren, that's correct. Pricing has risen somewhat; what we're observing — the figure I mentioned earlier involves one of our biggest customers, and we had that priced at roughly $2 per hour for the GPU capacity and our reserve contract. What we're seeing currently is that for the majority of our customers, we're signing agreements, and the marketplace appears to be around $2.20 to $2.25 for two-year reserve contracts, with prepayments somewhere in the 20% to 30% range on those contracts; so that's the picture on the pricing update. Then regarding the 10,000, that figure — we reduced it from the 26,000; so originally ours was 26,000. We had co-location capacity for 26,000. And where we stand now is simply due to the slowness on the InfiniBand component side. The 10,000 is a figure we feel very confident about achieving. We feel very confident on multiple fronts, both regarding GPU delivery, and also regarding GPU financing without resorting to a bigger debt piece like some market participants have done. So we feel very confident on both of those; but that's why we provided that guidance. That said, what I'd add is that I believe there's more we can accomplish on the GPU side. So we'll have the 4,000 plus 4,000 before long; so roughly mid-February, we'll be at 8,000 of those clusters out of the 10,000 we're guiding for; so I think that gives us ample room between then and the end of May.
Darren Aftahi
analystAlright, let me fit in one final question here. Regarding Garden City, it clearly seems like the ramp-up there didn't happen as quickly as people had anticipated. When it comes to the grid components, could you perhaps explain a bit about what's required, and how soon those things are able to be sourced? Also I'm simply curious — your willingness to keep pursuing business, perhaps at the next location in a state such as Texas — how would you sort of rate that in terms of your appetite for operating in a place like Texas? Thanks.
Wes Cummins
executiveSure. I reside in Texas, and I'm very fond of it. So I'd rather not criticize Texas at all, so I'll avoid that topic. However, the projects we're currently developing going forward are in North Dakota and Utah. Those are the two regions we're focused on. I believe we've discussed this previously. We're actively seeking additional capacity given the demand we're observing in the market. We possess a pipeline for further capacity exceeding 1 gigawatt. So we're making our way through that. Then, regarding the Texas site specifically, there are certain upgrades. I'm probably going to explain this poorly, but I believe some resiliency is required, meaning a capacitor bank must be added — not at our particular site, but at a substation nearby, in order to reach the full 200. There are two paths forward there. One option is getting approval for wind combined with grid, and the alternative involves this — I believe it's a capacitor bank that has to be installed, and by the way, that isn't a major cost. But we've been dealing with this since late November or December; and the guidance we provided represents what we consider the worst case, which would be the April window for the rest of it to be brought online; so essentially we're just waiting for the final 65 megawatts to come up there.
Darren Aftahi
analystThat's excellent, thanks.
Rob Brown
analystHello there, and good morning.
Wes Cummins
executiveMorning to you as well, Rob.
Rob Brown
analystTo build on the question about the fresh anchor client, might you provide some indication of which vertical that client operates in? I believe you referenced, perhaps, the enterprise side or the VC-backed side. Which of those categories does this client fall under?
Wes Cummins
executiveThat's something we're unable to do, though here's what I can share: regarding the pool of customers we're observing — among everyone evaluating the site — few businesses anywhere on the planet are capable of absorbing 100 megawatts, 200 megawatts, or 300 megawatts on their own. Consequently, that's an extremely narrow set, and every firm currently in contention with us in North Dakota carries a name just about anyone would know immediately. What they want is hosting with high-power density, data center capacity with high-power density, yet each one is a company whose name you'd identify right away.
Rob Brown
analystAll right. All right. Thanks. Next, I'd like to dig a little deeper into what was said about GPUs — specifically, are you still on the hook to purchase those 26,000 GPUs and get them running once May has passed, or does that still hinge on what happens with contracts?
Wes Cummins
executiveYes, those purchase commitments remain in force, and that holds even at the 34,000 level. So our expectation is simply that we'll keep going. Actually, Rob, let me make one thing clear regarding those commitments: as things stand, the figure is 34,000 for H100. It's still possible for us to swap those out, either toward H200 or GH200, correct? For us, these are flexible. That means when market conditions shift, we can respond accordingly. Even so, they remain queued up for us, and we're able to take delivery once every component is on hand. As for what went wrong during the quarter we just reported — David brought this up in his prepared remarks, and I want to make it clear — we accepted a second cluster while that quarter was underway. We were making payments on it. That's where the costs came from; altogether, the figure came in a bit below $4 million. In other words, we were footing the bill for that cluster while it produced no revenue, since the InfiniBand parts we needed weren't there to finish commissioning it and hand it over to our customer. What we did, essentially, was halt GPU deliveries on our own end, because none of us wants to keep paying for GPUs when we're unable to provide them to customers and bring in revenue from them. That, in short, is the situation we found ourselves in — yet every one of those orders is still on the books, and we anticipate getting them deployed. I suppose we simply have to exercise greater caution regarding the timing we attach to those deployments.
Rob Brown
analystUnderstood. Thanks for the context. I'll pass it along.
John Todaro
analystThanks for the question. There are a few things I want to cover. First, as you mentioned earlier, the plan was for 20,000 GPUs by December 23. I recall that on the prior call or at Analyst Day, you may have noted some potential InfiniBand delays. I'm just wondering whether that situation turned out worse than you anticipated, or if those delays were already on your radar and perhaps your team simply misjudged them?
Wes Cummins
executiveOn that specific point, John, we are receiving the vast majority of the networking gear we required. There was a single component, but without it the system won't function. For example, in one of our clusters, we have the full InfiniBand configuration except for roughly 28 transceivers, yet you cannot fully commission that cluster and start generating revenue. So the bottleneck is really just getting those transceivers in place. As I mentioned, we could have accepted many more GPUs, but I don't see the benefit, and I believe it would hurt us to take delivery without being able to produce revenue and cover the cost of the GPUs. So we delayed that and made that call in December. We could have taken a substantial number of GPUs in December, but again, there was no reason to. As those become available, I think you'll see us accelerate that again considerably, and we've begun to see the market loosen up in late December and January, but I'm not prepared to say we'll be able to speed that up enough to hit the 20,000, then 26,000, and 34,000 deployment.
John Todaro
analystUnderstood. Alright, that's useful. I had another thing I wanted to ask — you brought up a fresh client agreement on the Sai compute side, an enterprise buyer, and how you might get to a proof of concept and perhaps begin fulfilling that deal before long. I'm just wondering, given the hold-up, shouldn't the contract that already existed take priority over this new one, or has anything shifted regarding those agreements?
Wes Cummins
executiveThose agreements remain exactly as they were. And let me be precise, John — there is no contract in place with the enterprise customer. We're at the proof of concept stage, and after that we would shift into contracting. So I just want that to be clear. That said, nothing is different when it comes to our earlier clients. Still, it's thrilling to watch a completely new set of players emerge in the market seeking a substantial quantity of GPU compute. These are reputable businesses that generate revenue and offer a real product. And I'm simply pointing out that this represents a somewhat new segment of the market that we've watched take shape over the recent period — it genuinely began around late November.
John Todaro
analystAll right, understood. But I just want to make sure — despite those delays, it still sounds like customers are eager, basically beating down the doors?
Wes Cummins
executiveRight, that hasn't been a problem for us at all.
John Todaro
analystAll right, understood. Appreciate it, everyone.
Wes Cummins
executiveAs I mentioned before, John, what I'd say is this: ever since enterprise customers came into the picture, demand has risen compared with our prior conference call — that's the overall picture. Nothing has decelerated that we can see. It has gone up.
John Todaro
analystUnderstood. Thanks. I appreciate that.
Mike Grondahl
analystHi everyone. Could you give a ballpark figure for how much Applied is putting toward the total funding of the build, specifically the project portion for the anchor tenant? Approximately what amount do you need to contribute to that, just a rough figure? And how much has been put in up to now?
Wes Cummins
executiveWell — that's a fair question, Mike. If you consider — as we put it, it's 7 million megawatts. Let's assume the top end of that range. So that's 7 million megawatts, correct, we'll end up somewhere between 65% and 85% — pardon me, 65% to 80% when it comes to construction finance, at the project level finance. After that we anticipate bringing in what our industry refers to as an equity partner; though, like I mentioned before, that typically resembles mezz debt more than anything. So ultimately, you're looking at us, and what we expect is that our cash contribution will fall somewhere in the range of 5% to 10% of the project for the equity piece of it; and we have already spent in excess of…
David Rench
executiveTwenty-five million dollars.
Wes Cummins
executive…twenty-five million dollars allocated to Ellendale as things stand. And beyond that, Mike, as we examine it, David brought this up during his prepared remarks, regarding our company's cash flow, one thing worth highlighting is that come March 1, the money generated by our Bitcoin data centers gets a whole lot better. Correct? By then we've used up nearly all of those prepayments, which means the cash coming in from that side of the business gets a whole lot better.
Mike Grondahl
analystUnderstood, understood, that's useful. And my assumption is that the GPUs will be provided by the anchor tenant, but could you make that clear?
Wes Cummins
executiveYes. Regarding the data center business, all we do is supply space. Picture an Equinix or DLR type of operation. We supply the space, the equipment gets chosen and purchased by them, and after that we simply host it. Much like what we do on the Bitcoin side.
Mike Grondahl
analystUnderstood. Understood. And approximately, at what point would you start recording revenue from this anchor customer? And listen, I won't pin you down on this, but approximately, as things unfold, when do you think that revenue would kick off?
Wes Cummins
executiveWell, at present, what we're anticipating is that the revenue would come in the very beginning portion of the back half of this calendar year.
Mike Grondahl
analystso roughly July and August, something along those lines...
Wes Cummins
executiveyep.
Mike Grondahl
analystAll right. That's excellent. So, one final item from me. Regarding the Bitcoin hosting operation, are there any agreements being renewed or extended, or any revised sorts of conditions, or would you say that side of things is entirely tied up?
Wes Cummins
executiveYes, it is tied up. A couple of points worth mentioning: for our biggest client in that area, we hold 4 years — possibly slightly more than 4 years — on the majority of the capacity tied to that client under the agreement. The one other item worth mentioning, and this likely won't come as a shock, is that we're noticing — we're receiving far more inquiries regarding hosting capacity. We never go out marketing since we have nothing available to provide, yet we're fielding far more inquiries regarding hosting capacity across the past, say, 6 weeks, 8 weeks, as Bitcoin's price has climbed considerably.
Mike Grondahl
analystGot it. Okay. Hey, thank you.
Wes Cummins
executiveAbsolutely.
Kevin Dede
analystHey, Wes. Got a question for you. What I'd like to know is how many sites you currently operate or rent in order to deliver the electricity your cloud offering requires right now.
Wes Cummins
executiveAbsolutely. We've got third-party sites located in Denver, Minnesota, and Salt Lake City. Beyond that, we run our own Jamestown location up in Jamestown, North Dakota.
Kevin Dede
analystAll right, and regarding Jamestown, from what I gather, you’ve reached the ceiling of 8 megawatts there.
Wes Cummins
executiveJamestown is going to accommodate 5,000 GPUs for our operations. I could express that in megawatts, or I could give it to you in terms of GPU capacity, whichever you’d rather.
Kevin Dede
analystOh, any format you typically use works. I suppose what really sparked this question is the cloud build-out situation, correct? Considering how tight the market is right now, what steps are you taking to lock down the electricity required to satisfy your customers' needs on the cloud service side?
Wes Cummins
executiveYes, so we locked down that power during the summer of last year; in other words, around mid-year last year, we acquired these power sites. We recognized the demand and we moved quickly to obtain the capacity so we could serve it; thus we secured it at that time. Consequently, we possess the capacity from both third party sources and our own facilities for the 26,000 GPUs we mentioned. After that, our expectation is that it will shift into our own facilities beyond that 26,000 as we keep expanding.
Kevin Dede
analystOkay, so out of that Delta amount, 26,000 to 30,000 will be directed into the Ellendale facility, which is currently being built.
Wes Cummins
executiveThat's right.
Kevin Dede
analystAll right. I believe I picked up on your reference to a marketing initiative. Could you elaborate on what path you plan to follow with it? Is your thinking that it moves toward the enterprise market you're watching begin to take shape?
Wes Cummins
executiveYes. It's aimed squarely at the enterprise market. As you'll recall, Kevin, this has come up between us previously, but a single salesperson has never existed at our company. Our first salesperson came aboard a few months back, and we intend to bring on additional people for that capability, with the specific goal of pursuing this enterprise market we now see taking shape. That's what we expect; before that point, no salesperson had ever been with us; we possessed no sales force at all within the company.
Kevin Dede
analystGot it, and congratulations on that. I suppose I'm still somewhat uncertain about the way you expect that market to evolve, and also, I guess, your position relative to competitors, and if demand is really that strong, then why would any marketing effort be needed in the first place?
Wes Cummins
executiveWell, we brought on one salesperson, and we might bring on one more, but there's this notion of getting out there and ensuring folks are aware of who we are and what it is we do, since we had never done anything like that at any point in this company's history. So that's essentially the thinking. So I don't believe you ought to assume we're bringing on 20 salespeople, though I do believe it makes sense to add a handful of salespeople and grow that sales team. And the thinking here, which we've talked about quite a bit internally, is that we don't require it at this moment, but we don't want to hold off on building it until the point when we do require it.
Kevin Dede
analystThat's clear. All right, I appreciate it. <<inaudible>> any objection to sort of asking for more detail. Many thanks.
Wes Cummins
executiveNo, no, no; that's all, though. But yes, Kevin, we're talking about this right now on the call, yet there's been plenty of internal debate, with one faction asking why keep sales staff when there's nothing for them to sell. Then there's the other view that says we ought to build these things ahead of when they're required. I've come down on that second side, meaning in my view it makes sense to build out a sales force ahead of when it's actually required.
Kevin Dede
analystI can't argue with that. The right marketing is what drives everything. Well, Wes, congratulations once more on these results. I really appreciate you fielding the questions.
Wes Cummins
executiveThank you, Kevin. Operator <<operator_script>> That wraps up the questions we have. I'd like to give the floor back to Wes for a few closing remarks. Thank you, and thank you all for being here; my final thought is simply that I want to express my gratitude to the crew in Ellendale. Here we are in January. The weather isn't exactly kind for them to keep building at our site. So we're truly grateful to that team and to everyone who helps get it done for us. And I'm looking forward to talking with you again next quarter.
Operator
operatorAppreciate it. That brings today's call to a close. At this point you're free to hang up, and thanks for joining us.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Applied Digital Corporation transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →This call discussed
For developers and AI pipelines
Programmatic access to Applied Digital Corporation earnings transcripts and 132,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Applied Digital Corporation or any ticker on your watchlist.
StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.