Bitdeer Technologies Group (BTDR) Earnings Call Transcript & Summary
May 14, 2026
Earnings Call Speaker Segments
Pretesh Dahya
executiveThanks, operator, and good morning to all of you. It's a pleasure to welcome everyone to the first quarter 2026 earnings conference call for Bitdeer Technologies Group. With me on today's call are Jihan Wu, our founder, chairman, and chief executive officer, Linghui Kong, our chief business officer, and Haris Basit, our chief strategy officer. Haris will kick off today's call by walking through the company's results for the first quarter, along with operational progress and strategic direction. Then I'll wrap up with an update on how we performed financially. For today's call, we've put together a supplemental investor presentation, which you can find on Bitdeer's investor relations website under Webcasts and Presentations. Before management gives their formal remarks, I'd like to remind everyone that certain forward-looking statements may be made during today's call. Such statements rest on management's current expectations and are subject to risks and uncertainties, and actual results could differ materially as a result; for a fuller discussion of forward-looking statements and the risks and uncertainties tied to Bitdeer's business, please see the company's filings with the U.S. Securities and Exchange Commission. I'd also like to point out that starting with the first quarter of 2026, Bitdeer has moved from international financial reporting standards to U.S. generally accepted accounting principles. Under this transition, Bitdeer has adopted FASB ASU 2023 to 08, which calls for digital assets held to be measured at fair value each reporting period. Movements in the fair value of our digital assets will run through GAAP net income and could bring non-cash volatility into reported earnings. We'll go into this more during the financial review. With that said, I'll hand the call over to Haris.
Haris Basit
executiveThanks, Tesh, and hello to everyone. Bitdeer showed its underlying durability and ability to weather pressure during Q1 2026. While the wider mining sector faced difficulties, our integrated model moved forward across four strategic lines of business: Bitcoin mining, ASIC development, AI cloud, and colocation data center infrastructure. Progress in every one of those areas is substantial. To begin, our output from Bitcoin mining rose by nearly 500% compared with the same period last year. Next, we introduced the SEALMINER A4 series, which leads the industry. Then there's our AI cloud revenue, which is expanding quickly. And fourth, we are far along in the effort to transform our Tydal, Norway site into what should become Norway's biggest AI data center, with a lease tenant now in the late stages of negotiation. The strengths we observe throughout our portfolio, taken together, generate optionality that truly sets us apart in this sector; we stay dedicated to Bitcoin mining and foresee considerable opportunity ahead. Meanwhile, our 3 GW of power capacity worldwide is a strategic resource that matters more and more to AI and colocation clients. During Q1, total revenue came in at $188.9 million, up roughly 170% from a year earlier, alongside Adjusted EBITDA of $14.4 million — a gain of about $60 million compared with the prior year. Tesh will walk through more financial specifics shortly. Let's begin with a look at our power and infrastructure portfolio, still the cornerstone asset beneath all that we are constructing. Throughout the quarter, we kept achieving meaningful strides across our worldwide infrastructure footprint. By the close of March, we had roughly 1.7 GW of electrical capacity operating, plus a total global power pipeline of about 3 GW. In our view, this stands as one of the biggest and most AI-ready power portfolios held by any publicly listed company in our industry, and it keeps giving us strategic optionality as appetite for large-scale compute infrastructure grows stronger. Our main sites are considerable in size, spread over several continents and regulatory regimes. They offer access to renewable energy at appealing economics, with infrastructure built to handle demanding, round-the-clock operations. Such traits are hard and slow to duplicate, and they are increasingly what large-scale AI customers want as they chase power-constrained deployments. Demand dynamics for AI data center capacity have kept sharpening over the last several months. The gap between supply and demand for AI compute has grown wider, and we anticipate this shortfall will last well into 2027 and beyond. Time to power stays a crucial factor, and we are set up to serve clients who need capacity in both the near term and the midterm in a manner that almost no other operator can equal. Given this environment, we are putting priority on colocation deals for our bigger sites, which fit best for hyperscale, neocloud, and enterprise tenants after substantial committed capacity. At our smaller facilities, we keep chasing AI cloud possibilities, bringing capacity online with contracts behind it; this layered strategy shows a disciplined deployment of capital throughout our portfolio, pairing the right commercial model with the size and traits of every site. Here's a rundown of the current status at our key development sites. Tydal, Norway continues to be the colocation opportunity sitting at the top of our list. Our subsidiary, Tydal Data Center AS, signed a formal agreement on March 30, 2026 with Data Center Installations AS, a Norwegian contractor that specializes in this kind of work, to develop the Tydal facility and convert it into an AI data center. Gross installed capacity of 180 MW will be delivered by the project, with the first phase potentially finishing as soon as December 2026. Once done, Tydal is anticipated to rank as Norway's biggest operating AI data center and, measured by installed capacity, among Europe's largest as well. Co-location usage is the primary purpose behind this facility. It has been designed to follow NVIDIA guidelines and NVIDIA reference designs closely, and it is meant to accommodate deployment of both GB300 and NVIDIA's newest Vera Rubin AI technology. What prospective tenants find so compelling about Tydal is a set of attributes that are truly uncommon. Stable baseload power made possible by 100% renewable sources, plus an excellent power usage effectiveness, or PUE, of roughly 1.1, which the cold climate and chilled water from a nearby lake make possible. The way the site was built means retrofit capital requirements are substantially reduced compared with a greenfield build. We anticipate that our remaining CapEx to finish Tydal will be significantly below what a typical greenfield data center development would cost. Most long lead equipment orders are already in place, and Bitcoin mining rigs at the site are already being decommissioned. Finalizing key equipment installation contracts and technical installation work across several of our data halls are among the near-term milestones ahead; technical due diligence has also started on behalf of our future tenants. Negotiations with a possible co-location tenant for Tydal have reached advanced stages. If these talks conclude successfully, the result would be highly regarded, well-recognized end users. Morgan Stanley has been retained as financial advisor for this project. Management's top priority is signing the Tydal lease agreement. Turning to Clarington, Ohio, we hold 570 MW of power under contract with AEP. Among publicly listed companies in our sector, this ranks as one of the biggest AI data center development opportunities in the United States. Design and preparation work at the site continues. As previously disclosed, construction timing could be affected by litigation filed by a neighboring company. Our attorneys hold a strong view that our case is well-founded and that the litigation carries limited merit. On the business front, we are assessing plans capable of mitigating the effect on our overall development timeline. We stay optimistic regarding the site's potential, and at all our Ohio sites we keep strengthening relationships with the local community and government officials. In Rockdale, Texas, our approach follows a dual track: maintaining the existing Bitcoin mining operation while building new AI infrastructure on land next door; beyond that, we are engaged with ERCOT regarding 179 MW of incremental power capacity, targeted for energization by year-end. That takes the total capacity we'll have for power at Rockdale past 740 MW. At that location, talks are underway right now with multiple possible co-location tenants. Being situated within the ERCOT market is an advantage for the Rockdale site, and the plan from the very beginning is for it to be built to handle AI workloads. Thanks to that strategy, our mining operations that produce revenue can keep running during the whole build-out instead of being halted. In addition to those 3 main sites, conversion work is moving forward in Wenatchee, Washington, plus Knoxville, Tennessee. Design and permitting efforts for turning both into AI data centers are in progress, and we're aiming to finish the Wenatchee location along with phase one at our Knoxville location in Q4. In Niles, Ohio, we're pushing ahead on developing a 300 MW site tied to the grid, with a goal of energizing it in Q4 of 2028. Ground is also set to be broken in June of this year at our 101 MW site in Fox Creek, Alberta, Canada. On top of that, we keep hunting hard for more chances to put money into land and power capacity, and we'll pass along those updates when it makes sense. The U.S.
Haris Basit
executiveBitdeer's worldwide activities keep their main center here, and that's reinforced by how much faith we have in policies that favor business and innovation, which help both AI and digital assets expand. Our dedication to growing what we do inside the United States hasn't wavered. Turning to Bitcoin mining, we kept building out our self-mining platform all through the quarter. The self-mining hash rate climbed from 55.2 EH/s when December 2025 closed to roughly 65 EH/s as we finished March. That 65 EH/s figure marks growth of over 400% compared with a year earlier; output came to 668 Bitcoin during January, 705 Bitcoin during February, and 661 Bitcoin during March. March's slight pullback versus February comes down to seasonal conditions at our facilities in Norway and Bhutan, not to any real weakening in how the fleet performs — something April's production of 783 Bitcoin makes clear. We look for that forward momentum to carry on in the coming months. There's no flattening out happening in our mining operations. Launched officially on April 7, 2026, the SEALMINER A4 series stands as the most efficient mining rigs that anyone has brought to market. The top-end A4 Ultra Hydro model runs at 9.45 J/TH. Also part of the A4 lineup are the A4 Pro Hydro and the A4 Pro Air, both at 10.9 J/TH. These units give us deployment flexibility across varying site setups and cooling environments. Among air-cooled mining rigs globally, the A4 Pro Air ranks as one of the most efficient. Work on SEAL04 to 2 chip development carries on at our design center located in the U.S. A key point: because we manufacture internally, third-party hardware markups don't apply to these rigs when they go into our own fleet. That amounts to a structural cost edge relative to other mining operators. Adding these new machines will keep lifting our fleet efficiency, which stood at roughly 16.4 J/TH as of March 31st, 2026. Gains in efficiency like that, paired with our sophisticated chip design and supply chain resources, feed straight into a lower cost for each unit of hash rate generated — meaning stronger mining margins whatever the hash price happens to be. Across the next several quarters, our plan is to take our expanding SEALMINER fleet past the mining data center capacity we already have and partner with third parties to add incremental co-mining capacity at their sites. Near term, that lets us get the most out of mining economics while keeping the flexibility to push SEALMINER sales into the year's second half when market conditions make it worthwhile. As for building SEALMINERs, prep work on our Reno, Nevada factory is moving forward. The lease for the facility is signed, applications for construction permits are in with local municipal authorities, and we expect construction to begin by Q3. Making things in the U.S. sits at the heart of our vertically integrated approach and fits with both our goal of operational resilience and the shifting trade and supply chain landscape. Our AI Cloud business has grown up — no longer a pilot service but a commercially separate, structurally appealing segment with revenue rising quickly and an enterprise customer base that keeps getting deeper. On the AI Cloud side, annual recurring revenue stood at roughly $10 million when January closed, then rose to about $21 million at the close of February, and hit approximately $43 million by the end of March. GPU utilization went up, from 41% in January to 94% in March. When the quarter wrapped up, 2,128 GPUs were deployed, spanning H100s, H200s, B200s, and GB200s, and 1,948 of those were under active external subscription. More recently, through our April production update, we shared that annual recurring revenue has now hit roughly $69 million, with more than 4,000 GPUs deployed. Longer commitment durations are what customers are signing up for, and that boosts both revenue visibility and the stability of cash flow. Starting in late 2025, hourly pricing for H100s has risen by around 40%. Demand levels are what drive this directly, and the market is taking in this increase without any meaningful friction. Such pricing power is a sign of the robust fundamentals behind our AI Cloud business. During January, we brought our first NVIDIA GB200 NVL72 infrastructure online at our facility in Cyberjaya, Malaysia. That represents phase one of a faster build-out meant to serve enterprise-grade training workloads on the Grace Blackwell architecture. In February, a managed Kubernetes service with GPU-native orchestration was introduced, giving enterprise customers scalable infrastructure for AI training and inference. Our Model Studio platform now handles over 50 leading open-source models, letting clients deploy anything from basic inference all the way to advanced multimodal applications within one managed environment. Come March, we put our integrated AI solutions on display at the NVIDIA GTC conference, which created incremental business opportunities and bolstered our brand presence in the AI infrastructure ecosystem. We are actively looking into U.S. data center leasing opportunities and anticipate bringing GPU capacity and AI cloud services online for U.S. customers in 2026. In line with our stated approach, any large-scale U.S. GPU expansion will be backed by committed customer contracts. Shifting to our balance sheet, in February, Bitdeer successfully priced an upsized offering of $375 million in 5% convertible senior notes due in 2032. We closed Q1 with cash equivalents, and restricted cash of $298 million. We anticipate that the bulk of our fiscal year 2026 total financing needs will be addressed through project-level debt financing following a signed lease agreement for our Tydal Norway site. Now I will hand it back to Tesh to go over the detailed financials.
Pretesh Dahya
executiveAppreciate that, Haris, and hello everyone; it's a pleasure to be with you, and I'm eager to connect with a lot more of our shareholders over the next several months. Allow me to take you through the specifics of our financial performance in Q1. Before diving in, I want to remind all of you that every figure here is denominated in U.S. dollars and, as mentioned previously, this marks the initial quarter we are reporting under U.S. GAAP. Beyond covering results computed under U.S. GAAP, we will also touch on specific non-GAAP financial measures, Adjusted EBITDA among them. Non-cash fair value movements on our digital assets and convertible note derivative liabilities, plus certain other items, are excluded from Adjusted EBITDA, and in our view it offers the most consistent foundation for evaluating core operational performance. For a complete reconciliation of non-GAAP measures, please consult our earnings release that was published earlier today on Bitdeer's investor relations website. Consolidated revenue for Q1 came in at $188.9 million, which is roughly $119 million higher compared to the same period last year. That year-over-year increase was mainly fueled by the considerable growth of our mining hash rate and the Bitcoin production tied to it, a reflection of ongoing SEALMINER deployment across 2025 and into 2026. On a sequential basis, revenue fell from $224.8 million in Q4 of 2025, reflecting softer average Bitcoin prices in Q1 versus Q4, along with a greater share of our manufacturing output being allocated to self-mining deployment instead of external SEALMINER sales. Gross profit totaled — $39 million, equating to a gross margin of — 20.7%. Three converging forces produced this result. To start, Bitcoin prices stayed under pressure for the entire quarter. Next, substantial non-cash depreciation expense of $70 million weighs on our mining fleet, a consequence of how quickly we have expanded. As a reminder, we now depreciate mining rigs on a three-year straight line basis, and the pace of SEALMINER deployment across 2025 and into 2026 produces a significant concurrent charge. And third, seasonal power cost dynamics at our Norway and Bhutan facilities put pressure on energy costs during Q1. Going forward, the route to gross margin recovery is clear. Deploying the A4 series brings down our cost per Bitcoin mined. Normalization of rates in spring and summer lowers electricity expenses. Scaling AI cloud revenue enhances margin composition as that segment expands. Adjusted EBITDA reached $14.4 million for the quarter, up roughly $60 million versus the prior year. The sequential drop from $24.3 million in Q4 of 2025 mirrors the gross margin dynamics outlined earlier. Operating loss for the quarter stood at -$159.5 million, and earnings per share came to -$0.68. Net cash used in operating activities was $346.9 million, a 42% reduction against the Q4 net cash used in operations of $594.7 million. Lower SEALMINER supply chain and manufacturing costs were the main drivers of that sequential reduction, partly offset by increased electricity costs. Moving to the balance sheet. We closed Q1 with $297.7 million in cash equivalents and restricted cash, up from $177.9 million at the end of 2025. Total borrowings as of the close of Q1 were approximately $1.92 billion. Looking ahead to the whole of 2026, we're restating our projection for infrastructure capex tied to building out crypto mining data centers, landing somewhere between $180 million and $200 million. That figure applies purely to crypto mining infrastructure — it leaves out CapEx connected to SEALMINER hardware, GPUs, AI cloud, or colocation development. On top of that, we expect our mining hash rate to keep climbing, though the pace should be gentler than what we saw across the two quarters before this one. To wrap up, Q1 of 2026 stood out as a period of execution and strategic progress. Gross margins faced pressure stemming from a mix of a weak Bitcoin price, the depreciation accounting effect of growing our fleet, and power costs typical of the season. Those pressures won't last, and the catalysts that should restore margins down the road are concrete and moving forward: A4 deployment, power costs settling back to normal, colocation, and expanding our AI cloud. With all of that as our backdrop, we hit the milestones that will shape the value we intend to create in the quarters to come. We rolled out the SEALMINER A4. Our AI cloud ARR jumped 105% within just one month. We brought on a construction partner for Norway's biggest AI data center. And we bolstered our balance sheet by raising $375 million in fresh capital. The co-location opportunities in front of us are considerable, and we're chasing them with the entire organization's attention. Heading into Q2, we carry solid operational momentum, a distinctive asset base, and a team that's proven it can execute at scale. We're excited for what's coming and stay dedicated to generating long-term value for our shareholders. Thank you. Operator, please open the call for questions.
Greg Lewis
analystYes. Hello, and thanks — good morning, good afternoon, and I appreciate you fielding my questions. Haris, I understand we're in advanced talks regarding Tydal in Norway. That said, I'm curious about your thinking there. In the remarks, design and planning come up. Given that some customers share expectations for a data center while others differ, how far can we take the final design? Do we then have to wait on the customers to proceed? Thinking about the Norway opportunity — I know hyperscalers come up, but how significant is that? There are large tech Scandi firms that wouldn't be seen as traditional hyperscale by some, yet they're big technology players in Northern Europe. I'm just wondering whether you can offer any color on those questions about that opportunity.
Haris Basit
executiveOkay. Sure. Thank you, Greg. On the precise technical specs, customers differ, since each wants different machines installed — GB300s versus Vera Rubins, and how those machines are mixed. Still, I'd say we hold the vast majority, nearly all, of the design. We continue talking with the probable tenant, the party we're closest to signing, to confirm every design element satisfies their needs, which end up being quite near the NVIDIA reference designs. We believe that's well under control. Discussions continue, though right now they concern only very detailed matters. As for the tenant type, the two key items are a highly solid credit — an investment grade customer or a strong credit wrapper. That matters. Naturally the economics matter too, and those two things are our focus. Should it proceed as we anticipate within the timeframe we anticipate, I think investors ought to be fairly satisfied on both matters. I can't reveal much else about the tenant, but I believe we'll be able to announce that deal before long.
Greg Lewis
analystThanks for that. I was hoping to ask about Clarington. In the press release—actually, in the prepared remarks—you brought up, you know, possibly certain delays that are occurring, and we understand that it's active. Could you give us at least, like, a general picture of what's really going on? I mean, yeah, that caught us off guard, so we're just trying to get it.
Haris Basit
executiveMy apologies—which site do you mean?
Greg Lewis
analystWhat are some of those headwinds that you're going to have to deal with?
Haris Basit
executiveWhich location do you mean?
Greg Lewis
analystOh, my mistake there — Clarington.
Haris Basit
executiveAh, right, Clarington. So, as we put out previously, there's the litigation news.
Greg Lewis
analystYes.
Haris Basit
executiveregarding the site, we continue to work our way through it. As you might expect, we anticipate that the construction timeline will be affected. Beyond that, there isn't much additional detail I'm able to provide. We're examining approaches to reduce those effects.
Greg Lewis
analystSo what I'm really trying to get at is this — the power side already has its approval, which means whatever the holdup is would presumably sit more with land use, or is that roughly the way it works?
Haris Basit
executiveRight — power isn't actually where the issue lies.
Greg Lewis
analystOkay.
Haris Basit
executiveI'll say. Yeah.
Greg Lewis
analystFine, that works. Appreciate it, everyone.
Haris Basit
executiveThanks, Greg.
Mike Colonnese
analystHello, and good morning, everyone. Thanks for fielding my questions, and it's great to witness all the advancement taking place throughout your various business segments. So Tydal appears to be moving along well. I wanted to ask whether you might share some additional detail regarding Rockdale. From what I understand, you plan to build a brand-new AI data center at the same time as running your Bitcoin mining activities at that location. Could you discuss how much client interest exists for that particular asset? It seems like a truly distinctive opening because of the power capacity, and also what the development schedules might eventually look like for that portion of the portfolio as an AI co-location prospect.
Haris Basit
executiveYes. In my view, it's somewhat soon to forecast the precise development schedule for that. For AI, it's a highly appealing site. One factor that would make it even more appealing is having additional land, and that's what we're currently pursuing at that location. The power is available there, and it will be broadened to an even bigger power envelope, exceeding 700 MW. For AI, it's a solid location; we're in discussions with multiple prospective tenants at that site. They range from hyperscalers to neo clouds and even a few others. The demand level, I believe, is extremely strong. I don't think I can offer a solid timeline yet for executing that site; we're pressing ahead with at least ensuring we possess suitable land area where the AI data center can be built while the Bitcoin mines continue to run.
Mike Colonnese
analystUnderstood. That's really useful context, Haris. Thanks for that. So staying with AI, though shifting toward the cloud operation, which is clearly expanding quite rapidly when you look at GPU rollout and usage levels. I'm just trying to figure out how sustainable that revenue actually is. Clearly the utilization figures are a big help, but it would be great if you could give us more detail on the contracted portion of it. And beyond that, if you have any kind of internal targets you're aiming at to scale that business during this year. Obviously there are several business lines you're juggling, but when you consider growing the GPU count beyond roughly 4,000, which is where you stand right now, what's the best framework for investors to use there.
Haris Basit
executiveYeah. My view is that demand for GPUs is enormous, and on our end the constraint is really just how fast we can get those GPUs and AI cloud sites up and running. The demand exists. It spans every segment. As we said, we managed to increase pricing on our H100s by 40% and still had no trouble filling those. Longer term contracts are beginning to come in as well. I'm not sure — Jihan, is there anything you'd like to add there?
Jihan Wu
executiveOh, alright. I’ve turned my mute off now. Okay. At present, the bulk of our agreements are long-term ones. Most of our machines are tied up in long-term contracts. Currently, customers have to come to an agreement with us on specific terms, typically 3 to 5 years.
Mike Colonnese
analystUnderstood. That's really useful context, everyone. Thanks for letting me ask.
Haris Basit
executiveAppreciate it, Mike.
Analyst
analystHi everyone, Logan here filling in for Mike. We appreciate you taking our question. To start, could you share any details about how the discussions are going regarding pricing and terms over in Norway, plus give us a sense of what obstacles still remain before a lease can be signed at that location? Thanks.
Haris Basit
executiveSure, I doubt we'll be able to satisfy you on the pricing front, beyond saying that in our view it sits close to the highest end of the market compared to what has been publicly announced. We believe it will turn out pretty strong. We'll see. As for what remains, it's simply a great deal of granular work; we're currently in the later or more advanced phases of working out the lease agreement, and there are merely numerous minor specifics. Nothing major is blocking progress. Still, every one of these tiny items must be resolved prior to having a completed, executed lease. And no, there isn't any single issue creating an obstacle at this point. We're pushing to go as quickly as possible; this ranks as our top priority throughout the management chain here, and we're dedicating an enormous quantity of resources toward it. It's simply that an extensive amount of detail has to be addressed.
Analyst
analystUnderstood. That's really encouraging regarding the favorable pricing. Then, one additional item: during your April update, you noted that several other locations besides Norway, Clarington, and Rockdale are in advanced-stage negotiations. Is now the right time for you to publicly identify those locations by name? If that isn't possible, could you at least offer some insight into how demand for your locations has shifted across the past 90 days? Thank you.
Haris Basit
executiveYes, I'd say over the past 90 days it held steady. It's been, you know, quite robust throughout. I can't really say whether it has become slightly stronger or not, but certainly we haven't observed any weakening. Yes, we aren't able to disclose the timeline for any of the remaining locations regarding co-location. For the AI cloud locations we've already announced, you know, Q4 of this year for Wenatchee and the initial phase of the Knoxville, Tennessee location. Was there anything else beyond that you were hoping to learn?
Analyst
analystNo, that's all good.
Haris Basit
executiveOkay.
Analyst
analystUnderstood. Thanks, everyone, and congratulations on a strong beginning to 2026.
Haris Basit
executiveThank you, Logan.
Kevin Cassidy
analystYes. I appreciate you answering my question, and congrats as well on everything you've accomplished. Turning back to the AI cloud — it's really impressive that you managed to lift hourly pricing 40% for the H100. What direction does that go as you move to GPUs with greater performance? What sort of increase in the hourly rate ought we to anticipate?
Haris Basit
executiveSince I lack a solid sense of that, perhaps I'll have Jihan field it.
Jihan Wu
executiveOkay, so in the past, the contracts we signed were generally short-term ones. Once those agreements ran out, we got the chance to increase our pricing. At present, a large portion of our GPU cloud business sits under longer-term agreements. Going forward, the pricing should stay fairly steady. Yeah.
Kevin Cassidy
analystOkay.
Haris Basit
executiveI guess your question.
Kevin Cassidy
analystGot it. Okay, thanks.
Haris Basit
executiveIn what way does that rate vary between the top-tier systems and the H100, is that right? Something along those lines, or?
Jihan Wu
executiveYeah. Yeah.
Haris Basit
executiveYeah.
Jihan Wu
executiveWe, yeah, if we-
Haris Basit
executiveBetter leverage.
Jihan Wu
executiveYes. When we move up to higher-end GPUs, that means bringing fresh GPUs online. At this point, every one of those agreements is still being negotiated, while we get the data centers ready and handle the installation. Broadly speaking, what we're sensing is that on the demand side, customers are competing quite hard. We had to be selective about which clients to take on so things stay steady and remain profitable; that's the trade-off we have to consider. Honestly, on the whole I feel pretty positive about how profitable the GPU rental cloud business can be, since customers are ready to pay a solid price for access to those GPUs.
Kevin Cassidy
analystGot it. Alright, thanks. I suppose asking about SEAL04 — that second iteration — is basically a requirement for any Bitdeer earnings call. You said work continues on it, so can you share any schedule, along with what joules per terahash you're aiming for?
Haris Basit
executiveThe goal remains the same, and we aren't in a position to give a new timeline for it at this point. Apologies for that.
Kevin Cassidy
analystAll right. I felt I had to raise that one regardless.
Haris Basit
executiveRight. Honestly, I figured it would come up before anything else. Yeah.
Kevin Cassidy
analystOkay. Thank you. Congratulations.
Haris Basit
executiveThanks.
Nick Giles
analystThank you, operator. Morning, everybody. Perhaps as a follow-up to a question asked before, regarding the point at which, for some of these remaining locations, you'd be ready to, well, construct for co-location needs, and how much CapEx that would involve? Do you have a ballpark figure for the CapEx you've spent so far on converting things to co-location throughout the platform?
Haris Basit
executiveOur CapEx for co-location conversion hasn't been announced or disclosed, beyond saying that the capital needed in Norway is significantly lower than what is typically required. At other locations, meaning the U.S. sites, we anticipate CapEx needs will be nearer to the standard amount for building an AI data center; some of the savings achieved in Norway can be realized at other locations too, though not to the same degree.
Nick Giles
analystGot it. Thanks for that, Haris. Perhaps shifting topics for a moment — regarding the location in Reno, Nevada, that facility, the ASIC one — do you have any early ballpark figures for what the CapEx might look like there? And in what way, if any, would that affect the margin profile of that business?
Haris Basit
executiveYes. Just as a reminder to everybody, that is where we put together ASIC mining rigs. Jihan, could you address that?
Jihan Wu
executiveNot at this point.
Haris Basit
executiveRight. The figure for how much money that location needs hasn't been disclosed by us; as you know, it's a good deal less than what a facility such as a data center would call for, or even what a Bitcoin mining site would call for. What else was in that question?
Nick Giles
analystR-really-
Haris Basit
executiveOh, no.
Nick Giles
analystHonestly, this was simply out of curiosity, as you know.
Haris Basit
executiveRegarding the margin—
Nick Giles
analystWhen it comes to how that business performs on margin.
Haris Basit
executiveRight.
Nick Giles
analystYeah.
Haris Basit
executiveSo, constructing in Reno is going to cost somewhat more than doing so in Asia, or putting things together there. That said, you know, the bulk of what we pay for our mining rigs is actually tied up in the silicon, which, you know, TSMC still produces at the same site. As a result, we figure the added expense of doing assembly in the U.S. is going to be, you know, offset by things such as tariffs. So we believe it will be an excellent spot for us and, staying within a sensible price bump over manufacturing in Asia, particularly when you factor in tariffs.
Nick Giles
analystGot it. Okay, many thanks, Haris.
John Todaro
analystHi, everyone. Appreciate you fielding my question. Nice work on what's been achieved up to now. I suppose, turning back to Rockdale and Clarington, clearly certain items remain unfinished there before development can proceed. From what I gather, it's largely about acreage. So what are the main constraints in those spots? Are we simply in the middle of talks over that? Is more money required from you to finish those things? I'm just attempting to grasp this a bit more clearly so we can gauge how much further we might get.
Haris Basit
executiveWell, one way to look at it is that the quantity of power, say at Rockdale, far exceeds the quantity of land, correct? That's a, you know, matter we intend to fix. It's precisely around such matters that we want to confirm we can put all the power we possess at those sites to full use. Naturally, at Clarington, the litigation adds another layer of difficulty.
John Todaro
analystAlright, got it. Appreciate it. So moving on to the topic of selling Bitcoin mining machines. Clearly, a large number of publicly traded U.S. miners are scaling back as they pivot toward AI HPC. Your company has done somewhat more outside sales into global markets. I'm curious how this alters the approach to sales. Does it work in your favor rather than against you that more publicly traded, U.S.-centered miners are reducing activity, and perhaps that opens up greater chances for international sales? I suppose I'm just attempting to, yeah, lay out how this affects external sales over a somewhat longer horizon.
Haris Basit
executiveSomething I'd like to point out is that right now we aren't truly pursuing external sales all that aggressively. As you know, practically the entire output goes to our own data centers for internal use. As you noted, we do make sales abroad. The reality that many U.S. mining firms are scaling back is not as — it carries a somewhat softened effect because of that. I'm not sure. Jihan, would you like to add anything regarding Bitcoin mining ASIC sales or demand?
Jihan Wu
executiveAt the moment, thanks to a steady flow from our semiconductor fabrication service, our plan is to grow our self-mining operations. In my view, self-mining is a business that makes money as well; we still hold some Bitcoin mining sites that haven't been sold; we also have many partners interested in forming co-mining partnerships with us, meaning we supply the Bitcoin mining rigs while they supply the Bitcoin mining farm, allowing us to split the Bitcoin mining hash rate, and we would take the larger portion of it. On the mining partnership side, the electricity bill has to be transparent, with no markup. Mm. It scales rather well. At present, we aren't pushing hard to sell the mining rigs. The Bitcoin price right now remains in a bearish situation. Should we sell the mining rigs, I think we would be forced to do so at a terrible price. Expanding our self-mining, in my opinion, is the most economical choice for our company.
John Todaro
analystGot it. That helps. Yeah, the main emphasis is, as you know, mostly in-house. All right, appreciate that, guys. Thanks.
Haris Basit
executiveActually, I believe it's Tesh. Tesh, would you like to offer any final thoughts?
Pretesh Dahya
executiveYeah. I think we simply want to express our appreciation to everybody for being on this call. You know, we're coming out of Q1 with obvious operational momentum in place, a strategy that's focused, and we're truly moving decisively when it comes to executing on our pipeline for AI infrastructure. Thanks for being with us today. We're eager to keep generating sustainable value creation over the long term.
Haris Basit
executiveThank you, everyone.
Operator
operatorEveryone, that brings us to the end of today's call. We appreciate you joining us. At this point, you're free to hang up.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Bitdeer Technologies Group transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →This call discussed
For developers and AI pipelines
Programmatic access to Bitdeer Technologies Group earnings transcripts and 132,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Bitdeer Technologies Group or any ticker on your watchlist.
StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.