Keel Infrastructure Corp. (KEEL) Earnings Call Transcript & Summary
November 5, 2026
Earnings Call Speaker Segments
Laine Yonker
executiveThanks, and welcome, everyone, to Keel Infrastructure's conference call for the third quarter of 2026. Joining me today are Ben Gagnon, our Director and Chief Executive Officer, and Jonathan Mir, our Chief Financial Officer. Before we get started, I want to point out that this call is being webcast and that a slide presentation accompanies it. You can find today's press release and the presentation on our website in the Investors section. If you turn to Slide 2, I'd like to remind everyone that we will be making certain forward-looking statements on this call, and that actual future results might differ from what those statements imply. This forward-looking information rests on certain assumptions and carries risks and uncertainties. I'd encourage you to review Keel's 10-Q for the full list, which you can find on our website as well as on the SEC website. Please also note that we will reference certain non-GAAP financial measures, and as a result, they may not be comparable to similar measures that other companies present; we invite listeners to look at today's press release and our filed 10-Q for the definitions of these non-GAAP measures and the reconciliations to GAAP measures. Also note that unless otherwise stated, all financial references are in U.S. dollars. Now, moving to Slide 3, it's my pleasure to hand the call over to Ben Gagnon, Director and Chief Executive Officer. Ben, please go ahead.
Benjamin Gagnon
executiveThank you, Laine, and good morning to all of you. I'd like to begin today by tackling the macro issue that's looming over everything. Recent months have presented difficulties for everybody. Interest rates have been climbing sharply, and the 10-year treasury has just reached a level not seen in over 2 decades. Debt markets that were fully accessible 90 days back continue to operate, though they've grown pickier and costlier as of today. Equity markets, too, have shown no mercy, and numerous companies in our sector have dropped over 50% from the peaks they reached earlier this year. Data centers have turned into a political hot button, despite the fact that virtually every American depends on them daily; and geopolitical friction has introduced yet more uncertainty into energy markets both worldwide and at home. None of this comes as news to anybody listening, and none of it is specific to Keel; we have nothing to conceal. So let's confront it head-on. When we chose the name Keel for this company, we explained that a keel serves as a ship's backbone, invisible yet indispensable. Its core function is to keep the vessel upright and advancing through turbulent waters. It's what allows a ship to stay on its heading when strong winds push from the wrong side. During this quarter, those winds were fierce. The waters were turbulent, but we stayed on our heading. Staying on our heading means delivering exactly what we promised; so let me hold us accountable to that. In the prior quarter, we committed that Moses Lake would complete permitting and begin construction; that happened, and building is underway as of today. We committed that we had strong confidence in the rest of our Pennsylvania permits, and that remains true. At both locations, zoning and land development are already secured, and only the final state environmental permits remain. Those have moved more slowly than anticipated, yet as of now, no permit application has ever been rejected at any of our sites; we also committed to providing an update on expansion load studies at Panther Creek and Scrubgrass around December or January. Those applications keep advancing favorably, though at a somewhat reduced pace, and we now anticipate delivering that update during Q1 2027. Should that timing shift, we'll let you know straight away. None of this happened by chance. It's our team's strength that keeps us stable and propels us onward even as we sail against the wind. The area where we've fallen short of our commitments is leasing; back in May, we set a target of signing 3 leases before the year closed. And although we no longer anticipate signing 3 within this year, demand has never been stronger, and our strategy remains unwavering. Every one of the recent headlines shares a single common thread. Each one further tightens the supply of the industry's principal growth constraint, power. One project halted in one place, a moratorium in another, a permit suspended, financing withdrawn, a power plant running behind schedule. Just in the first half of this year, it's estimated that about $200 billion of data center projects nationwide got blocked or delayed. Every one of those announcements removes 2027 and 2028 capacity from the market, which leaves what's left—our existing developments, for instance—in even shorter supply and more valuable. That's the supply picture. Let me now take you through demand, and I'll do it through the voices of the largest buyers anywhere. On to Slide 4. Supply continues to shrink, yet demand has shown no hesitation. In recent weeks, the four largest consumers of data center capacity worldwide—Microsoft, Alphabet, Meta and Amazon—have each posted results. I'd encourage anyone on this call who invests to read those filings directly, since they support the demand case more convincingly than anything we might tell you. Together, they're expected to spend more than $800 billion on CapEx this year, and all 4 have indicated these investments won't slow down anytime soon. Since January, the combined contract backlog at Microsoft, Alphabet and Amazon has climbed by roughly 2/3, reaching approximately $1.8 trillion. That represents demand customers have already committed to, waiting on capacity. And all 4 have told their investors, in their own words, that capacity is insufficient. Amazon said, we will still not have enough capacity to meet all the demand we have in '26, and I believe this demand will also be true in '27. In fact, the demand we already have for '28 is striking. Microsoft said customer demand continues to exceed available supply. During the prior quarter, Microsoft ended up spending below its plan since capacity from third parties arrived behind schedule. Meta commented that available compute falls far short of what demand requires. Alphabet, meanwhile, has started leasing compute from third parties—described by the company as a bridging strategy—while it continues expanding its own capacity. NVIDIA reports seeing demand of at least $1 trillion through '27 for its Blackwell and Rubin platforms, and Morgan Stanley projects a 70 gigawatt power shortfall across U.S. data centers through '28. This market does not scare us. Quite the opposite: it is precisely the market we described in our thesis close to 2 years back and have been getting ready for. What I believe matters most is the following. Altogether, the hyperscalers have inked data center leases worth about $1 trillion that haven’t begun yet, and a lot of that power won’t come online until ’28 or after. Demand keeps outpacing supply for ready-for-service dates all the way through the end of ’28, since hyperscalers, neoclouds and numerous enterprises already have locked in chips for ’27 and ’28. What they lack is power that can be available on that same timeline. So consider this: if the largest, best-capitalized builders in the world are short on ’27 and ’28 power, then who has it? Keel. Even as available short-term electricity capacity tightens sector-wide, here at Keel our power for 2027 and 2028 sits further along, is more firmly secured and nearer to being delivered than was the case 90 days back — and steady incoming interest from customers demonstrates that. Moving now to Slide 5. On August 18, a single week following our prior call, Governor Shapiro put his signature to an executive order that turned Pennsylvania's grid standards for data center buildout into requirements. Under those grid standards, data center developers in Pennsylvania must cover the full cost of new power capacity themselves, involve communities early and in public, provide community and workforce benefits above and beyond statutory requirements, and pledge environmental safeguards paired with continuing monitoring. To phrase it plainly: fund your own way, be transparent with and respond to communities, employ people locally where you can, and safeguard the land, water and air; everyone gains from these standards, and we wholeheartedly back the order along with the necessity of responsible data center development. Endorsing it comes easily since the grid standards broadly match Keel's own standards and the efforts we have undertaken ever since we set up our presence in Pennsylvania; thus we could adjust. Still, putting the executive order into practice generated considerable fresh hands-on work for the team.
Benjamin Gagnon
executiveGetting to a full grasp of the executive order and how it bears on Keel projects required extensive engagement with each relevant regulator plus many government offices and agencies, and after that our team and the teams of our prospective customers had to do further engineering to craft solutions. That consumed time, yet most of it now lies in the past, and we currently possess clarity regarding engineered solutions that function. For investors, here is what implementing the order amounts to in practice. First, the permits sitting before the DEP at present fall outside the order's new requirements, though the order additionally removed data centers from the state's fast-track permitting program. Put simply, data center permits can no longer get priority review. They proceed through the DEP's standard process. That does not directly affect our sites, since reviewing our remaining permits does not hinge on the fast-track program, but it does build a bigger backlog for the DEP. Second, backup power. All of our Pennsylvania sites were always going to require a backup solution; it was always budgeted, and it was always part of the plan. What changed is which type of backup. During the last 3 months, we have engineered a solution, one component of which centers on battery storage, that works for our customers, works for Keel and complies with the order. Above all, we don’t anticipate this will materially change tenant project economics or timelines. Third, the power delivery timelines we’ve planned under our ESAs are still the same; we expect the Sharon and Panther Creek substations to be energized in 2027. At this point, RFS dates are directly tied to lease signings and will hinge on when we sign and break ground. Customers understand this and want megawatts online as soon as possible, with revenues beginning in early 2028 and capacity at each site ramping through 2028. Yet none of that captures the executive order’s underlying intent. That intent was about communities, and Keel leads the pack in this area. When local residents object to data centers, it comes down to three issues: they don't get clear information, they don't feel safe where they live, and once the permits are issued there are no firm promises. Most developers throughout the industry answer with a package of benefits and go no further. Our answer is what we term the Keel standard, and three specific commitments stand behind it. The first is a community benefit agreement, or CBA. Right now we are working on our initial one with the Nesquehoning Borough Council for Panther Creek, and we started that effort before Pennsylvania mandated it. Sharon and Scrubgrass are next. Our community benefits agreement leads the market and is built so that as on-site power grows, the community gains too, sharing in what we achieve. Next, a structured channel through which residents can voice concerns. We're assembling a process for these agreements in which every resident receives a local point of contact, defined timelines for responses, and an appeals path, all supervised at the Board level. Nesquehoning is the first location, after which it extends across every one of our sites; this is neither a hotline nor a generic e-mail address. Basically, it's about making every channel of communication available to the community so people can share what they're observing, what they're hearing, and how they're feeling. And there's a company mandate driving this — not simply to look like a good corporate citizen, but to genuinely be a good community member. Third, we measure before we build. We've engaged third-party consultants to gather input from Nesquehoning's residents via a community baseline assessment. Ahead of Panther Creek's construction, we're listening to and documenting how the community views housing, employment, education, income, health, local services, and several other areas. In November, those consultants will meet with residents, and in December, each household in the Borough will get a confidential survey. In 2027, we'll present the key findings to the Borough Council, then repeat that assessment periodically, and follow the same approach in Sharon and Scrubgrass. This lets us monitor the real changes our projects bring about, see how the community is affected, and ultimately base our decisions on evidence instead of guesses. Throughout our sector, the majority of community commitments end with a benefits package. Not many add a structured channel through which residents can voice concerns. Even fewer take measurements of conditions prior to and following construction. All three of these things are what we're doing. That's what genuine accountability after approval looks like on the ground, and it's already visible today. In Nesquehoning, our investment in Panther Valley School District pays for a full-time community school coordinator. It also backs the after-school programs, covers the school bus system, and provides funding and staffing for food pantries. Together, those pantries serve roughly 500 families and 2,000 individuals each month. Our team is present in the community, showing up because people are there. We have also run over 20 town halls or informational sessions throughout Nesquehoning, Sharon and Scrubgrass. Those sessions were publicized and socialized, and the towns turned out. More than 500 people came to the events, and they heard straight from our senior team how they describe data centers, explain Keel and walk through what our projects mean for them. This isn't about charity, and it isn't about PR. It's about being a good neighbor — and good neighbors make good business sense. When infrastructure projects have strong community backing, they actually get built and they last. Because we hold to those standards, Panther Creek and Sharon both had their zoning approvals locked in before anyone even started talking about the executive order. And once that order was signed, we truly didn't have to alter one aspect of how we work with the community. Honestly, this ranks among the most rewarding parts of the job, and nobody needed an executive order to push us toward doing the right thing. We've been at it since Day 1. We routinely get input from officials at all levels of government about our community engagement and the benefits of our operating approach. What we did need to do was collaborate with regulators, our engineers, and our customers to address the new requirements. That brings me to leasing, which I know is on everyone's mind. In May, we aimed to sign 3 leases by year-end. Pennsylvania's new regulatory framework has delayed our permitting and commercial timelines by months, and we no longer expect 3 leases to be signed this year. Even so, our commercial strategy remains unchanged. The level of demand we're seeing for our sites is unlike anything before. In this sector, some of the biggest developers are running a year or more behind, so when the slip is only a matter of months, our customers get it. Up to now, zero prospective customers have turned away because of this, and fresh parties continue to approach us; we're firmly of the view that getting solid leases signed isn't a matter of whether it happens, but of timing. And as I've often noted, a lease isn't a prize to tout in a press release; it represents a 15-year commitment, and we won't put our name on an unsuitable lease at an unsuitable price merely to meet a deadline.
Benjamin Gagnon
executiveMarket conditions have been much more turbulent than the real-world situation on the ground. And since no lease has been signed as of yet, each lease we do sign will carry pricing based on prevailing market terms and be tailored to tenant-specific requirements. What counts is that these projects get priced and assessed on a yield on cost basis. Costs for newer technology, materials and labor might go up or down, and the cost of capital may move as well. Whenever that happens, we intend to reflect those shifts in the lease economics so that risk to our shareholders is minimized; so here is what we commit to going forward; we will not provide you a date for a lease. We'll keep you informed with clear, transparent updates as each site moves forward in development. And when we do sign, it will be the right lease, with the right customer, at the right economics — including what it costs to finance. That's how we remain on course and maximize long-term value for shareholders. Let's move to Slide 6. Now to the sites, beginning with Moses Lake. During Q3, we obtained every approval required to start construction, and we broke ground. Moses Lake is still on schedule to be our first site energized in '27 and the first to produce HPC revenues; it's modular, built to suit, and the route to energization is shorter than a traditional build. Before we ever started construction, all the critical materials were either bought, under contract, or already in production. We've also designed Moses Lake so it can move from GB300s to Vera Rubin with just a small additional cost, which gives tenants more flexibility and makes Keel a more valuable solution. Moses Lake is the only one of our sites funded entirely from our own balance sheet. As with any site, our goal there is to announce the lease and its financing together. That said, completing Moses Lake doesn't depend on a lease or project financing, so there's no pressure on us to finance it on unfavorable terms. Power availability in the Pacific Northwest right now is tighter than it has ever been, and at Moses Lake we have several parties involved who require megawatts immediately. Among our sites, Moses Lake is the smallest—accounting for under 4% of our near-term megawatts—and a facility of that scale is a better match for a rapidly expanding AI or cloud business than for a hyperscaler. We will apply the same standard we use at every other site: a structure that safeguards our returns, credit support suited to the customer, and financing aligned with the lease. To a lesser degree, we recognize that a Moses Lake lease will be interpreted as an indication of how we execute, and that is how we are approaching it. Turning to Slide 7. To build on what I said earlier, pressure on the commercial side keeps growing at our Pennsylvania locations. Across the last three months, we've finished a substantial round of technical due diligence with several prospective tenants, moved LOI talks forward with a number of parties at both sites, and, most importantly, preserved our power delivery timelines under the ESAs in spite of a new regulatory framework. I'll begin with Sharon. At Sharon, we hold 110 megawatts of secured power from FirstEnergy. In Pennsylvania, this site is the most advanced of our locations, and just a single state environmental permit is still outstanding — the DEP has already put that permit out in draft form. Sharon, at 110 megawatts, is right-sized for a broad spectrum of customers, ranging from hyperscalers to AI companies scaling quickly, and that is the mix we are encountering in conversations. That is also why the credit structure carries such weight in this setting. Pairing a high-growth AI enterprise with investment-grade credit support is what converts a sound customer into a financeable long-term lease. Panther Creek is our flagship site. It has 350 megawatts of secured power from PPL, and it could grow to 500 megawatts or more. It sits in one of the most sought-after AI corridors in the country. That scale is why the talks at Panther Creek involve the largest capacity buyers out there. Zoning and land development are already done, and we're finishing up our final state environmental permits — 1 of the 3 is already in draft, and the other 2 are in standard technical review with the DEP. For a campus of this size, the counterparty matters more than anything else. The larger the customer, the more they care about certainty on power, permits and delivery. Each time we secure a permit, Panther Creek gains a capability that very few locations across the country possess: large-scale power in PJM for 2027 and 2028, with space to expand for years afterward. In contrast to Moses Lake, both of our Pennsylvania sites are big enough that project financing will be necessary. Given that, at Sharon and Panther Creek we have remained disciplined, and we will continue to be selective in every conversation with potential tenants; what we prioritize is signing a tenant with an investment-grade rating, or a counterparty backed by an investment-grade wrap. Turning to Slide 8. I want to step back here, because in my opinion this slide carries more weight than any other in the deck. I think there are a few key things this company should be judged on at the moment. What is our megawatt count? How dependable are those megawatts? How much certainty do we have about their timelines? Where do they stand when it comes to permitting, design and construction? And what demand is there for them? On all of those measures, Keel is in a stronger position today than 90 days ago. Let's begin with the near term. Our 478 megawatts at Moses Lake, Sharon and Panther Creek moved forward on every front. Moses Lake went from approved to under construction. Pennsylvania now has only its final environmental permits left, and our designs have been updated for the new grid framework. We’ve moved into advanced lease negotiations with all three, and additional prospective tenants keep joining the process. Now consider what follows them. With our expansion capacity, we have a chance to grow the capacity we’ve already secured to four times its current size. As for Panther Creek, through our work with the PPL and Blackstone Infrastructure joint venture, we’re seeking to support construction of natural gas generation and take that campus beyond 350 megawatts, toward 500 megawatts or more. Scale of that kind is highly attractive even to the most demanding tenants in the market. At Scrubgrass, things are progressing well as we work to secure up to 1.3 gigawatts of expansion capacity, and we’ve gone about it the Keel way. We've got the land secured, a thorough load study is in progress, horizontal lateral planning is moving forward together with our development partner, and 5 community sessions took place before we submitted a single permit. And up in Quebec, we've gotten the local approvals we need to move our 96-megawatt site forward, and now we're waiting on final ministerial approval. You may also have come across recent press coverage concerning a site in Allentown, Pennsylvania. As we've said before, we keep hunting for opportunities to expand our portfolio and generate value for shareholders and customers. We're currently exploring a potential chance at the Allentown location that would allow us to acquire a completed power shell together with 75 megawatts of 27 PPL power. We're conducting thorough diligence alongside the current owners and with local and state regulators, and we'll keep investors informed as matters progress. How we expand is guided by capital discipline.
Benjamin Gagnon
executiveWe're only moving forward with this new site because customer demand is unmistakable, and we grasp both the regulatory obligations and the schedule needed to get it ready for service. Setting Allentown aside, our expansion portfolio comes to roughly 2 gigawatts in total; and here's the part that excites me. Quarter after quarter, a growing share of those megawatts advances up the ladder — from potential to secured, secured to permitted, permitted to designed, design to under construction, and then from leased to energized. That's how genuine value is created in this business — not through announcing megawatts, but through maturing them; and any project across our industry that slips removes more '27 and '28 power from the table, which makes the power that does get delivered worth more. Supply keeps contracting while demand keeps rising, and we plan to be among the companies that delivers. Moving to Slide 9. Let me pull this together; it was a difficult quarter for our sector. I said so at the outset, and I won't retreat from it now. The water is rough, and it's rough for everybody. But here's what actually took place within Keel this quarter. We broke ground at Moses Lake. We brought Pennsylvania to its final environmental permits under what the governor describes as the strictest guardrails in the nation, with not one application denied. We established the industry standard for community engagement, as shown by our community benefits agreement, and we've kept every potential customer at the table while new ones keep arriving; and our pipeline stands more secure and further advanced than it did 90 days ago. Things took longer, yet nothing was canceled, and demand today is higher than it has ever been, with increasingly fewer options for customers to grow in '27 and '28. The 4 largest buyers of compute in the world just told their investors they can't get enough capacity, and we are building precisely what they're missing. I'll say this: the market is validating the exact thesis our strategic pivot rested on 2 years ago; we foresaw the supply-demand imbalance. We got ready for it. Now it's here. And as supply grows scarcer and demand keeps rising, the companies holding real near-term power in the right locations and developing it the right way are the ones that will win. That's Keel; we built this company for precisely this moment, and we won't waste it, and we have the balance sheet to see it through. Jonathan will now walk us through it. Moving to Slide 10.
Jonathan Mir
executiveAppreciate that, Ben, and morning to all. Ahead of covering how we're allocating capital and funding the business, I'll take you through the numbers for Q3. On Slide 11: for the third quarter of 2026, revenue landed at $28 million, compared with $68 million during Q3 of 2025. The drop was driven mainly by our U.S. Bitcoin mining operations being decommissioned in this year's second quarter, plus a lower average price for Bitcoin. For the quarter, we posted an operating loss of $8 million; a year earlier, the operating loss was $18 million. Loss from continuing operations came to $62 million, or $0.10 per share, while in the third quarter of 2025 that figure was $11 million. The main reason for the change in loss from continuing operations was a $55 million noncash unrealized loss on the fair value of the company's capped calls connected to the 2025 convertible notes offering. Adjusted EBITDA was negative $27 million for the quarter, versus $19 million in the prior year period, which reflects the wind down of Bitcoin mining operations I mentioned earlier as well as a decline in average Bitcoin price. Looking at the first three quarters of 2026, cash SG&A came in at an average of $24 million each quarter. Regarding Bitcoin, we've fulfilled what we promised on two fronts: substantially winding down Bitcoin mining and divesting our Bitcoin holdings. In the third quarter we sold 2,520 Bitcoin, bringing in $192 million of proceeds, and we timed those sales to take advantage of stronger markets. By September 30, what we held in Bitcoin was nominal; back in Q2 2026 we shut down every one of our U.S. mining operations. The only active mining left is in Canada, where we produce a few Bitcoin daily. That production gets sold routinely to fund our operations and investments. Our liquidity planning still leaves out the modest Canadian Bitcoin operations that remain. By November 4, 2026, our liquidity was roughly $780 million, all of it in unrestricted cash. Another $53 million sits in restricted cash, which serves as collateral behind various letters of credit we've put up for expansion capacity. Turning to Slide 12. Each quarter we go over the three pillars of our financial strategy — capital allocation, capital formation and capital structure — and that strategy shapes key operating principles as we work to maximize long-term, risk-adjusted shareholder value. One, we don't build on speculation. Two, we place high value on holding strong liquidity reserves. Third, we'll apply sensible levels of leverage when funding our projects and secure financing terms as near as possible to the moment we sign leases, so we steer clear of basis risk that comes from attempting to time the markets; these are core principles of infrastructure investing, and Keel is an infrastructure company. As spelled out in our 10-Q, pre-lease capital commitments currently amount to $380 million through the close of 2028. That outlay covers things like engineering agreements, procurement and manufacturing, and site management. We'll invest selectively so we can keep pace with the speed our customers expect. As a reminder to everyone, the pre-lease investments we're making today will be applied toward our equity contribution once we ultimately finance those projects. The money going out the door today means we won't need as much debt at the holdco level and/or equity later on. On top of that, proceeds from a project financing at Moses Lake will let us recycle capital into the equity required for Sharon and Panther Creek. Each dollar raised at Moses Lake removes the need for a dollar of outside equity. That kind of capital rotation sits at the heart of our strategy. We'll keep scanning our assets for chances to leverage their value both to cut back on or avoid external equity financing and to keep the balance sheet strong. We always hold more liquidity than we need to cover all capital spending required ahead of leasing and construction, along with our cash SG&A through 2028; we will be choosy about any outlays before leasing and construction so that we keep the benefits that come with a robust liquidity position. Right now we don't anticipate needing any outside debt or equity financing prior to signing a lease; when markets are highly volatile, it's up to us to proceed carefully and to raise capital whenever we see a good match between attractive uses of proceeds and sensible financial terms, as occurred this summer, and then to put that capital to work in a transparent way for shareholders' benefit. On that topic, investors frequently want to know how we oversee and rank pre-lease expenditures. We never put money into projects speculatively, without predetermined plans, caps, and confidence that value will be created. Our funding runs through what we refer to as three stage gates. Every gate carries a set scope, a set spend, and a set list of conditions that have to be satisfied before we proceed to the following one; that framework is precisely what lets us move and de-risk our sites as quickly as our customers need, while avoiding committing shareholder capital before the information that warrants it is in hand. Stage 1 is obtaining power and permits. This is the least expensive piece, yet it delivers the greatest value for each dollar, since it converts an energy position into an asset that is permitted and buildable. In Stage 2, we secure equipment with long lead times that determines when delivery happens—things like transformers, substations, and fiber—as permitting and approvals approach completion. Through these investments, our ready-for-service dates become concrete for customers. Stage 3 covers the entire build, and that is where most of the capital gets spent; we commit that capital only once a lease is signed, when the economics are under contract and we have obtained project financing that secures an appealing return for our shareholders. Stages 1 and 2 are financed off our own balance sheet; once a lease is signed, Stage 3 is handled through project financing. As risk diminishes, we put capital to work. With project financing, our view is that the best outcome means getting financing terms locked in at lease signing while keeping basis risk as small as possible. Market timing isn't something we'll pursue. The goal is to secure a spread for our investors that delivers appealing returns. We are highly aware of how sensitive our business's economic model is and of the current financing climate; we speak with our financial advisers almost daily, which lets us know in real time what financing terms a given customer's possible lease would likely carry, and that knowledge plays a vital role in our evaluation process. Moses Lake has stood as the one deliberate exception to this practice; it is small and modular, and it brings our first megawatts onto the grid sooner, in 2027. And again, after that site is leased, the proceeds from its project financing will be recycled into the equity requirements for Sharon and Panther Creek. Because Moses Lake is small, we anticipate leasing it to a tenant that is smaller than the ones we are discussing with Sharon and Panther Creek; and again, because of that size, we anticipate raising financing through a private credit solution instead of the high-yield bond market; we think our lease pricing at Moses Lake will produce reasonable risk-adjusted returns even in today's financing market. We reaffirm the commitment we have made on each earnings call. Whenever we raise external capital, we will be transparent about what that capital will be used for and why we think the related long-term risk-adjusted returns generate value for shareholders. The stage-gate structure is the process we rely on to hold ourselves to that commitment. Money comes in only after the risk has been removed—never beforehand. We do not expect to require any borrowing or share issuance until a lease has been executed. As we have demonstrated across hundreds of calls with investors, whenever investors want further detail or clarification regarding any part of our operations, we will supply it during those conversations and keep up our habit of making Ben and me easily reachable by our shareholders. I will close with a few points. Keel has numerous routes to success. We hold several sites, and we have several prospective customers. We have several approaches for structuring leases and financing. No single project is essential to us. The regions where we work are conducive to responsible data center development. Our infrastructure-only model remains straightforward for investors to grasp: we secure power, move it through permitting and construction, lease it to creditworthy customers, and finance it based on those leases. Amid volatility, we concentrate on fundamentals and what falls within our control, relying on a strong balance sheet, a disciplined strategy, and plans investors can easily follow. With that, operator, please open the line for questions.
Mike Grondahl
analystWhen you've been talking with tenants, could you describe how you see lease structures and terms changing over the past 90 or 180 days?
Benjamin Gagnon
executiveMike, yes, of course. That's a great question. The terms we're reviewing across the sites do differ quite a bit depending on Moses Lake, Sharon versus Panther Creek. Broadly speaking, I'd say tension is tending to build across all 3 sites, since we keep advancing the sites and bringing them nearer and nearer to the time line. The sensitivities people have at the moment are increasingly centered on permits, community and financing, obviously. On permits and the community side, I believe we've given our potential tenants strong confidence in our path, our success and our continued path forward; and as for financing, that's something we're working through with all the various counterparties; and we're quite selective regarding the various counterparties we are working with and speaking with, because we're only focused on good quality counterparties that are going to be financeable. But broadly speaking, I think the terms are getting somewhat more competitive and somewhat more tense in the negotiations as we get nearer and nearer to our commissioning dates, and most of the market seems to be — most of the market supply seems to be shrinking.
Mike Grondahl
analystUnderstood; and then perhaps as a quick follow-up on that point. On a relative basis, could you rank your 3 sites in terms of the demand at each one?
Benjamin Gagnon
executiveSo the way to think about relative demand among customers at each site really hinges on scale; and what we mentioned on the earnings call a few months back is that the counterparties at Moses Lake and Panther Creek are entirely different. Whereas at Moses Lake, it'll be more of a — probably more of an emerging company. At Panther Creek, only a few buyers worldwide could afford that scale and are genuinely interested in that capacity. And so when we're talking with the biggest developers in the world, the biggest buyers of compute, their focus is Panther and Sharon; and then when we look at more of the neoclouds or emerging companies, language labs, those sorts of things, their priority will either be on Moses or Sharon depending on their scale and secondarily, their time to energy requirement.
Greg Lewis
analystIt's been quite a week, folks. I did have one question. I genuinely liked how you described the way the project moves forward — some initial CapEx, and then we sort of hold off until the lease is in place before spending starts. I suppose, when I think about the other existing sites that we're in the process of developing — any sense of what that CapEx looks like to get one of them to Stage 2? Is there a way to frame roughly what that CapEx will look like across the next 12 months?
Jonathan Mir
executiveYes. So from now until the end of 2028, our capital commitments come to roughly $380 million in total. Around half of that goes toward completing Moses Creek. Then the bulk of what remains covers substation work and fiber work at both Sharon and Panther Creek. As for the Stage 1 development costs, those are quite modest. They're mostly people and a key space — folks sitting in conference rooms. So once we reach the end of a Stage Gate 2, leaving aside the decision to buy long lead time equipment, it would take considerable effort to spend $1 million a megawatt to have a site ready to go. So the dollars involved in Stages 1 and 2 are quite small next to the overall project construction cost; and we're very careful about how we think about allocating those dollars across longer-term projects like Scrubgrass, for example.
Greg Lewis
analystOkay, that's really useful. Then, just thinking about — I mean, clearly we want to add power across every site — well, not every site, but several of them. Could you take us through how that works? Obviously, there's the detailed load study underway right now at Panther Creek. But say that detailed load study wraps up — what does the process look like from there for getting final approval on that additional 150?
Benjamin Gagnon
executiveSure, glad to walk through it. Once that detailed load study finishes, it essentially locks in all the engineering needs, the financial needs, and the timing for delivering the power by what estimated date; after that, a negotiation window opens — typically about 3 months — to negotiate the ESA; and inside the ESA, we'll handle the last round of talks on the power delivery schedule, the upfront items like initial deposits, letters of credit, and whatever else is required to fund the infrastructure, and that should take roughly 3 months.
Mike Colonnese
analystThe first question from me: I was hoping you could give a bit more detail on when you expect to lock down the rest of the permits at Sharon and Panther Creek. And would it be fair to say those milestones might count as the closing conditions for signing contracts with prospective tenants?
Benjamin Gagnon
executiveMike, on the remaining permit schedule at Sharon, we're down to just our final environmental permit, as I mentioned on the call, and it's currently in draft form. Draft form basically means they've completed an extensive review. They essentially believe it's likely to be approved and they plan to approve it, but a review process and a window still remain that they need to work through before it's final and actually done. And they could always revise and change things and extend that a little if they need to. But we would expect that once things are progressing at this stage, they're likely to come. It's just a matter of time. As for Panther Creek, we have 3 remaining, one in draft and 2 in technical review. So everything has been submitted, everything is being processed, everything is moving forward. We've been given no red flags or indication that any permits are going to have issues or faults, but it's a little hard to guide on the time line now given the backlog at the DEP, and that's kind of a changing condition in real time. I think the positive thing here is that we were so far advanced on our permits before the executive order came out that the impact on us is pretty minimal, because we were down to our final permits already, and most of those were already in process.
Mike Colonnese
analystThat's really useful context, Ben — I appreciate it. And I've just got a quick question about the mining business. Could you remind us where the hash rate sits today, and give us an update on when we should expect mining to wind down from here?
Benjamin Gagnon
executiveIt's roughly 5 or 6 exahash, Mike; it isn't particularly meaningful; the whole operation is in Quebec, and it produces a couple of Bitcoins per day. It's still generating positive free cash flow, though it's fairly marginal, and as Jonathan mentioned on the call, we don't factor it into our liquidity forecast planning; we'd expect it to keep shrinking as we receive the approvals from Quebec that we're hoping for and work through over the months and quarters ahead. And until there's a clear path forward regarding conversion of the Quebec assets, we plan to keep the Bitcoin mining running, but we have no plans to invest further in it. Not another dollar will go toward purchasing additional miners or upgrading. We'll simply keep operating it until we've confirmed the conversion, or the convertibility, of those sites.
Michael Donovan
analystI noticed that you raised contracted power at Baie-Comeau to 30 megawatts from '22. What's your thinking on how to develop that site for HPC? Which further approvals would be required? And how could its delivery timeline stack up against Sherbrooke?
Benjamin Gagnon
executiveYes; so the approach we're taking in Quebec is that we're replicating our Sherbrooke playbook. That was the lowest-hanging fruit we identified. It's the community where our relationships are strongest, where we have the most scale, and where the location is best suited for an HPC site. So that's the first project we're taking forward. And we — as we've said before, all the local approvals are in hand, and we're simply awaiting the final ministerial sign-off. Once that comes through — we're waiting for it to happen — what we'll do then is replicate that same Sherbrooke playbook at Baie-Comeau. And we had a chance to essentially pick up a small expansion at no cost, and we could secure the right to an extra 8 megawatts at the Baie-Comeau site for essentially no dollars spent. So for us it was a very interesting option, assuming we get the Sherbrooke playbook completed; we have a somewhat more compelling site at Baie-Comeau to develop.
Michael Donovan
analystThanks for that. And just to build on what Mike asked, given how deal structures keep changing, would a powered land lease be something you'd look at for any of your sites? Or is your focus on delivering the whole facility?
Benjamin Gagnon
executiveYes. A powered land lease is something we would be open to. We've examined powered land, powered shell, full colo, and the cloud model too; and in our view, each of these business models suits different companies; we've made a deliberate choice not to go after the top rung of that ladder, meaning full compute. But powered shell, powered land, or colo — every one of those is an interesting option that remains on the table.
Brian Kinstlinger
analystTurning to Moses Lake — permits were completed in September, and demand has been unprecedented — so what's been preventing us from proceeding with the lease at that location? And ought we to anticipate that happening ahead of year-end? Or does it look more like a first quarter 2027 event?
Benjamin Gagnon
executiveBrian, I appreciate the question. Just as we stated during the call, from this point onward we won't be giving any kind of guidance regarding lease timing for any of the sites. That said, there's an enormous level of interest and demand around this site, along with competitive tension at that location. One factor that has been quite beneficial to us at Moses Lake is that, since we're funding this site from our own balance sheet, we've been able to keep pushing ahead with it, to keep developing it — with each day we advance and every beam of steel that rises, the project becomes less risky and we generate more value for the end customers; so that is helping us sustain a very high degree of tension at Moses Lake, and we have strong confidence that we'll secure a very good deal there; however, we don't wish to provide, nor will we be providing, any kind of expectations regarding the timing of that.
Brian Kinstlinger
analystJust to make sure I understand on my follow-up — it's ready for lease. At this stage, there's nothing on your side needed to prepare it for leasing. Correct?
Benjamin Gagnon
executiveNo further permits are needed from us, and no additional engineering work is required to complete a lease. Right now, during the commercial process, we're engaged in quite extensive technical diligence and negotiations with several counterparties.
Bill Papanastasiou
analystSorry about that ahead of time. I got cut off earlier when I put my hand up. To start, could you give us an update on how the team is handling the supply chain situation for long lead time equipment, given how much demand there is for data centers and how tight supply is?
Benjamin Gagnon
executiveBill, that's a great question. So here's what we've done — a few things, really. First, we locked in all the long lead time equipment we need for the power connection, right? So everything required for the substation transformers and for building out the actual powered land portion, we have all of those long lead time items secured across all 3 of our sites. At Moses Lake, we obviously have everything secured and contracted and on the way, with a lot of it already received and in hand. And then for the longer lead time equipment needed to build out the data center at Sharon and Panther Creek, what we don't want to do is actually lock ourselves into long lead time equipment purchases that may not ultimately be what the end tenant wants. If you think about the timeline to RFS, it's a very simplified Gantt chart with 3 buckets. There's obviously permitting and planning. There's another bucket, which would be the leasing; and then the third bucket would be the long lead time equipment; and given this stage in the permitting process across Panther Creek, the critical path is going to be leasing; and the way we can keep the critical path on leasing is that, instead of committing to long lead time equipment, what we try and do is try and commit to manufacturing slots, which help us minimize the CapEx or minimize the capital we commit in terms of deposits to secure timelines and also preserve the flexibility for us to modify the actual equipment we're purchasing for the end tenant based on their ending needs; so this is a way for us to try and be very capital efficient while we maintain our timelines and maintain our flexibility through the negotiations.
Bill Papanastasiou
analystGreat. Thanks for that. And second, we've been hearing about some significant shifts up in the Canadian data center space — especially Anthropic coming into the country, plus what people are saying could be a second big deployment. I'm wondering whether you've noticed any pickup in demand in that region, and how you see exposure to frontier AI labs in Canada evolving going forward?
Benjamin Gagnon
executiveCanada is a market that differs enormously from the U.S. My sense is that fewer frontier labs have set up there, simply because building new data center capacity north of the border has proven more difficult. If you actually count GPUs installed across the country, plenty of individual U.S. data centers have more GPUs running for HPC and AI workloads than all of Canada does; so at this stage the scale is comparatively modest. The genuinely compelling opening in Canada, which we've touched on a handful of times before, is the legislative push toward data sovereignty and compute sovereignty there, at both the national and provincial levels. And given that growth and supply of data centers and GPUs face a much tighter bottleneck in Canada, combined with that legislative capture keeping compute demand local, premiums on compute in Canada tend to run considerably higher than they do for equivalent compute south of the border. That creates a strong opening for plenty of companies to enter Canada. My view is this isn't necessarily confined to — or perhaps even centered on — language labs. I suspect there are some quite interesting — possibly more interesting — opportunities with large Canadian corporations and the government than there may be with the language labs, which enjoy the flexibility to locate anywhere.
Nick Giles
analystI wanted to ask whether you'd be open to entering into exclusivity — is that something you'd consider? Or should we assume you'd really just prefer to sign a lease? And if signing a lease without exclusivity is your preference, might you consider an expansion option or a ROFR on additional capacity — Panther Creek comes to mind?
Benjamin Gagnon
executiveThanks, Nick. Yes, that's a great question. At the various sites, we try our hardest to preserve as much competitive tension as we can throughout the process by not signing exclusivities, or by signing only limited exclusivities that let us keep negotiating and keep marketing the site. That approach is the one we favor, since clearly it delivers the strongest likely adjusted result, correct? It retains the largest number of parties involved. It keeps all participants concentrated, and it keeps each of them somewhat alert to the fact that unless they secure the lease, another party will. At Moses Lake, for instance, this has genuinely assisted us in advancing progress with multiple tenants, given that they understand they are competing for that power and for those time lines; so to the greatest extent we can, that will be our aim. Nick, we won't be able to guarantee that in every case—particularly when it comes to some of the largest companies involved—but we'll make every effort to limit exclusivity, maintain as much tension as we can, and ensure that as many parties as possible remain engaged.
Nick Giles
analystThat makes a great deal of sense, and I appreciate it, Ben. Perhaps a quick follow-up regarding electricity costs—people don't discuss them nearly as much as they did back in the Bitcoin mining days. I was wondering whether you could briefly address where your sites stand when it comes to electricity cost, and how much sensitivity tenants actually show toward those costs in your conversations?
Benjamin Gagnon
executiveThank you, Nick. Honestly, it hardly ever arises. Relative to the operating margins on the GPUs themselves, electricity costs are really fairly minor. And with everyone so fixated on the timeline to power, sensitivity regarding the price of electricity itself is far lower—there's much less of it. What everybody concentrates on first and foremost is always the timeline, the risk of deployment, and the risk of deploying on time. We'll probably see energy cost considerations enter the picture down the road. But my sense is that the growth bottleneck would first need to be relieved. I'd imagine supply would have to exceed demand before those economic sensitivities become the dominant thing people fixate on. In my view, when people focus on cost, it's the financing costs they focus on—not the energy costs.
Brian Dobson
analystThanks for the excellent detail on the lead-in and the call. As you talk with prospective clients and given that — I'm not after anything specific, just broadly, how are these prospective customers responding to higher building costs and higher financing costs? Do you figure that in the end this gets passed along and the yield on the contract stays fairly comparable to what we've been observing, or could it be that, with the potential for regulation, we might see improved pricing?
Benjamin Gagnon
executiveBrian, I appreciate the question. Regarding shifting costs, I'd say a few separate dynamics are at play. And I get why investors in the market are somewhat confused by this, since the figures you come across out there in the market vary quite widely. You could encounter solutions priced as low as $5 million a megawatt. You could encounter solutions perhaps upwards of $20 million a megawatt; and I don't think there's any genuinely established rule of thumb that applies across every site. Scale, location, timing, design, equipment, uptime requirements — all of it will factor into the cost. Our view, and what we said on the call, is that these projects get evaluated on a yield on cost basis, both by the tenant and by us in our role as developer. When construction costs rise, we do incorporate those into the lease economics so that the yield costs, or the yield economics, stay competitive. And if costs were to fall, the lease economics would be reflected the same way. So there's somewhat of a naturally built-in sort of hedge, you could say, in how these contracts get negotiated and structured. Where I think you run into a serious problem is when you sign a lease without having everything contracted on the back end; and then a gap exists between the price you've signed at and the price you're actually fulfilling at. And what we've managed so far — we've been quite conservative in how we proceed with these sites and in what we commit to, so that we avoid that problem, and we avoid that mismatch between signing a lease and actually pricing out each individual component inside it. So our strongest hedge against rising prices is simply trying to best time the lease and everything together, which is the strategy we've been carrying out.
Martin Toner
analystDoes what you've said today rule out a lease being signed before the end of the year?
Benjamin Gagnon
executiveLike I mentioned on the call, we're not going to give any kind of guidance on timing—whether that's positive or negative. We're just not going to offer any guidance on that. What I can tell you is that the tension has never been higher; we keep moving the sites forward. We made good progress even this morning. So we're continuing to push ahead. It's happening day by day; all of these are being worked and negotiated in real time. And so we'll give the market updates when it's appropriate and when we're in a position to do so, but we won't offer any kind of guidance expectations regarding time.
Martin Toner
analystFair enough. Now, could we turn to a few political questions? The Pennsylvania state Senate has flipped. Do you believe that will lead to legislation governing data centers, and if so, what impact would that have on the timeline?
Benjamin Gagnon
executiveLook, that's a tough one for us, and as a rule we prefer not to weigh in on politics, particularly with the midterms having just happened. What I would say is that Governor Shapiro won in a landslide, as everyone expected. He has stayed strongly supportive of data center construction, though within what he himself has described as the toughest guardrails anywhere in the country. When you consider the states that the midterms affected, Pennsylvania is likely in a better position than a great many other states across the past few days. And I think the reality is that data centers are going to remain a political topic for a while yet. I don't believe it stops with the midterms. What we do believe, though, is that we've been running effectively under the Keel standard, which is essentially quite close to the grid standard, ever since we began in Pennsylvania. And we think we'll be very, very well positioned for whatever comes along over the next year or 2. The feedback we've gotten from permitting offices, regulatory agencies, government offices, and local state senators and politicians has been greatly positive. Positive feedback has come to us from top to bottom, and we expect to keep making progress on our good work in Pennsylvania.
Martin Toner
analystJust one more. Is there anything politicians could do that would keep you from securing the remaining permit at Panther Creek or Sharon?
Benjamin Gagnon
executiveI'm not sure what any politician could actually do to halt that process, since these permits are highly technical in nature and really aren't political at all. I think the strictest guardrails in the nation that Governor Shapiro has already put in place represent very, very strong principles. And I don't think we should expect that additional action is needed in the immediate coming weeks. But we believe we have high confidence — our confidence in closing out our permits remains high. I don't know — I don't believe there's anything anyone could do at this time to stop that.
Benjamin Gagnon
executiveAppreciate everyone being here today, and my thanks go out to the whole Keel team. This quarter pushed all of us. We'll be back to speak with you in the next quarter, and by then we'll be further ahead. Thanks.
Operator
operatorThat brings today’s conference to a close. Thanks for joining us. You’re welcome to disconnect at this point. Have a good day.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Keel Infrastructure Corp. transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →This call discussed
For developers and AI pipelines
Programmatic access to Keel Infrastructure Corp. earnings transcripts and 132,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Keel Infrastructure Corp. or any ticker on your watchlist.
StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.