Applied Digital Corporation (APLD) Earnings Call Transcript & Summary

July 30, 2025

NASDAQ US Information Technology IT Services earnings 25 min

Earnings Call Speaker Segments

Matt Glover

executive
#1

Thank you, operator. Hello, everyone, and thanks for joining Applied Digital's Fiscal Fourth Quarter 2025 Conference Call. Ahead of management's prepared comments, we'd like to note that some of what we say today may qualify as forward-looking statements under securities laws, which come with various risks and uncertainties. As a result, we want to caution that numerous factors—many beyond our control—could cause actual outcomes and events to differ materially from those outlined in those forward-looking statements. For a fuller picture of the risks, uncertainties, and assumptions tied to our forward-looking statements, please refer to the disclosures in the earnings release and the public filings we've made with the Securities and Exchange Commission, or SEC. We don't take on any duty or commitment to revise forward-looking statements when situations or occurrences arise after those statements have been made, unless the law demands it; we also cover non-GAAP financial measures, and we urge you to review our disclosures along with the reconciliation tables tied to the relevant GAAP measures and the earnings release thoroughly when weighing these metrics. For in-depth disclosures and descriptions of our business, plus uncertainties and other shifting circumstances — including, though not restricted to, the risks and uncertainties laid out in the Risk Factors Section of our annual report on Form 10-K and our quarterly reports on Form 10-Q — we point you toward our SEC filings. Applied Digital's SEC filings can be viewed at no cost on the SEC's site, www.sec.gov. Everyone should know that we are recording this call, and a replay will be accessible through a link posted in the Investor Relations portion of Applied Digital's website. At this point, I'll hand things over to Wes Cummins, Applied Digital's Chairman and CEO. Wes?

Wesley Cummins

executive
#2

Thank you, Matt, and good afternoon to all of you. We appreciate you joining us for this call covering the fourth quarter of 2025. To begin, I'd like to thank the people who work here for the dedication and effort they keep showing in service of what we're trying to accomplish — delivering purpose-built infrastructure for an HPC industry that is expanding quickly. Ahead of handing things to Saidal Mohmand, our CFO, who will walk through the financials in detail, I want to update you on a few things happening in the business. Let's begin with the HPC data center hosting segment. In the quarter, we executed transformative 15-year lease agreements with the AI hyperscaler CoreWeave covering 250 megawatts of critical IT load at our campus in Ellendale, North Dakota, which is now called Polaris Forge 1. Over the life of those leases, roughly $7 billion in contracted revenue should be generated, and they put Applied Digital in a leading position within AI and HPC infrastructure. CoreWeave exercised its option last week for another 150 megawatts in a third building at Polaris Forge 1, which highlights what this campus can become as a scalable hub for next-generation AI workloads. For Polaris Forge 1, one of the most ambitious data center projects anywhere in North America, these long-term leases represent a defining moment. Built specifically for artificial intelligence and high-performance computing, the campus pairs enormous power capacity with swift deployment and is engineered to scale as high as 1 gigawatt. The initial 100-megawatt facility is slated to be operational in Q4 of 2025, the second 150-megawatt facility is set to come online in mid-2026, and a third 150-megawatt facility is planned for 2027. Polaris Forge 1 acts as a launch pad for what comes next in AI infrastructure, and in our view it confirms the vision we had of delivering power dense, reliable solutions and becoming a category leader in the design and construction of AI factories. With momentum from these leases and demand for AI infrastructure surging, we are actively taking our multi-gigawatt pipeline to market with a diverse set of customers. One of our key strengths over the past 2 years, we believe, has been refining our process — cutting SKUs by about 50% and consolidating suppliers. Our proprietary building design, we believe, provides more flexibility, and we've created a repeatable process requiring minimal customization and backed by a strong supply chain. Because of that, we believe projected build times have come down from 24 months to 12 to 14 months, which lets us fulfill large-scale commitments more quickly and efficiently than we could previously. We're also emphasizing the numerous benefits of building in the Dakotas, together with our distinctive design featuring an innovative closed-loop direct-to-chip liquid cooling system. That design aims at a projected PUE of 1.18 and near 0 water consumption, meant to guarantee outstanding efficiency and sustainability; we favor this location because of its plentiful low-cost synergy, part of which comes from stranded power along with over 200 days of free natural cooling. Our analysis shows that a data center customer using 100 megawatts might achieve savings as high as $2.7 billion across a 30-year span when measured against industry data centers currently operating in other regions. Through choices we've made regarding where to build and how to design, we aim to put ourselves in a spot where we can expand substantially throughout the Dakotas and in other areas covered by our pipeline. In addition to CoreWeave, we have finished diligence and onboarding with two other North American hyperscalers that carry investment-grade ratings. That achievement deserves real emphasis. What we've come to understand during the last two years is that the internal approval and contracting work involved in onboarding hyperscalers takes longer and involves more complexity than we initially expected; we think the experience gained from leading the market through this process, along with signing our first leases, will serve us well as we keep talking with prospective tenants and work through our pipeline; we likewise anticipate gaining from this edge as new market participants face the time, capital, and labor required to get past these industry barriers to entry that other players encounter. Also, from our standpoint, we believe we're now positioned to conduct business with such companies going forward through a far quicker negotiation and contracting completion cycle. As a matter of fact, right now we're at different points in talks with a number of investment-grade hyperscalers regarding sizable capacity campuses beyond our Polaris Forge 1 campus, and one of those discussions has reached an advanced stage. Based on what we've been through, we recognize that these big, complicated lease contracts need approval at numerous levels, which makes it hard to predict when or whether any will close. Let's shift now to our Data Center Hosting segment. At present we run 286 megawatts of data center hosting capacity that is entirely under contract serving our cryptocurrency clients at two North Dakota sites. Bitcoin pricing is still robust, which is a good thing for our customers, and we stay upbeat regarding this business and what lies ahead for it. Moving on, let's talk about our Cloud Services segment, which delivers high-performance computing infrastructure for AI use cases. As we told everyone on the previous quarterly call, our Board of Directors decided we would examine strategic alternatives for this segment; that review is still underway, and we'll share an update once we have additional information to give shareholders. With that said, I'll hand things over to our CFO, Saidal Mohmand, who will go through our financials. Saidal?

Mohammad Saidal Mohmand

executive
#3

Appreciate that, Wes, and hello everybody on the line this afternoon. With the leases now signed for Polaris Forge 1, our team is busy collaborating alongside our financing partners so we can lock down the project financing tied to these data centers, something we anticipate happening sometime within the coming 4 to 10 weeks. From the close of the quarter until now, roughly $270 million has been brought in via our ATM plus our Series G preferred stock. When you add that to the substantial equity already held in the campus, our view is that this leaves us strongly positioned as we move to complete the new financing package; so let's shift focus to the quarter. Keep in mind that, absent any specific note otherwise, all the figures we're covering next relate solely to continuing operations and leave out the Cloud Services business. For the fiscal fourth quarter of 2025, revenues came in at $38 million, which marks a 41% rise year-over-year against the comparable period a year earlier. The primary driver behind this gain was more capacity brought online within our Data Center Hosting Business. On the cost side, cost of revenues climbed $7.5 million, reaching $30.2 million versus the comparable prior period. Once again, additional capacity coming online across our Data Center Hosting businesses fueled this rise. SG&A expense rose $15 million, landing at $28.1 million. Growth across the company overall drove that increase, and it included a $9.4 million jump in stock-based compensation stemming from accelerated vesting on certain employee stock awards plus expenses tied to the PSUs. Personnel expense also grew by $3.4 million, mostly because of added head count needed to support the business, and there was $2.3 million in other expenses, primarily software expenses and insurance premiums. During this quarter, depreciation and amortization expense rose to $4.1 million, versus $3.6 million for the same period in 2024. Interest expense fell $9.3 million, coming in at $4.5 million. Net loss attributable to common stockholders totaled $26.6 million, or $0.12 per basic and diluted share. Adjusted net loss attributable to common stockholders came to $7.6 million, or $0.03 per diluted share. Adjusted EBITDA for the quarter was $1 million, and a reconciliation covering these metrics appears in the press release we issued earlier today. Shifting over to our balance sheet. We closed the fiscal fourth quarter holding $120.9 million of cash, cash equivalents and restricted cash, plus $688.2 million in debt. As mentioned before, that figure leaves out an extra $268.9 million in proceeds generated by our ATM and Series G preferred stock offering, which took place after the quarter ended. Now on to guidance. In the past, we haven't offered specific forward-looking guidance. That said, because of certain near-term dynamics surrounding the core releases, we're giving some directional guidance for the upcoming quarter; we anticipate revenue will grow significantly on a sequential basis, starting in the quarter that ends August 2025, thanks to the technical fit out of our first Polaris Forge 1 building. Keep in mind, our customer covers the cost of that fit-out, with a small margin going to the company. A significant portion of that fit-out income is going to hit during this fiscal quarter, and it will also land in the period that wraps up on November 30, 2025. Keep in mind, this happens ahead of when we start recording the lease income tied to that facility. So with that said, I'll hand things over to Wes, who has some closing remarks.

Wesley Cummins

executive
#4

For the last 2 years, our focus has been on forming solid ties with just about every big hyperscaler out there, and we've shown off how well we can build by getting through what we consider to be among the toughest technical reviews and procedures that the industry's hyperscalers require. That work has led to connections with multiple hyperscalers, and those should set us up for upcoming projects. Thanks to the CoreWeave lease, we figure we're now about midway to our internal target of $1 billion in yearly net operating income across the coming 5 year — meaning over the next 3 to 5 years; we're confident we can get there, because of what we see as our edge with a multi-gigawatt pipeline, our demonstrated design and construction know-how, and solid ties with hyperscalers who look busier than ever chasing land, power and data center capacity. On the whole, we view this as merely the start for Applied Digital as we assist in shaping the future of AI and high-performance computing infrastructure, and our optimism about what lies ahead stays strong. We'd love to take your questions now. Operator?

Nick Giles

analyst
#5

To start with, I wanted to ask how we ought to view the pace of development across 2026; and I'm also curious whether there might be a period in which you could start construction on another campus, or if that would instead be a 2027 groundbreaking at a location besides Pigeon Forge?

Wesley Cummins

executive
#6

Nick. We do anticipate starting construction — and work toward that has already begun — on one more campus, and possibly two, prior to the conclusion of this year.

Nick Giles

analyst
#7

Understood. All right. Then perhaps for my follow-up, I believe you gave a window of 4 to 10 weeks regarding the financing. So I'm just wondering whether you might share a bit more detail. At this stage, which items would be the biggest bottlenecks? Alternatively, what might push things toward one extreme or the other within that window?

Wesley Cummins

executive
#8

Nick, let me start with a thought, and after that I'll hand it over to Saidal; though in my view, the main bottleneck at present during this process is simply the way activity typically decelerates during the latter portion of August before picking back up in September across the industry as a whole. Then I'll pass it to Saidal for whatever remarks you'd like to add.

Mohammad Saidal Mohmand

executive
#9

That seems reasonable to me, Wes. One more thing I'd mention: you're also dependent on outside professional firms — think about the consultants who put together construction reports, and even attorneys who can prepare paperwork and turn those documents around. So delays can always creep in from that side. That said, we've got a solid team, plus a strong lead banking partner we've already lined up, and since there's so much work ahead, that partner has every incentive to move quickly. There's a lot of enthusiasm for this area overall.

Rob Brown

analyst
#10

Congrats on everything that's been achieved. You mentioned that 1 customer is in advanced talks and is part of your big pipeline, but — can you tell us — is this the client you've already brought through much of the onboarding process, and now it basically comes down to negotiating the contract? Or just tell us where things stand.

Wesley Cummins

executive
#11

Yes. So — we'd rather not share much detail on it, Rob, in terms of — identifying who the customer is, but it's an investment-grade North American hyperscaler that we're in advanced negotiations with. So that's a fairly limited group. And — but we're holding continuing discussions with 4, 5, 6 of the hyperscalers regarding the campuses we're working on both in the Dakotas and outside of the Dakotas. But I'd say that things have sped up from that standpoint, just in the market overall over the past month.

Rob Brown

analyst
#12

Yeah. All right. That sounds good. Then regarding the Ellendale site, my understanding is that fit-out work is set to begin next quarter. What remains to be finished there? Or is it essentially just completing that fit-out and having the customer begin moving equipment into the building?

Wesley Cummins

executive
#13

Right. Fit-out is the main piece, and it's already in progress. After that, the customer will bring their equipment to the location, along with cabling and racking and cabling, and those are truly the remaining items. What we expect is that during calendar Q4 of this year, things will begin to ramp up around October through November.

Mike Grondahl

analyst
#14

Nice work on those 150-megawatt options that CoreWeave signed; and tied to that initial $250 million from CoreWeave, the 100-megawatt facility plus the 150-megawatt facility. What do the terms look like for that project financing? Are they sort of arriving in line with what you'd anticipated? Could you share any color on that?

Wesley Cummins

executive
#15

Yeah; by and large they're arriving as anticipated. I'll let Saidal share whatever specifics he's comfortable providing on that, though for me it's mostly as expected.

Mohammad Saidal Mohmand

executive
#16

Right, that's accurate. And I'd say the industry generally recognizes this for comparable financings involving this kind of tenant. Consider that with your investment grade, you're sitting around the high 2s; consider that low <<inaudible>> combined with low 4s is typically where pricing lands for a tenant of this type, along with loan-to-cost, or LTC, around 70%. That's the pattern we're observing across the market, and it's turning into something fairly standard.

Mike Grondahl

analyst
#17

Understood. Then, considering the 100 megawatts, followed by the 150 and then the additional 150, do you have approximate launch dates for those buildings?

Wesley Cummins

executive
#18

Yeah. So the initial 100, like we said, lands in Q4 of this year, then the second building — the 150 — comes in mid-26, and the next 150 arrives during the first half of '27. And Rob — pardon me, Mike, those are calendar quarters.

Mike Grondahl

analyst
#19

Understood—yet is that still moving along nicely?

Wesley Cummins

executive
#20

Indeed.

Darren Aftahi

analyst
#21

Congratulations from me too. I have a question about Building 2. From what you've said, ground has already been broken there, and I realize a substantial sum has gone into the campus overall. The timeline appears to be 12 months out, give or take. So, is that an aggressive schedule? And if things slip, do you face a penalty in the form of a credit against the lease? Or could you just walk me through what happens if you're 1 or 2 months behind with CoreWeave? Then for my second question, there's quite a bit of discussion in the release and in the white paper you authored regarding the Dakotas. I'm curious whether, apart from South Dakota, you lean toward locations where PUEs look very appealing, perhaps more so than somewhere like the Southern part of the United States. Any detail on that would be useful.

Wesley Cummins

executive
#22

Sure, Darren. Regarding Building 2, we received the latest photos from the campus today, and the building is now actually being erected, so a considerable amount of work has already been completed on the foundation and dirt work. The building is therefore going up, and going up fast, and we feel great about that timeline. As I said in the script, we've worked very hard, and the team has worked very hard over the past year to streamline what we do. So what that means is we've made a major reduction in both the total part count and our supplier base, which gives us a process that's easy to repeat and very efficient. The plan for this one is to get it up in about half the time Building 1 required. There was a lot we took away from Building 1, and beyond that, the design allows for far more flexibility, meaning a greater liquid air mix. Every tenant wants a different liquid air mix, but — on top of that, it's built with lower costs in mind. So our confidence in this project is high, particularly given that we're right in the middle of summer over there and the structure is already rising, which means it'll be closed in so we can do construction and fit out during the winter. Also, the agreement is just a typical lease arrangement, and it includes penalties for late delivery that we would be responsible for. Regarding what you mentioned about additional campuses, the Dakotas aren't the only location — our confidence in North Dakota is quite strong. There's a site in South Dakota that we've been developing, but beyond that, we have several campuses, and they're sizable ones, located in North Dakota. We've got labor available in that area. There's a general contractor we've partnered with effectively in the past. So when it comes to every component involved in North Dakota, we feel very at ease. Beyond that, clearly the fiber piece is progressing with that additional line, which is significantly boosting fiber access across the state. That said, we do have additional locations, primarily within MISO, though those extend right down to the nation's southern region too. Right now, North Dakota is the focal point of our efforts.

George Sutton

analyst
#23

Mike, congratulations to you too. So, Wes, you said hyperscalers are busier now than they've ever been. I'm asking because a few of them appear to want to control their own infrastructure. Are we discussing situations in which you'd hold the campus, as with Ellendale? Or are we discussing, in certain instances, powered shells?

Wesley Cummins

executive
#24

No. And I appreciate the congratulations. At this moment, our emphasis is squarely on full stack. That means owning the entire building and running the operations, and that genuinely accounts for all the talks and the inbound interest we're getting. Hyperscalers that self-build or use powered shells have a preference, and they always have. And when the market gets tight, they usually sign colo agreements of the type we already hold and the type we're pursuing for later on. But at this moment, George, we're holding firm on full stack colo rather than powered shell. I don't — blending a campus between some full stack and some powered shell might turn out to be interesting for us. Yet at this moment, the powered shell alone doesn't interest me much. As a public company, I don't believe it's necessarily a strong business model — perhaps more so for a private company on the powered shell side.

George Sutton

analyst
#25

Great. And regarding what you call the Dakota advantage, I'm just wondering, have you made any headway in South Dakota when it comes to the sales stack, given that it's such a critical gating item for deals.

Wesley Cummins

executive
#26

Yes. We haven't, and that's probably something for the next legislative session next year. So we're — at the moment, we're concentrating on another large campus in North Dakota, where we're in advanced negotiations, and then a campus in the southern part of the U.S. and MISO too.

Wesley Cummins

executive
#27

Wonderful. I appreciate all of you being here, and I'm eager to talk with you again in October.

Operator

operator
#28

Everyone, that brings us to the end of today's call. We appreciate you joining us. You're welcome to hang up now.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete Applied Digital Corporation transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

This call discussed

For developers and AI pipelines

Programmatic access to Applied Digital Corporation earnings transcripts and 132,000+ others is available through the EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research

OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Applied Digital Corporation or any ticker on your watchlist.

StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.