Jennifer Drew-Bear
executiveThanks, and welcome everyone to the conference call for Bitfarms' Fiscal Year 2025. Joining me today are Ben Gagnon, our Chief Executive Officer and Director, plus Jonathan Mir, who serves as Chief Financial Officer. Before we get started, I want to point out that this call is being webcast alongside a slide presentation. You can find today's press release and our presentation on our website in the investor section. If you turn to slide two. I want to remind everybody that during this call, certain forward-looking statements will be made, and future results could differ from what those statements imply. This forward-looking information rests on certain assumptions and carries risks and uncertainties. For the full list, I'd point you to Bitfarms' 10-K. You should also know that we'll be referencing some non-GAAP financial measures, and as a result those figures might not line up with comparable measures that other companies report. We ask those listening to check today's press release along with our 10-K, where you'll find definitions of these non-GAAP measures and how they reconcile back to GAAP. Keep in mind that unless we say otherwise, every financial figure we cite is in U.S. dollars. Moving now to slide three, I'm happy to turn things over to Ben Gagnon, our Director and Chief Executive Officer. Ben, over to you.
Ben Gagnon
executiveMorning, everybody, and thanks for joining our earnings call covering Fiscal Year 2025. In 2025, we took a decisive step: we exited our legacy Bitcoin operations and set out to construct North American infrastructure for the next wave — HPC and AI. This was a year of intentional, high-stakes change, guided by a clear set of priorities: lock in a North American pipeline, shore up our balance sheet, speed up site development, and put ourselves in a position to court customers from a standpoint of operational strength at the very moment the energy crunch is holding back AI's expansion. I can state with both confidence and pride that we achieved precisely the goals we had laid out. What you're looking at right now — the way our capital is structured, the locations we hold, the people we've brought together, the plan we're executing — all of it came from intentional decisions, was put together with rigor, and exists to move us ahead. We implemented core structural shifts to put the business in a new position, and we directed all of our attention toward developing HPC infrastructure in North America. Nothing done by halves, nothing given up, and eventually, no Bitcoin at all. We assembled an entirely new enterprise, and although the name on the door today is Bitfarms, starting tomorrow we begin our life as Keel Infrastructure. The name tells you everything. On a ship, the keel sits at the very bottom of the structure — it's the piece that holds everything steady and keeps the vessel pointed the right way no matter what conditions exist above the water. It's structural, it's vital, and that's precisely how we view our part in the HPC and infrastructure space. Our aim isn't to go head-to-head with hyperscalers or Neoclouds. Our aim is to make them succeed. Essentially, we deliver that crucial, largely invisible foundation that allows the most advanced AI platforms in the world to deploy on time and expand without interruption. Tomorrow, April 1st, we expect to wrap up the re-domiciliation and put the finishing touches on the rebranding, and two business days after the deal closes, trading under the Keel ticker will start on the Nasdaq and the TSX. We step into this next chapter from a place of real strength. Keel holds more than 2 GW in its pipeline, making it a leader in the region, with power land portfolios that rank among the biggest in the highest-demand markets across North America, plus the financial muscle to carry out our plan. Right now our liquidity sits well above the CapEx we've budgeted to carry us through permitting and eventually into signing leases, which hands the company considerable financial flexibility to pursue our strategy. That strategy is just as straightforward. Every one of our site and campus developments is being designed as either a powered shell or a colocation facility. That, we believe, is where the greatest value for shareholders can be delivered while serving prospective customers at the speed and to the specs they require. Originally, alongside colocation, we were looking into whether pursuing a modest amount of GPU-as-a-service made sense at our Washington location, Moses Lake, since the power there is the cheapest for data centers anywhere in the country and the footprint is comparatively small, and we thought it might be a path to extra shareholder value. Since the previous quarterly call, the number of prospective customers we've talked with has grown; those discussions make it obvious that colocation represents the most accretive business model for that site; this isn't unique to Moses Lake and holds true for each of our remaining sites too, where demand runs even higher; our focus will stay on our strongest suit, serving as an infrastructure developer and owner. That aligns squarely with our core competencies. Ours is a group of developers bound together by disciplined action, creating cost-effective, institutional-grade infrastructure as quickly as customers need it. The same strengths that let us create our energy platform—moving quickly to market, staying disciplined with capital, and running operations tightly—are precisely what HPC and AI rollouts require today; this is just the natural continuation of what we already do well. With all the pieces in place and our investors showing tremendous support, casting over 99% of votes in favor of the HPC and AI shift, the U.S. re-domiciliation, and the name change, starting tomorrow, our company becomes Keel Infrastructure. Turning to slide four. When we began this pivot, we assembled a three-year transformation plan, and as of today, we're nearing the halfway point in completing it. Throughout 2025, we did the difficult groundwork that underpins our transformation. That included buying Stronghold, securing extra power capacity in Pennsylvania, shifting the portfolio's balance toward North America, an oversubscribed $588 million raise done entirely with institutional investors, our move to U.S. GAAP, establishing a New York headquarters, and assembling a fresh executive team. All of that is now finished. We've locked down power and land in several of the most important power markets, we've got a group of in-house specialists plus strategic partners who've constructed data centers for the biggest corporations on earth, and our balance sheet is structured to carry us through 2026; that puts us in a strong position to keep advancing our site development and hit the schedules our prospective hyperscalers and Neocloud customers require. Execution is the entire story for 2026. Starting tomorrow, our re-domiciliation to the United States will be finished and our official rebranding as Keel Infrastructure will take effect. We've hit two major milestones that position us well for the next phase of growth. With those now completed, we expect the upcoming significant achievements to come from executing on our developments at Panther Creek, Sharon, and Moses Lake. There, we're moving at full speed and focused intensely on three simultaneous active work streams. The first involves finalizing permits, which we expect to wrap up in the coming months. The second is the architecture and engineering work currently underway, which stays in sync with the ongoing customer conversations and what they need. And the third, of course, is our go-to-market push to secure highly financiable leases with investment-grade tenants. Commercialization efforts are already going well. The milestones ahead that investors should look for are finishing pre-construction items such as permitting, making headway in customer engagement, and eventually signing leases, which we're confident we can pull off this year and which will serve as major catalysts.
Ben Gagnon
executiveWe also anticipate that 2026 will be the year we move past Bitcoin and Bitcoin mining. We're likely among the earliest miners to start winding down our exposure to Bitcoin mining so that capital can be redirected into HPC and AI infrastructure, and during 2026 we'll speed up those efforts as development at our sites moves forward. Delivery defines 2027; that's when we expect sites to come online, megawatts to start flowing to customers, HPC and AI revenue to genuinely get underway, and our transformation into a top-tier North American HPC and AI infrastructure provider to be finished. As 2027 closes, our expectation is that Keel will stand as a proven infrastructure developer and a regional leader spanning Pennsylvania, Washington, and Quebec, and from there we'll simply keep growing and scaling in 2028 and afterward, reaching beyond 2 GW as we execute on our expansion capacity. Let's move to slide five. When it comes to HPC infrastructure, everything hinges on power, location, and timelines. What we hold is both scarce and valuable: secured power, land, and expansion capacity across Pennsylvania, Washington State, and Quebec — several of the markets experiencing the strongest demand and the highest barriers to entry. We understand this, and so do the tenants we're talking to. For hyperscalers and Neoclouds, our campuses answer their toughest scaling challenges. On location, we offer proximity and fiber connectivity into major metro areas and data center clusters, which addresses latency concerns and puts our tenants close to their own customers and to other data centers. On timelines, robust secured power for 2026 and 2027, plus expansion capacity in 2028, is extremely sought after when energy capacity is difficult to obtain and waiting lists stretching multiple years are standard. Tenants gain value because they can deploy years sooner by leasing from us instead of investing in building out organically. Then there's energy efficiency and cool climates — the lower the PUE, the more critical megawatts you get. Panther Creek illustrates nicely how hyperscaler and Neocloud appetite plays out. Interest in that site was already substantial last year, but inbound customer activity jumped once we locked in zoning during February. That's no accident. It's a proof point we've been highlighting for the past year, though it may still puzzle some investors; let us be clear — investment-grade tenants place real value on de-risked sites where the path from lease to revenue is fast. The further we advance, the stronger our leverage. Stronger leverage means better leases, and better leases mean more long-term shareholder value. Let's turn to slide six. There's no disputing that power is the binding constraint on AI infrastructure deployment and will stay that way in the years ahead. Major investment banks — Goldman Sachs, JP Morgan, Wells Fargo, Guggenheim, Moelis — have all published extensively on the subject. The consensus is unambiguous. New power generation simply cannot come online quickly enough to satisfy AI demand now, tomorrow, or over the next five years. This bottleneck is structural in nature, not cyclical. Hyperscalers and Neoclouds who once made plans looking out one year are now committing to supply chain agreements spanning 24 to 36 months. These aren't tied to particular projects — they're platform-level arrangements — and these players are now fiercely battling for both power and land so they can deploy. You likely already know this, but here you can see a breakdown of the five development sites, the power we've locked down, and in certain cases, the additional power possibilities that together form our 2.2 GW pipeline. Moving to slide seven. I'd like to briefly frame our present valuation, since a substantial gap exists between the level at which we currently trade and the worth we're set up to realize as a business. When we compare our present valuation to that of our peers, everything comes into focus. At roughly $1.9 million for each available megawatt of secured 2027 capacity, we're being valued in the middle of a Bitcoin miner group, which trades at about $1.7 million-$2.1 million per 2027 megawatt. That means the market values us for possessing power, rather than for what we intend to do with that power. For those holding our shares and bonds, we identify three separate catalysts, and each one could produce significant re-ratings. The first is clearly lease execution. Throughout our sector, businesses with signed leases command $4 million-$6 million per 2027 megawatt. That's a two to three times premium over our current level. This is the market's steady signal, caused completely by lease execution. Not facility delivery, not revenue generation — merely signed leases. A signed lease locks in revenue and financing, lowering the risk on these developments. The market compensates for that; with close to 500 MW being actively commercialized right now and clear visibility on permitting at Panther Creek, Sharon, and Moses Lake, this catalyst sits comfortably within reach. The second catalyst, and possibly the strongest one for long-term holders, is locking down our expansion capacity. Two-thirds of our 2.2 GW portfolio, or about 1.5 GW, consists of expansion capacity, to which we believe the market assigns little or no value. Although locking down these megawatts is a process that will require additional time, we believe more megawatts can be obtained during the second half of 2026, needing very little CapEx while representing considerable embedded value as powered land even prior to any lease being signed or any shovel hitting the ground. The third catalyst is delivering in 2027. Once facilities have their risk reduced through commissioning and start producing revenue under long-term contracts, development risk ought to fall sharply and the operator valuation figures become transformational once more. We aren't taking a leap of faith regarding technology, our capacity to steer power, or market demand. The tech is here. The power is secured. The sites are advancing. The inbound demand is real. The market hasn't yet factored in what occurs when a developer turns into a counterparty as we shift from advancing sites to executing leases. That represents the biggest chance in front of us to speed up permitting, get leases signed, lock in our capacity for expansion, and in the end deliver for our customers. That's the path to generating value for shareholders and bondholders alike. Moving to slide eight. Six key areas shape our execution plan, and each one backs our capacity to deliver at the pace and scale tomorrow's customers will demand. First, we've locked down a deep talent bench, bringing aboard more than 60 years of infrastructure and development plus over 50 years of data center construction experience combined within only the last few months. These are people who've delivered at scale for the world's most demanding customers. Jonathan Mir came on as CFO, carrying 25 years of expertise in energy infrastructure strategy and project finance; we've also brought in an SVP of construction and of power, a VP of HPC operations, and a head of permitting to oversee how these critical functions get executed; the right team is now in place to carry out our vision. Second, we're bringing the right industry leaders on as partners. T5, Turner Construction, Corgan, CWT, Vertiv. These companies have constructed data centers for the largest hyperscalers on earth, not just once, but hundreds of times.
Ben Gagnon
executiveWhen people check out the partners we're working with on these projects — and those will be up on the new site once it goes live tomorrow — they'll notice we've put together the right group to make sure we get stronger results. Then there's the third thing: we've got the money we need to get our sites to market. Our liquidity as of March 27th, 2026 comes to $520 million in cash and Bitcoin, and our expectation is that this is far beyond the CapEx we've budgeted to reach a lease at Panther Creek, Sharon, and Washington. Jonathan will walk everyone through our capital position and financing strategy in more depth in a moment, but the bottom line is straightforward. We have ample funding and we can move quickly. Number four: a disciplined Bitcoin exit. Obviously, we're not a Bitcoin miner anymore. That said, because our liquidity is strong and robust, we're able to take a disciplined approach to exiting; we'll keep operating right up to when the sites must be prepped for construction, squeezing out as much free cash flow as we can prior to selling the miners; and we'll sell Bitcoin into strength when the opportunity arises, capturing and reinvesting each dollar possible into HPC and AI infrastructure. Fifth: power assets nobody can copy. The megawatts we hold are located in areas where entry barriers are big. Multi-year wait lists exist in Pennsylvania, Washington State, and Quebec. Nobody gets to skip ahead. The 350 MW we have at Panther Creek, 110 MW at Sharon, and 18 MW in Washington were all locked in before the AI demand wave turned these markets into highly sought-after locations. This is power that others can't simply duplicate, which hands us an advantage over competitors when it comes to top-tier tenants who know these markets well and want assets such as ours badly. That brings us to point six. What creates value in this market is speed to power. For the customers we serve, delayed deployment carries an enormous opportunity cost, so bringing capacity online as fast as we can is the priority. Revenue is lost with each day of delay. Consequently, availability of power and certainty that we can deliver are what primarily shape lease economics. Since our Q3 call, this dynamic has driven lease rates up, just as we predicted. Keel Infrastructure has a genuine opportunity here. The assets are in place and our team is prepared. What we built in 2025 makes me incredibly proud, and I have full confidence in what we'll accomplish in 2026 and 2027. With that, I'll hand the call to Jonathan.
Jonathan Mir
executiveAppreciate that, Ben. Moving on to slide nine. It's been five months since I came aboard. My attention has gone toward refining how we handle capital allocation, making our balance sheet and capital structure more robust, and making sure financing moves help build shareholder value over the long haul. I've enjoyed a front-row view of how deep the talent runs, how disciplined operations are, and how much strategic momentum exists throughout Bitfarms. I collaborate closely with our operations and development groups, partly to grasp where our assets are currently headed and partly to keep our capital plans matched with what lies ahead. What impressed me most is the remarkable potential we hold, powered by the caliber and promise of our sites, a solid balance sheet, the strongest liquidity we've ever had as a company, and a wide-ranging team that is thoroughly engaged and dedicated to excellence; we are acting fast and with clear intent. It's a pleasure to be here with all of you today and talk about the headway we're making. I'll take this time to go over how we performed in fiscal year 2025 and lay out our present capital approach, which we think underpins the accretive growth we're aiming for in 2026 and afterward. Now to slide 10. Before we get into the quarter's financials, let me quickly set up how the results are being shown this quarter. Starting with Q3 2025, the Paso Pe facility in Paraguay is now categorized as held for sale. Consequently, every revenue line, operating cost, and asset balance tied to Paso Pe gets reported as discontinued operations within our fiscal year 2025 financials. Whenever I mention continuing operations, I mean only our North American platform, which is the bedrock of our shift into HPC and AI infrastructure. With that said, fiscal year 2025 revenue came to $229 million, a 72% rise year-over-year. For fiscal year 2025, we posted an operating loss of $150 million. That figure takes in $98 million in non-cash depreciation, along with $28 million of impairment charges. Compare that with our 2024 operating loss of $28 million, a number that itself included $102 million in non-cash depreciation and $4 million of impairment charges. Our net loss for 2025 came to $209 million, which works out to a $0.38 loss per basic and diluted share. In 2024, the net loss was $7 million, or a $0.02 loss per basic and diluted share. Several things account for the difference between 2024 and 2025, including changes in the fair market value of digital assets, driven mostly by Bitcoin's price decline as well as by gains we recognized when Bitcoin was disposed of during the year. Two other items also affected how the two years compare. To begin with, we recorded a $68 million loss stemming from movements in our derivative assets and liabilities. Next, impairment charges in 2025 came in $25 million above what they were in 2024. Across the year, adjusted EBITDA stood at $29 million, against $31 million for 2024. On to slide 11. 2025 was intentionally a year of optimizing and improving the balance sheet, laying groundwork for the growth phase that comes next. We managed to complete an oversubscribed $588 million convertible offering, which widened our liquidity considerably. Back in February, we paid off the Macquarie debt facility. Doing that cleared out our old debt, simplified how our capital is structured, and freed the company from covenant restrictions. Every one of those benefits supports our push into HPC infrastructure. We had originally drawn on the Macquarie facility to accelerate work at Panther Creek, funding important project activities like buying long lead time items and doing substation work. Paying off that facility was a strategic decision — it makes the balance sheet stronger and opens up room for us to secure financing on better terms, whether at the parent level or the project level. At present, we're holding $520 million in cash. That funding allows us to advance Panther Creek, Sharon, and Moses Lake all the way through lease execution without going to the capital markets for more money — although if appealing chances arise that would boost our capacity to produce the strongest achievable long-term risk-adjusted returns for shareholders, we may pursue them. Macquarie proved to be an excellent ally, and we appreciate the backing they gave us during such an early stage of our shift into HPC AI infrastructure. Let's turn to slide 12. As we move toward commercializing our development sites, our financial approach is straightforward and built on three pillars: capital allocation, capital formation, and capital structure. Taken together, these are designed to generate the strongest achievable long-term risk-adjusted returns for shareholders. Starting with how we allocate capital: we direct funds toward initiatives whose profit potential exceeds their weighted average cost of capital. From operations that sit outside our core focus, or that deliver subpar returns, we pull capital away, redirecting it toward investments offering better yields. Moving on to capital formation: our approach to financing is designed to support our exceptionally large avenues for growth, all while preserving the liquidity required to keep a dependable operational foundation. Regarding how we carry out financing, we'll seize favorable openings as they arise. For building out our data center projects, the funding will come through debt at either the project or parent level, alongside equity or equity-linked offerings at either the project or parent level. We are staying disciplined, and right now we have strong capitalization, which lets us move forward on commercializing and signing leases at Panther Creek, Sharon, and Washington. Turning to point three, our capital structure. The way we've set up our capital structure is meant to secure the strongest long-term returns for shareholders on a risk-adjusted basis, while keeping the company flexible overall and backing our growth. What we're aiming for is a purposeful approach to liquidity, so that we can make sound commercial calls and smart capital allocation choices, instead of letting liquidity constraints dictate our schedule. Zooming out, our path forward is well defined. Our focus is on constructing an HPC AI infrastructure platform with a regional emphasis and strong growth, built on prudent use of capital, a healthier balance sheet, and a development pace designed to boost returns while lowering risk; funding is secured through the crucial stages that reduce risk, including permitting and leasing at Moses Lake, Sharon, and Panther Creek; as we move into 2026, we carry momentum, flexibility, and a financial structure built for expansion. Our team, holdings, cash position, and approach are all in place, and we're set up well to secure for our investors the long-term value opportunities that exist right now. That said, I'll hand things back to Ben for his closing comments.
Ben Gagnon
executiveAppreciate that, Jonathan. Just over 12 months back, when our team started actively weaving AI into our operations and our everyday routines, something clicked for us. This isn't merely one more tech cycle; what we're seeing amounts to a paradigm shift — closer in scale to the Industrial Revolution than to the Internet revolution. Tokens, not calories or joules, now serve as the essential unit for measuring productive capacity. That point hit home vividly 2 weeks ago at NVIDIA GTC, where I watched hundreds of businesses deploy AI across everything from simple work such as cleaning and image generation all the way to remarkably intricate uses, among them protein folding, physics simulations, and even brain surgery. Strolling the conference floor and chatting with those attending, a single truth stood out: we have barely started to touch what AI can do. And yet, even at this early stage, AI already enables people, communities, and enterprises to achieve exponentially more; we're seeing Jevons paradox play out at the same time across all industries, courtesy of AI, in which greater efficiency can counterintuitively fuel higher demand rather than lower. Turning an idea into an action, a product, an image, a refined concept, a service, or any number of other outputs has literally never been cheaper. The possibilities really are boundless. Though nobody can say precisely how AI will remake what lies ahead, one thing is certain. It will demand vast quantities of power. Our 2.2 GW of capacity, plus strategically located land spanning Pennsylvania, Washington, and Quebec, stands right along the path of this transformation, and we plan to seize that opportunity on behalf of our shareholders, and we're eager for what comes next. With that, I'd like to hand the call over to Q&A. Operator, please go ahead.
Mike Grondahl
analystHi there, appreciate it, folks. To start things off, Ben. You mentioned the choice you made to avoid the GPU rental path over at Moses Lake, and instead pursue only the colocation approach. Would you mind expanding a bit on which two or three main factors led you toward making that call?
Ben Gagnon
executiveYeah, that's a really good question, Mike. You know, when we initially brought this up back in Q3, we were consistently looking at it side by side with colocation. You know, our goal is to get the most value possible for shareholders, so at our sites we're always going to weigh a number of different business models. Because, you know, they've got the cheapest energy and all these other advantages, we figured it would make a great deal of sense. As we kept having more and more conversations with customers regarding Washington and other sites, it became really obvious to us that our best opportunity is simply to stay a pure play infrastructure developer and owner and allow those customers who truly want these megawatts to lease these megawatts.
Mike Grondahl
analystUnderstood. Then second, I think it was a quarter or two back when you laid out a philosophy regarding holding off on inking a lease, since the terms kept getting better — suggesting, you know, that you'd remain quite patient and put off that lease. Could you give us an update on how you're viewing that approach to executing a lease and roughly when it might happen?
Ben Gagnon
executiveRight. So, when it comes to how we execute leases, our approach hasn't changed. It's still the same now. In our view, securing the strongest possible lease terms is the optimal path to boosting shareholder value, since those terms will ultimately shape our NOI and our multiple. Given that we aim to sign deals running 10 to 15 years, taking perhaps somewhat longer than investors might prefer is genuinely essential if we want stronger terms over a longer horizon. If you examine what truly fuels value in these lease economics, risk stands out as one of the largest factors. We've discussed this point many times across the past couple of months. For the majority of these sites, the greatest risk is this: you can absolutely go out, hold discussions, and generate substantial interest. Sometimes you might even finalize a lease before permits are secured. Every bit of that risk ends up reflected in the agreement's pricing. You'll be committed to it across 10 to 15 years, and that will hurt, you know, the long-term value we're building for shareholders. Our approach has stayed remarkably steady. What works in our favor is that, you know, we operate in markets with heavy demand and steep barriers to entry, so obtaining permits takes somewhat more time in Pennsylvania or Washington compared with Texas, which ranks as the simplest market in the United States for that. We think that generates considerable additional value, since it's far more scarce, far tougher to acquire, and there simply isn't as much optionality.
Mike Grondahl
analystGot it. Well, thanks. Hey, good luck in 2026.
Ben Gagnon
executiveThank you, Mike.
Brett Knoblauch
analystHey, everyone. I appreciate you fielding my questions. To kick things off, perhaps you could elaborate on which specific locations are still pending the permits you need?
Ben Gagnon
executivePermitting is, you know, a fairly involved thing, and we're securing them at a number of locations spread over several jurisdictions. Every one of them comes with its own set of rules, its own regulations, its own timelines, its own reviews, its own, you know, authorities. You know, going through precisely which permits are still outstanding at each and every site would be way too much detail. Good progress is still being made by us. Sort of, you know, we're focused on what we can see over the coming couple of months, and given everything so far, including how well the community engagement has gone up to this point, our thinking is that, you know, over the next few months, at some point in the mid to late summertime, we ought to reach fully permitted status at a minimum of one site, and possibly every one of them.
Brett Knoblauch
analystAll right. Now perhaps regarding the leasing situation at your various locations. Our understanding had been that Sharon might be, you know, the initial one to proceed, since that site is comparatively further along. Does that remain your view on this? During the presentation, when you sort of enumerate, you know, the power pipeline and roadmap, what portion of that comes from on-site generation that you're exploring? Any update you can share on where things stand with, you know, obtaining that generation?
Ben Gagnon
executiveRight, absolutely. Let me take the latter portion of what you asked first — you know, every bit of the power we're discussing building out for our HPC and AI data centers at this moment is tied to the grid. Those two plants we currently run, at Scrubgrass and Panther Creek, that arithmetic doesn't appear in those charts for the secured capacity or the site development plans; however, at Scrubgrass specifically, we're pursuing an increase of the generating capacity there using natural gas. We've been doing work to connect with the Tennessee Natural Gas Pipeline. We're getting, you know, fairly solid outcomes there alongside the engineering firms. There's likely still one or two more months to go before we get, you know, a clear route ahead on the engineering plans. You know, Scrubgrass is more our pipeline site, so that power generation opportunity falls more along a 2028 and 2029 timeline. All the rest is grid connected, it's secured today, or it's currently active. My apologies, Brett, I'm drawing a blank on the first portion of your question. Could you repeat it?
Brett Knoblauch
analystSure, regarding the pace at which certain locations might come online faster — yes.
Ben Gagnon
executiveYes. The main factor there will be how well we do with permit schedules and with the customers. All 3 locations — Moses Lake, Sharon, and Panther Creek — are currently part of our active go-to-market efforts. Each one has customers involved under MNDA, and that's been true for a good while now. We keep moving those discussions and negotiations ahead. Honestly, what I'd want investors to understand about permits is that they function more as a condition for closing a lease, correct? They aren't really a condition for starting a negotiation. We carry on these talks and negotiations at the same time as we pursue permitting. As permitting draws nearer and nearer, the negotiations will likewise draw nearer and nearer together, and whichever site gets leased first will probably be the one permitted first.
Brett Knoblauch
analystAwesome. Really appreciate it. Thank you, guys.
Ben Gagnon
executiveThank you, Brett.
Stephen Glagola
analystHi, I appreciate the question. Regarding what you just mentioned, could you shed some light on the order of events involving notice to proceed and the signing of leases? To put it differently, is it possible to execute leases in advance, with the condition that notice to proceed comes later, or would notice to proceed need to happen first before a significant customer agrees to a lease?
Ben Gagnon
executiveIn our opinion, before a customer agrees to something binding, they will expect NTP, and that conclusion comes from the many discussions we keep having. There may be a few customers open to signing ahead of NTP, but such parties are not the investment-grade counterparties we are genuinely looking to work with.
Stephen Glagola
analystAll right, thanks. One last thing from me. So how do you view the availability of Vera Rubin hardware across 2026 and into early 2027, and how much might swings in supply affect when lease conversations happen at your locations? Thanks, Ben.
Ben Gagnon
executiveYes, Stephen, that's a solid question. I believe we've been discussing Vera Rubin going back to the Q3 call, since every one of our sites is essentially set to come online during 2027, so we're working to ensure they're built for the most advanced equipment arriving in 2027 and 2028, which means the Vera Rubins. On the supply side, no impact has shown up yet. I realize there's constant geopolitical unpredictability around the globe that could disrupt those supply chains. Still, since energy represents such an enormous bottleneck, and it has consistently been the enormous bottleneck limiting growth, my view is no geopolitical scenario will shift that bottleneck away from energy and toward GPUs. At this moment we hold no expectation that it will affect leasing or demand for sites, given that power remains such an extreme bottleneck. It's difficult to picture anything geopolitically that would eclipse that.
Stephen Glagola
analystGreat. Thanks, Ben.
Ben Gagnon
executiveThanks, Stephen.
Michael Donovan
analystHey there. I appreciate you fielding my question, and nice work on the momentum. Could you share where things stand with ESA progress — more precisely, the ISA to ESA conversion at Panther Creek?
Ben Gagnon
executiveSure thing; excellent question, Mike. As I imagine most investors are aware, we hold a 350 MW secured ESA alongside PPL; beyond that, there's also an ISA letting us pull roughly 60 MW off the grid, tied to the transmission line and substation already in place at the power plant we've got running today. Converting that is really a question of regulation more than anything. Pinpointing exactly when those approvals will come through is tough. Nothing physical has to be constructed. No CapEx is required. It genuinely comes down to securing regulatory sign-off to turn a non-firm service into a firm one, which would let us push capacity past 350 MW up to what we'd guess is roughly 400 MW, maybe a touch higher. Our expectation is that it occurs within this year, though nailing down a precise schedule is difficult since regulators are involved.
Michael Donovan
analystGreat. Appreciate that, Ben.
Ben Gagnon
executiveThanks, Mike.
Brian Kinstlinger
analystGreat. Thank you. During the prior quarter, Ben, you mentioned that the GPU-as-a-service offering at the Moses Lake location was expected to be aimed at, if I recall correctly, Q1 for launch. If the approach shifts toward colocation, what happens to that schedule, if anything? Also, for my second question, could you discuss how the worldwide memory scarcity is affecting your buildout of sites or altering what you need in the near term or how you plan around lead times?
Ben Gagnon
executiveYeah. That breaks into 2 parts. Regarding moving away from GPU as a service toward colocation, merely altering the business model doesn't truly have much effect on how development schedules unfold; we really don't anticipate any slippage tied to making that switch from GPU as a service over to colocation. Honestly, it simply comes down to the way we prefer to deploy our capital and the way we want the business to be focused. As for the memory shortage, you know, since we are strictly an infrastructure developer and owner, that genuinely doesn't factor into our thinking all that much. For the most part, that's something for the customer to sort out within their own supply chain, given that we aren't the party putting money into the GPUs, the compute, and the servers.
Brian Kinstlinger
analystThat's great, thanks.
Martin Toner
analystHello there, good morning.
Ben Gagnon
executiveYes, that's right.
Martin Toner
analystQuestion. Could you folks expand on how to push capacity higher than that? Can you sort of provide us with timelines and your thinking on that?
Ben Gagnon
executiveSince it was somewhat quiet, I'll restate the question just in case anyone else or other folks struggled to hear it. I think what was asked is whether you can share timelines for how we could grow Panther Creek up to 500 MW and past that. To go past the 350 MW ESA we've already locked in, there are really two avenues for growth. The first one involves switching that ISA from non-firm service into firm service, which I mentioned just a moment ago. That's essentially a regulatory issue that we anticipate settling at some point during this year. It might happen tomorrow, or it could be several months away. As for growing past that point, what we need to do is actually secure new power applications. The positive part is that utilities in the region are genuinely interested in putting money into new generation; in this specific case, we weren't the ones seeking new power. Instead, the utility reached out to us and inquired about how much additional power we could handle at the site. Given the bottleneck constraint around power, that was clearly a very welcome call for us here at Bitfarms to get; it's quite an uncommon one within the industry. They intend to increase generation capacity in the region, particularly to serve our site with more capacity. This will likely be a two to three year timeline, since there's a great deal of process tied to bringing up new generation and constructing those new transmission lines. For many of our customers, what they truly desire is the quickest route to energization along with a clear path to scale across multiple years. That aligns well with what the hyperscalers and the Neoclouds are looking for.
Martin Toner
analystThat’s excellent. Many thanks. I’m hoping my audio comes through more clearly now. Could you give some clarity on the timing for signing your first lease?
Ben Gagnon
executiveWell, I’m unable to provide a precise schedule, but when it comes to milestones, as I mentioned previously, the key issue is getting NTP cleared as essentially the final closing condition or the last milestone before we can sign a lease. For the investors and analysts listening in, what matters most to monitor, particularly in the months ahead, is how we keep making progress toward NTP. Since once NTP is resolved, that is essentially the only remaining item separating us from an executed agreement.
Martin Toner
analystUnderstood. Excellent. Appreciate it. One final question from my side. Could you explain a bit why the mining exahash for Q4 landed where it did?
Ben Gagnon
executiveWe keep reducing our exposure to mining as our attention stays on U.S. HPC infrastructure investments. We have not put any capital into Bitcoin mining; no funds are going toward upgrades or additional miners, and we are working hard to shrink the fleet while also pursuing spinoffs of assets like those in Paraguay that cannot be converted. Our hash rate should, in investors' view, keep declining gradually throughout 2026 as we carry on with this shift toward HPC and AI.
Martin Toner
analystThank you very much, Ben.
Ben Gagnon
executiveThanks, Martin.
Mike Colonnese
analystHello there. Ben, good morning to you and the rest of the group. I appreciate you fielding my question today. Ben, what I'm wondering about is this: once the rest of the permits are in hand at all 3 locations — and from what you're saying, that probably happens within the next few months — how should we think about the schedule on the data center build and handover side? You seem fairly confident that bringing in revenue might begin as early as 2027, but I'd welcome anything more you can share on that front.
Ben Gagnon
executiveSure. What I'd say is that this 12 months really amounts to the period where we execute, while 2027 is when we deliver. Across each of the 3 projects we discussed today — Panther Creek, Sharon, and Washington — our expectation is that all of them will be live, begin producing megawatts, and start bringing in revenue from customers during 2027. Updates will keep coming from us as things progress. My sense is that after we've obtained NTP and gotten leases signed, we'll be in a position to give investors far better visibility into every individual project and the particular schedules attached to each one.
Mike Colonnese
analystUnderstood. I appreciate the answer. Let's return to the Bitcoin mining side. From what you're describing, it seems the hash rate will be gradually reduced while a portion of the HPC AI data centers are coming online. So what's the right framework for thinking about hash going offline and moving through your near-term results?
Ben Gagnon
executiveSure, I'll address that at a broad level, and then I may hand it over to Jonathan for more detail. At present, Bitcoin mining is still profitable, though only barely. The margins are thin. It continues to add to the business, yet it truly isn't the center of the business. It isn't where our time goes. It isn't where our efforts go. Since we did so well last year raising capital and reinforcing our balance sheet, it really isn't all that material for the developments we have this year, the operations or the CapEx. We'll simply keep scaling it down, aiming to capture value through an orderly exit. If it turns out to be wiser to sell certain miners somewhat sooner than required so construction can start, we'll weigh that, as we always will, to get the most value for our shareholders. To us, this is really a fairly small piece of our balance sheet and a fairly small piece of this year's financial plan. Jonathan, would you like to add something else?
Jonathan Mir
executiveWhen we look ahead at our liquidity, the goal we've set strategically is making sure we're well capitalized throughout the lease process and past it, with no requirement to bring in fresh capital from the markets. That factors in how Bitcoin mining operations stand right now. It doesn't presume any betterment in that area's economics. Conservative assumptions regarding the condition of the Bitcoin market form the basis of our plan.
Mike Colonnese
analystThat's quite useful. I appreciate you letting me ask these questions.
Ben Gagnon
executiveThank you, Mike.
Nick Giles
analystMorning, everyone at Keel. During that stretch when Bitcoin mining has been phased out but the HPC side hasn't started bringing in revenue yet, is there any way the generation assets at Panther Creek and Scrubgrass could be put to work — for instance, through the PJM capacity auction?
Ben Gagnon
executiveBoth of those power plants are in fact active in PJM capacity auctions. That's been the case for a long while now. The capacity payments coming to us from that do provide a benefit.
Nick Giles
analystUnderstood. Fine. Is there any rough sense of scale for what those might amount to during the 2026 planning year?
Ben Gagnon
executiveWhat I'd say is that, honestly, when it comes to capacity auction payments, we've more or less hit the maximum. A cap was established by them, and the capacity auction payments ended up right at that level.
Nick Giles
analystSure, that makes sense. Perhaps this one's for Jonathan. So, you've done some work on the capital structure, but I was just curious if you could add anything about what you'd want in an initial debt package, how terms are moving, and what kind of tools you'd be able to use while building and then after energization.
Jonathan Mir
executiveThat's a fair question, Nick, thanks. What we do essentially is weigh our financing choices both at the asset level and up at the parent company level. One thing we've noticed in the market, as I'm sure everyone has, is that the spreads have narrowed between those issuing high-yield debt at what look like pretty appealing rates for strong investment grade counterparties or credit wraps. Those are moving closer to where bank-originated traditional construction and project financing sits. Each option brings its own benefits, whether that's ease of handling the capital once it's in place or the costs of negative carry. When we get nearer to a point where we need funding, we'll decide what looks best for our shareholders regarding how we choose to finance. At this moment, what I'd say is
Nick Giles
analystGreat, thank you both.
Jonathan Mir
executiveOh, my apologies, Nick. I was about to mention that conditions in our sector, and for infrastructure as a whole, appear steady at the moment.
Nick Giles
analystGot it.
Craig Kendy
analystHello, this is Craig Kendy, filling in for Brian Dobson. I suppose this will be the last one. Regarding the re-domiciliation filing to the U.S., should we be aware of any cost implications or structural implications when it comes to ownership as you move into this over the next couple of days? Thank you.
Jonathan Mir
executiveMorning, Brian. A benefit of the redom, and one reason we did it, is that being a U.S.-domiciled company now makes us eligible to be included in indices with that requirement. The Russell 1000 and the Russell 3000, for instance, are ones we'll qualify for, and so is ownership in any other fund that was otherwise restricted to buying U.S. securities. Our view is that this is quite helpful when it comes to shifting our shareholder base toward one that's institutional and long term. On our end, there are no implications for cost or flexibility. We just see this as a nice path forward, with plenty of benefits for our shareholders.
Craig Kendy
analystThat's really useful. Many thanks.
Bill Papanastasiou
analystGood morning to you both, and thanks for fielding my questions. I'd like to ask about the Washington location and the choice to move in the colo direction. Can you verify there won't be any material effect on the purchase commitment that was signed in November? Or is the team weighing this development shift, with allocation going to other sites?
Ben Gagnon
executiveAppreciate it, Bill. Switching business models won't affect the capital commitments or the equipment already bought for the Washington site. Actually, yes, Bill.
Bill Papanastasiou
analystGreat.
Ben Gagnon
executiveThat simply assists in lowering the CapEx, since the compute is no longer something we're paying for.
Bill Papanastasiou
analystGot it, thank you. As you progressively move toward AI HPC, how should we broadly think about maintenance CapEx on the Bitcoin mining sites you already have?
Ben Gagnon
executiveInto the Bitcoin mining sites, we aren't putting any money. Essentially, all we're doing is keeping them operational. Nothing more is going into those sites, nor into additional sites, nor into additional miners.
Bill Papanastasiou
analystThat's great, and I appreciate the color. Thank you.
Ben Gagnon
executiveThanks, Bill.
Ben Gagnon
executiveMuch appreciated, everybody, for being with us on this call today, and I genuinely can't wait to talk with all of you the next time around as Keel Infrastructure. Take care, and have a wonderful day.
Operator
operatorThank you for your participation. This does conclude the program. You may now disconnect.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Keel Infrastructure Corp. transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →This call discussed
For developers and AI pipelines
Programmatic access to Keel Infrastructure Corp. earnings transcripts and 132,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Keel Infrastructure Corp. or any ticker on your watchlist.
StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.