Matt Glover
executiveThank you for joining our 2025 conference call. Prior to management delivering its prepared comments, we want to remind all of you that certain things we say today might qualify as forward-looking statements under securities laws and carry various risks and uncertainties. Consequently, we advise you that numerous factors exist, many outside our control, that might lead actual outcomes and events to differ substantially from what those forward-looking statements describe. Regarding more thorough risks, uncertainties, and assumptions tied to our forward-looking statements, please review the disclosures in our earnings release and the public filings we make with the Securities and Exchange Commission; we disclaim any duty or commitment to revise forward-looking statements so they reflect situations or occurrences arising after the point those forward-looking statements are delivered, unless the law demands it. We likewise cover non-GAAP financial metrics and urge you to examine our disclosures, reconciliation tables, and the relevant GAAP measures in our earnings release with care when evaluating these metrics. We point you toward our SEC filings for thorough disclosures and descriptions of our business, along with uncertainties and other changing circumstances, including but not limited to, the risks and uncertainties laid out under the captioned risk factors in our annual report on Form 10-K and our quarterly report on Form 10-Q. You can obtain Applied Digital's Securities and Exchange Commission filings at no cost by going to the SEC website at www.sec.gov. Finally, I want to remind everyone that we are recording this call and it will be accessible for replay through a link in the Investor Relations section of Applied Digital's website. At this point I'd like to hand the call over to Applied Digital's Chairman and CEO, Wes Cummins. Wes?
Wes Cummins
executiveAppreciate that, Matt, and good afternoon to all of you. Thanks for being with us on this conference call covering our fiscal first quarter of 2025. To begin, I'd like to express our gratitude toward the employees whose continued dedication and hard work support our mission — delivering purpose-built infrastructure to the high-performance computing industry, which is expanding quickly. Before I hand things over to our CFO, David Rench, who will take you through a thorough review of the financial results, I want to walk through some recent business developments. Once the quarter ended, our balance sheet got a substantial boost through strategic investments made by a group of institutional and accredited investors, NVIDIA and related companies. We truly appreciate the confidence our investors have shown, and we're eager to put this capital to work on high return projects within the digital infrastructure sector. Now for an update on where things stand at our Ellendale HPC campus. Construction is proceeding on schedule, and we are in the final stages of the lease with a U.S.-based hyperscaler. On top of that, site-level debt financing is moving forward and should close soon after the lease is executed. In our view, this first 100-megawatt building represents only the start for Applied Digital, since we've already designed two more buildings at this site and intend to grow capacity there to 400 megawatts. At the same time, we're looking into ways to speed up monetization of our pipeline, which exceeds 1.4 GW. I'll now give an update on each business unit, beginning with data center hosting. Right now we hold 286 MW of data center hosting capacity serving our cryptocurrency clients, spread across two fully contracted North Dakota locations that run at full capacity. Turning next to cloud services, the business that supplies high-performance computing power for AI applications: this segment keeps growing as we deliver on existing contracts and pursue fresh opportunities in our pipeline. By the close of the first quarter, six clusters were online. Substantial headway has been made on amending the lease financing for our GPUs, and we anticipate wrapping that up during the current quarter. As envisioned, this amendment lets us amortize the GPUs' value across their expected useful life rather than the lease term, which should meaningfully lift our reported results and better capture the true economics of this business. The market visibility for our cloud business has risen considerably thanks to our recent investment round, and we expect to bring additional clusters online beginning in the second half of our fiscal year, which starts December first. All told, the positive trends throughout our business are encouraging, and our confidence in the growth trajectory remains strong. With that, I'll hand the call to our CFO, David Rench, who will walk you through our financials and give an update on guidance. David?
David Rench
executiveAppreciate that, Wes. I want to start off by calling attention to how our top line grew, climbing 67% to reach $60.7 million during this quarter. The main force behind that expansion came from what cloud services agreements added. To break it down, revenue of $34.8 million came out of our data center hosting segment, and our cloud services segment pitched in $25.9 million. Yes, costs did rise, but that mostly reflected bigger depreciation and amortization charges. Depreciation and amortization came to $34.4 million for the quarter, compared with $8 million during the equivalent stretch a year ago. You should also keep in mind that right now we're carrying substantial costs tied to data center leases supporting our cloud operation, since GPU clusters haven't been installed at those sites yet. Consequently, this quarter the company took on $4.1 million of expense for facilities that still aren't producing any revenue. Looking ahead, we intend to put those data centers to work, and that should help us absorb those costs. Adjusted EBITDA rose sharply this quarter, hitting $20 million. On the quarter, our Adjusted Net Loss landed at $21.6 million, equal to $0.15 for both basic and diluted shares, with the calculation resting on a weighted average share count of 149 million shares. Moving on to the balance sheet: we closed out the fiscal first quarter holding $86.6 million across cash, cash equivalents, and restricted cash, plus $143.6 million of debt. And finally, shareholders' equity stood at $241.8 million, essentially twice what it was 3 months earlier, thanks to a fresh injection of capital from major investors. At this point I'll hand things over to Wes for his closing remarks.
Wes Cummins
executiveThank you, David. Many of you likely know that our company was among the first in this industry to recognize the substantial power demands involved in providing the computing capacity needed to run complex AI tasks at scale within sizable, high-density data centers. To address that, we began construction on a cutting-edge 369,000 sq ft site toward the end of last year, a project built from the ground up for HPC use cases. With our in-house data center blueprint and architecture, our view is that we've set a new standard for what sophisticated HPC can achieve, since this purpose-built site addresses sophisticated cooling, intense power density, security, interconnectivity, compliance, and control needs. Because we got into this sector early with a sizable commitment, we're now deep into negotiations on both the contract and the site-level financing for a lease of our North Dakota campus, and the other party is a hyperscaler headquartered in the U.S. Beyond that, we think interest keeps building among elite players in the industry for the HPC data centers we design and build ourselves for a specific purpose. When you pair that momentum with stronger lease pricing and appealing debt financing arranged at the site level for our buildings, our view is that it makes us an early visionary in this rapidly expanding piece of the market. The need for thousands of facilities like these has been highlighted by what major hyperscalers have announced lately, and that confirms the path we've chosen to follow. During the last five weeks, interest and demand have risen considerably among additional leading hyperscalers seeking capacity for 2025 and 2026, and that capacity is incredibly scarce right now. Because we are constructing and can provide meaningful capacity in 2025, and because we have put together a deeply seasoned team, we are able to enter this rapidly expanding market segment as a full stack developer serving hyperscalers; our belief is that this will enable us to generate revenue from our remaining campuses where power will be ready in 2026. In addition, we think the strategic investments made by well-known investors serve as a powerful confirmation that our direction is correct. This widening recognition, in our view, both reinforces where we stand in the market and underscores the enormous opportunity inherent in our strategic plan. We aim to turn ourselves into a platform that can construct and run numerous HPC data centers on a large scale. There are potential catalysts on the horizon that excite us, and we will continue putting our capital to work in a strategic manner so we can secure the best returns relative to risk and boost shareholder value as much as possible. While we keep working through our expansion and growth, we are implementing certain executive team changes meant to put us in a stronger position. David Rench is going to take on the Chief Administrative Officer position, while Saibal Momen is going to take on the Chief Financial Officer position, and both shifts take effect Monday, October fourteenth. At this point, we are ready to take your questions. Operator?
Lucas Pipes
analystThanks a lot, operator. Wes, along with the team, congrats on the latest funding round and everything you've accomplished. Wes, I'd like to start with the lease discussion. My earlier understanding was that the exclusivity window tied to the LOI had been prolonged, so I'm curious whether that window has now lapsed, whether it's been extended again, or whether that exclusivity is still in effect. I appreciate whatever you can share.
Wes Cummins
executiveAbsolutely. Hey, Lukas, how's it going? The exclusivity window is now officially over; we made the decision not to extend it; at this point we're simply working toward wrapping up the lease document itself. Neither side, as I see it, felt there was any justification for prolonging exclusivity merely to get that document finished.
Darren Aftahi
analystHey, everyone. I appreciate you answering my questions, and congratulations to Saibal and David regarding their new roles. Can you clear something up for me? To start, the press release mentions that the lease with the hyperscaler for 100 megawatts has been finalized. I just want to be certain: does that lease cover only 100 megawatts, or does that hyperscaler hold options for more capacity at the campus?
Wes Cummins
executiveYes, Darren, thank you. What you ought to anticipate — and I believe this is something we've discussed consistently — is that the first lease will be 100, and then the remaining 300 will take a different form. However, the expectation is that a reservation on the other 300 MW will be part of that lease. As I think we mentioned in the script, we are already designing those facilities, or they are largely designed. Some earthwork has begun on them, some early work to get things moving. We've — you know, I feel as though we have gone over this multiple times, you know, regarding North Dakota winters. So progress on those has already started, but the expectation is that the entire campus will be taken by that single tenant, though it will arrive as two leases.
Rob Brown
analystGood afternoon. Turning to the GPU side of things, you mentioned more clusters, and my sense is demand is quite robust there, with capacity fully utilized. How are you thinking about those extra clusters, and what's your view on the timing?
Wes Cummins
executiveYes. Rob, like we described in the script, we anticipate beginning to roll out more clusters. We're sitting on capacity — data center capacity secured at very appealing pricing, I should say — for bringing those extra clusters online. We observe the demand out there in the market. What's happening in the market at present is whether customers would rather go with Hopper, or whether they'd prefer to hold off and shift to Blackwell when you get into, you know, the back portion of the first half of the next calendar year. So those conversations are taking place, and that's essentially what we're focused on. But we anticipate that during the back half of our fiscal year, which, as you're aware, kicks off, you know, on December first, we'll start rolling out more clusters once again; we've put in a great deal of effort to ensure we're arranging the proper kind of financing so that, once more, the P&L, you know, that I discussed regarding the reworking of the leases we hold, that we properly record depreciation, that the payment schedule extends to three years rather than two years, so it aligns more closely with the business model. So we've put in a great deal of effort across the last nine months to ensure we've got the right financing in place to move that forward. There's a lot of interest on our end. We received a really nice lift, you know, from the investment back in September, plus considerably more visibility on us. So you ought to expect that we begin deploying more clusters under a revised financing structure during the back half.
Mike Grondahl
analystYeah, guys. Hey, Wes, when we talk about the demand environment, once those 400 MW get leased up, have you begun conversations yet with a possible second or third customer? And do you have any sense of where that data center could end up being located?
Wes Cummins
executiveYeah. Thanks for asking; as I hinted at somewhat during my prepared remarks, starting with our prior call — that is, in late August, the final week of August, and then across September — we witnessed a meaningful uptick in activity. That's just one data point, so I'm not going to declare a market trend based on it. Even so, a substantial volume of inbound interest came our way from three more hyperscalers. We've discussed before which hyperscalers we usually pursue, and three beyond the one we're already engaged with in North Dakota are now pressing hard for capacity in 2025 and 2026. We're taking the sites in our portfolio to market with those customers, and from where we sit, demand has climbed considerably, particularly for 2025 and 2026 capacity. You know, twenty-five is essentially spoken for at this stage. No further twenty-five capacity exists out there that would include the 100 MW at Ellendale for twenty-five. Plenty of parties have begun shifting toward the first half and even the second half of twenty-six. Still, we're witnessing a substantial level of demand and, you know, working toward securing another LOI at a separate location, probably within the Dakotas. I wouldn't say North Dakota, but probably within the Dakotas for us for that second site; but we are witnessing a substantial level of demand for what we have.
Mike Grondahl
analystDo you think an LOI could come in calendar 2024 or early 2025? Any ballpark sense of when that LOI might be possible?
Wes Cummins
executiveYeah, based on what we're seeing in terms of activity, something could come together by the close of calendar 2024 for one more site; for us, Mike, this market is so dynamic, as we're watching plenty of developments unfold; at least during this quarter, plenty of favorable developments have come our way, the quarter we're in right now, you know, the investment. On the supply chain side, we've made some really substantial strides. Within the industry, certain things are happening where projects are getting delayed because power timelines keep slipping. As one illustration, we've watched a bit more than 400 megawatts of backup gen come onto the market from projects whose power timelines got pushed out by several years, if not longer, so that equipment is being resold into the market, and we've recently capitalized on that, so there's plenty of, you know, forces at work in this industry, and it's highly dynamic, and we're working to stay as nimble as possible so we can capitalize on those things. Since that will help us, from a supply chain standpoint, speed up both the building two and three in Ellendale, and also additional sites, so just a lot of things happening.
Mike Grondahl
analystAll right, thanks.
Analyst
analystWas I someone you meant to pick, George Sutton?
Wes Cummins
executiveGeorge, your voice comes through to me, so it has to be you.
Analyst
analystAll right, my apologies. It's nothing — this is George Sutton. I'd like to see if you can provide a bit more detail regarding where things stand with getting the lease finalized. What's still outstanding? My thinking has been that you've been working out a delivery date partly tied to the connections coming into the facility and partly tied to the backup. So is that still the situation with the lease?
Wes Cummins
executiveThat isn't actually what's still outstanding on the lease, but allow me to clear that up, George. I believe there was a bit of misunderstanding about that during the prior call. So, as you know, I was referring to the point at which lease revenue begins. And I've mentioned that it's, well, in certain respects it will really come down to the tenant's decision. So, to make that clearer: the facility is going to be ready sooner, during the first half of 2025, with single feed, after that in the middle of 2025 with dual feed, and after that in the second half of 2025 with dual feed plus backup gen. So in practical terms, the client could begin taking power if they're okay with going single feed using only UPS redundancy — then the question becomes whether they'd rather hold out for dual feed. And so, from a safety standpoint, I'd say, you look at the second half of full backup gen, dual feed, meaning complete redundancy at the site — so I think there was a bit of misunderstanding. I'm just attempting to clarify it. Very little remains to be done on the lease, George; honestly it's just, well... I've tried to estimate this, and my estimates have been off multiple times. Our confidence that this lease will be finalized is very high, and in truth, it might take only a few days. It might take six weeks. There's a range within that, perhaps, on the slim chance, eight weeks; but, well, it falls somewhere inside that range, and nothing in particular is actually blocking the lease. It's simply the process. That process isn't under our control. We push on it as hard as we're able to, but our confidence that the lease gets completed is very strong. Beyond that, we've put substantial effort into the site-level financing. The bank group is arranged on that. As you're aware, they're prepared to fund as soon as the end of this month, whenever the lease is signed. So every piece is in place and ready, and this will, well, be finalized, and once it is finalized we'll make an announcement and then handle the funding at that point, which will come shortly after. But I regret, George, that I can't hand you highly specific items — the process just isn't something we control. One thing I'd mention as extra context: we've never supplied this company before, and for us this deal is quite big — though honestly, given how large it is and how long it runs, I'd say it's significant for the customer as well. What I've been told by outside sources is that a new vendor in this situation usually needs somewhere between 12 and 18 months to complete the process, and here we are around month 6. That's remarkably quick progress, and it feels like we're right at the finish line. I'm doing my best to share what detail I can, though clearly our own timeline has slipped past a few dates we'd set. Still, the collaboration with them continues advancing daily, and each week brings substantial movement. Based on everything available to us, our confidence is high that the signature will come. The trouble is, predicting exactly when is genuinely difficult.
Analyst
analystMy guess is it won't happen by the time the next hurricane arrives, though with any luck it will be done before the following one. Now, regarding building two, you said dirt is starting to be moved. I realize you'd rather not carry this on your balance sheet. Could you help us understand how you're starting to put together buildings two and three, and where things stand with all of that?
Wes Cummins
executiveYeah. The dirt work, or earthwork, compared with the cost — compared with what the whole building costs — is actually tiny. So that's the sort of item that's simple enough to move forward on. We've been going through the design process. A few design changes are going to happen. If you aren't getting better, you ought to get better each time, so some modifications should be anticipated. On top of that, it's going to be... Right now the expectation is 150 megawatt IT load for that building rather than 100; so there are some adjustments, but we're pressing to have that building finished in the second half of calendar 2026, and then building three in the second half of calendar 2027. And so we have to. A significant amount of work has already been done by us. That work isn't costly in dollar terms, but it's a significant amount of work so we can be sure those timelines are met.
Analyst
analystAll right. Thanks for the clarity.
Wes Cummins
executiveYep.
John Todaro
analystHey there, Wes, and hello to the rest of the team. I suppose I have roughly a pair of questions, and both tie back to the lease. You brought up that two leases are coming — 100 megawatts, plus another 300 on top of that. Should we figure the economics will be more or less identical for both, or ought we to assume somewhat stronger economics perhaps on the initial 100, with them pushing back a bit tougher when it comes to the remaining 300? Any thoughts you can share there. Then for my second item, at least when it comes to that first lease, would you say all the major points we'd care about are settled at this stage, so that what's left is basically administrative work that might stretch across 6 to 8 weeks?
Wes Cummins
executiveYeah. So I appreciate that, John. And once more, I'd rather not claim it might stretch to that long — it's, once more, somewhat of a guessing game. But yes, you've got the second portion of that right; regarding the first portion, two leases, those are two distinct structures, yet from an economic standpoint they should appear quite comparable, if that makes sense.
John Todaro
analyst... All right, so, regarding that earlier point—the economics around revenue and EBITDA—we ought to—
Wes Cummins
executiveRight.
John Todaro
analystWhen we're building the model, that's still roughly how I'd approach it. Okay.
Wes Cummins
executiveRight, although a single one of those leases, as you probably know, should take the form of something like a colocation arrangement, in which the rate comes to $1 for each kilowatt monthly, while the rest follows a yield-on-cost approach, which hyperscalers more commonly use, yet from an economic standpoint the two will appear quite alike.
John Todaro
analystI see. That makes sense. On the second item, just so I have it right, at this stage you'd describe it as being primarily in a clerical phase, is that fair to say?
Wes Cummins
executiveThat's correct.
John Todaro
analystOkay. Thank you, Wes.
Wes Cummins
executiveYep.
Michael Donovan
analystHello, Wes and David. Michael Donovan here, dialing in for Kevin. Regarding cloud services, could you share your observations on customer churn, and how have prices shifted alongside demand?
Wes Cummins
executiveSure, so on the pricing side, surprisingly, it's been fairly flat for, wow, nearly the past 12 months on the... let's just say on Hopper, for an hourly bare metal rate; so keeping it to bare metal for a GPU per-hour price, that's stayed pretty flat. I mean, we're still, you know, giving quotes in the twenty, or, pardon me, the two, around two twenty-ish on average each hour. Then regarding customer churn, you know, we continue growing with our biggest customer. There's one customer that carries, you know, more of a question mark over it in Character.AI, given the shifts that have occurred there and the payment. You know, I'm not familiar with the payment specifics. I think everybody on this call knows the same specifics I do, which is what I read in The Wall Street Journal of approximately $2.7 billion, I believe, was the figure. So there are some question marks surrounding that, and there's a possibility we swap customers out there, but we have demand for those clusters to keep growing. I'll return to what I've discussed the past couple of calls, which is we're highly focused on the enterprise market, which has been a developing market, and we're seeing growing demand in the enterprise market. What I'd say about the AI lab and the sort of the AI startup market is I feel like it's become much more prudent in that market. You're seeing a lot better. You know, far more thought going into business models rather than, you know, if you went back fifteen or eighteen months, you were looking at how, you know, how many GPUs can I get online and how quickly? So I think people are looking more around, you know, business models, and I, you know, I actually feel a bit more comfortable around those companies; and I think we have, you know, in our biggest customer, in Together AI, just a company that thinks about that a lot and has some really great customers on their end and a wide range of customers as well. But that market's still seeing, you know, significant demand growth; we're seeing new entrants, you know, from a customer side perspective in that market, both on the enterprise and you know, back to the AI labs and the AI startups. But the pricing has been largely stable there.
Michael Donovan
analystAll right, thanks for that, Wes. Moving to something a bit more conceptual — is your team working on any engineering answers for recirculating heat? And if that's the case, are you considering bringing in customers as a way to offset power costs there?
Wes Cummins
executiveYes — you're referring to capturing heat for the data centers, right?
Michael Donovan
analystExactly.
Wes Cummins
executiveYes, so a good deal of our time has gone into exploring approaches for doing just that. When it comes to our Bitcoin data centers, capturing the ambient heat generated for any sort of use is significantly more difficult, because those rely on air cooling. The HPC site, though — the Ellendale Two facility — is shifting toward liquid cooling, which opens up a far simpler path to capture the waste heat produced there and seek out possibilities for co-location. Given where our operations sit, agricultural uses are really what we need to pursue for putting that heat to work, and we're looking into it now. We anticipate beginning to roll some of that out during calendar 2025, once that facility is up and running. But the kinds of things you'd consider are, say, greenhouses, aqua farming, mushrooms — agricultural options suited to the regions we operate in across North Dakota — in order to put that waste heat, or the heat the facility discards, to good use.
Michael Donovan
analystOkay, great. Thank you, Wes.
Wes Cummins
executiveAbsolutely.
John Gruber
analystYes. Yes, quite nice — the jazz playing during this call sounds good. Wes, here's what I want to ask: on your previous call, the figure stood at 90%. Has it moved to 91%, or has it reached 99.5% at this point? What's our current position, roughly... You provided us an assessment during that prior call.
Wes Cummins
executiveJohn, that's an excellent question, and, well, if my memory serves me right, during that earlier call, well, 90% of the effort was finished, and honestly I struggled to estimate what, well, the schedule looks like for those final ten. Still, I'd put us at, well, 98.5% or 99% of the way there; it's, well, largely clerical work for us now, just as John put it to you. So, as I mentioned, I wish the process were more within our control, but, well, we apply pressure wherever possible, yet I believe we've reached the tail end of it. Getting to this point has been a tremendous effort by the team.
John Gruber
analystThank you.
Wes Cummins
executiveAbsolutely.
Darren Aftahi
analystHey everyone, one more quick question, Wes, about those two leases you mentioned. I'm a bit curious — regarding the yield on cost for that second one, do you have a target range in mind? And then for that second lease, considering how you might build before securing a client, would you want some kind of prepayment component to help finance buildings two and three down the road? Thanks.
Wes Cummins
executiveDarren, regarding that — I won't discuss the specific yields on lease rates or our pricing there. I believe it's too early for that. Still, it does fit within the model we've consistently described from an economic standpoint. As for what we expect on buildings two and three, or B and C as we call them internally, we'll proceed. As I mentioned, we're investing a small amount, very minimal dollars, not significant CapEx. What we anticipate is having a signed lease and project financing secured before building there, so we won't go through anything like what happened with the first one, where, as I've said repeatedly, breaking into this market as a full stack developer required speed to market, and that's worked well for us. But for buildings two and three, expect a signed deal before any major CapEx spending. That said, from a market standpoint, looking at what we've observed, particularly during September, we're seeing potential offers from hyperscalers providing capital to build plus upfront payments. We have a — we're — we'll pursue that for some of our other campuses. But we are seeing some of that in the market, which speaks to demand for twenty-five and twenty-six and the scarcity of what's available.
Darren Aftahi
analystThank you.
Wes Cummins
executiveI appreciate all of you being here on this call. I'm looking forward to talking with you in January.
Operator
operatorThanks for joining. That brings today’s teleconference to a close. We appreciate everyone taking part. At this point, you’re free to hang up your lines.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Applied Digital Corporation transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →This call discussed
For developers and AI pipelines
Programmatic access to Applied Digital Corporation earnings transcripts and 132,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Applied Digital Corporation or any ticker on your watchlist.
StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.