JSW Energy Limited (533148) Earnings Call Transcript & Summary

January 29, 2021

BSE Limited IN Utilities Independent Power and Renewable Electricity Producers earnings 60 min

Earnings Call Speaker Segments

Operator

operator
#1

Good day, everyone, and welcome to the JSW Energy Q3 FY '21 results conference call, presented by Axis Capital Limited. <<operator_script>> Kindly be aware that this call is being recorded. I'll now pass the line to Mr. Abhishek Puri with Axis Capital Limited.

Abhishek Puri

unknown
#2

Thanks, Monica. Speaking for Kotak Institutional Equities, I'd like to welcome everyone to this call covering JSW Energy's 3Q FY '21 results. Joining us from management are Mr. Prashant Jain, Joint Managing Director and CEO; Mr. Pritesh Vinay, Chief Financial Officer; and Mr. Ashwin Bajaj, Group Head, Investor Relations. At this point I'll pass things to Ashwin for his opening remarks, after which management will continue. Thank you.

Ashwin Bajaj

executive
#3

Good evening, everyone. My name is Ashwin Bajaj. As was mentioned <<inaudible>> in the introduction, Mr. Prashant Jain and Mr. Pritesh Vinay are here with us. We'll begin with some opening comments from Mr. Jain, and after that we'll turn things over to Q&A. So with that, I'll hand it to Mr. Jain.

Prashant Jain

executive
#4

Thank you, Ashwin. The quarter that just ended proved quite eventful for everyone here. As far as power demand goes, a strong rebound was recorded. During quarter 3, demand for power rose 6.4%. What's more, October brought double-digit growth in power demand, at 12%, driven by a lower base effect as well as a rebound in economic recovery. In the present quarter as well, during January, we observe power demand expanding at a rate of 4.5%. So across 9 months, we are witnessing a contraction in power demand of nearly 4%. My expectation is that we will end the year with power demand contraction under 3% and demand growth near 5%, 5.5% for H2. Owing to the lower base effect in H1, next year, in H1 we'll witness strong power demand growth. I am also fairly confident that a power demand growth rate of 4% to 6% will be seen consistently over the next 10 years' time frame. That, then, hands us a really solid opportunity. Regarding the company's net generation, long-term power generation — net generation climbed 6% year-on-year.

Prashant Jain

executive
#5

And overall, net generation rose by 1%. So that shows our merchant volumes came in lower. Since merchant volume was lower, EBITDA declined 6% to INR 655 crores. However, thanks to a lower interest cost, PBT came in 14% higher year-on-year, and profit after tax was up 12% if you strip out the one-off that was present in last year. Now, during the quarter, we performed exceptionally well on receivables. Receivables stood at INR 1,693 crores at quarter end, which is a 7-quarter low and 22% lower year-on-year. Thanks to strong cash flows and strong recoverability on the receivables, we brought our debt down by INR 952 crores — net debt was reduced during the quarter. And over the first 9 months, we have cut our debt by INR 2,226 crores in the first 9 months. As a result, at quarter end we stand at INR 6,719 crore of net debt, with a weighted average interest cost of 8.29%, which will also decline further because of the resets coming up in the quarters ahead. And with that, our net debt-to-equity is 0.46x, and I don't have the numbers in front of me, but I believe this will be the strongest balance sheet in the country, with a net debt-to-equity of 0.48% and net debt-to-EBITDA of 2.17%.

Prashant Jain

executive
#6

Now, moving forward — but before I get into the forward-looking part, I should note that during the quarter the JSPL loan was also fully settled. As a result, nothing remains outstanding from JSPL. Looking ahead, regarding the 810-megawatt SECI tender for which we received the LOI last quarter, we expect the PPA to be signed for 540-megawatt during the current quarter, while 270-megawatt will be signed in Q1 of next year. We are fully prepared when it comes to executing the project, both on the sites side and with respect to placing the orders. And we will be able to commission the project well ahead of the 24-month schedule measured from the date of the PSA. As for the 240-megawatt Kutehr project, execution there is proceeding on a fast track. And we are running according to schedule. On the PPA side, we expect that in the current quarter the PPA will be signed and sent to the regulator for approval. We are also working very actively with the group companies to finalize close to 1,100-megawatt of RPO obligation, which solar and wind projects will meet.

Prashant Jain

executive
#7

And over this quarter and the one after, we expect to wrap up those terms and conditions. We also anticipate those projects being finished within a time frame of 18 to 24 months. As a result, we think we'll be positioned to execute nearly 1,800 megawatts of solar and wind capacity plus 240 megawatts within a 36-month time frame. So that's our view of how capacity moves ahead. What that means is we've witnessed the conclusion of deleveraging on our balance sheet. So the net debt figure you're seeing, INR 6,719 crore, is the lowest. And we are — we exit at the bottom of the net debt. There are a couple of additional developments from the quarter. And at this Board Meeting, we have approved a slump sale of an 18-megawatt thermal power plant, which was set up at Salboni, to sell this asset to JSW's Cement. We have appointed a valuer, who will value the transaction. And it will be — the transaction will occur at the carrying value — investment value on our books or above that, and we will be able to disclose it by the end of this quarter, as and when the transaction is consummated.

Prashant Jain

executive
#8

We expect the transaction to close by 31st of March, and the sales proceeds to come in before 31st of March. The company has placed a very strong emphasis on ESG compliance, and that shows in its rating. From CDP, we have obtained the highest rating that any power producer in India has achieved. As a matter of fact, it is the highest rating, probably close to — globally among power producers, since the average rating worldwide is B and in Asia it is C. And we look forward to the possibility that, going forward, perhaps next year or the year after, we will aspire to reach the top leadership rating of A. In a similar vein, our MSCI ESG rating has also been upgraded from single B to BB, which is likewise the highest-rated power producer in India. And there too, we aspire to attain BBB and then an A rating going forward. So we are making substantial progress toward ESG compliance and also toward making this company a growth company in the renewability space. We are also very, very excited about the government policies in that regard. Today, the Ministry of Power has notified the HPO obligation trajectory as well.

Prashant Jain

executive
#9

So because of those HPO obligations, I expect roughly 10,000 megawatts of PPAs to be signed from now within the next 5 years. That also shows our commitment in the hydro sector, and we are working very aggressively to build that portfolio. Beyond this 2,000-megawatt — 1,800 megawatts of wind and solar plus 240 megawatts of hydro — we are trying to build a large book of resources across solar, wind, and hydro sites, because we believe execution time in solar and wind is very short. But you need to have those locations, or the sites, under your control — including the right of fee and then connectivity. So your company is working aggressively to acquire such locations in various states that have high potential for wind and solar resources, and we are continuously investing in that. And therefore, in time to come, we will be able to leverage it, and as and when good bids come at attractive return ratios, we will be able to participate in those bids and then grow the business. And with this, I end my opening remarks, and we are happy to take any questions you are having.

Prashant Jain

executive
#10

Much appreciated.

Operator

operator
#11

The operator has given the instructions, and the first question comes from Atul Tiwari at Citigroup.

Atul Tiwari

analyst
#12

Could you give us some color on the CapEx and the weighted average tariff you'll have for that 1,800-megawatt renewable project?

Prashant Jain

executive
#13

Alright, here's how to think about it: when it comes to SECI's 810-megawatt project, the tariff stands at INR 3. And for whatever wind capacity we're installing, the cost falls somewhere between INR 6 crore and INR 6.5 crores for each megawatt. Solar, meanwhile, will run from INR 3.75 crore to INR 4.1 crore per megawatt. That gives you the rough CapEx picture, and it shifts based on how much blending we end up doing. For balanced group captive projects as well, the CapEx figure per megawatt stays the same. We expect roughly 225 to 250 megawatts to come from solar that we'll be putting up, and somewhere around 800 to 850 megawatts from wind that will be installed. So that's the shape of it. Taking it all together, the range comes to between INR 9,500 crore and INR 11,000 crores — that's the band I can give you — for this full 1,800-megawatt build-out. And the group captive tariff should land in a comparable range to what you're seeing with the SECI 9 tariff. So that's how it works out. Yes.

Atul Tiwari

analyst
#14

Okay. And sir, just one thing I want to clarify on that. So this CapEx you mentioned, broadly speaking, does it include the cost of land, or is land everything?

Prashant Jain

executive
#15

The cost of power delivered at the delivery point goes up. So in the case of the SECI tender, the delivery point is the CTU periphery. And when it's a group captive arrangement, delivery is to that specific transmission point, wherever that happens to be. If a private TRANSCO is involved, then it's delivered to the customer. Or, if the route is through the STU, then it's at the periphery of a particular substation. So every cost is included — the preoperative costs, all statutory fees, everything all put together.

Operator

operator
#16

Aniket Mittal from Motilal Oswal has the next question.

Aniket Mittal

analyst
#17

Sir, I actually have a couple of questions, and they relate to the renewable side. First, I was hoping for your wider perspective on the recent drop in tariffs we have observed across the renewables market. And how are you viewing the intensity of competition in the sector at present? Second, in light of the tariff decline we have witnessed, I just wanted to understand — from the signing of the 810-megawatt PPA, you said that each spectrum 540-megawatt is to come in this quarter. Could you point out which discounts you are in talks with? And is there any uncertainty regarding the price, or rather the tariff, given the decline we have seen?

Prashant Jain

executive
#18

Let me put it this way, Aniket. Solar and wind are two very different creatures. That's the first thing. And each of them is driven by separate RPO obligations. In the same way, as of tomorrow, the hydro HPO obligation has been notified, and there the levelized power tariff will fall in a range north of 425 or 450. It will be above that level. So every category of renewable power carries its own competitive advantage, its own load profile, and its own generation profile. And the discoms need various types of power so they can manage their grid and also satisfy their requirements. That is exactly why they are willing to pay a tariff of that kind. So for wind, I believe the present tariff at INR 39 is genuinely achievable, and that is what gets demonstrated despite roughly 24 gigawatts of PPR in solar still awaiting signature. In wind's case, though, within 3 months — I'm saying the PPA will be signed in the quarter we're in now. So that demonstrates both how certain the PPA signing is and how viable the tariff is. So we are fully confident that this tariff is viable, and that is why, from the discoms' perspective as well, the PPA is going to get signed.

Prashant Jain

executive
#19

The second thing concerns your question about the tariff reduction that's mainly occurring in the solar segment. You really have to look at who is placing those bids. Each time a new player arrives, they submit a bid. Due to some option value, whatever it is they're attempting, those bids never actually see the light of day when it comes to finalizing the PPA and to execution by developers. Take the Badila project, done at a tariff of INR 244 3 years ago — how many developers actually built it out, and how many gave it up? And even now people are prepared to bid at a lower intensity. That's exactly where JSW Energy holds back from taking part in auctions of that kind, where we believe unsustainable behavior is on display. So we're prepared to focus on certain niche areas where responsible behavior is what we observe, and we keep looking at those areas. We believe enough opportunities exist for players such as us. Since the space is large, the country's renewable capacity addition requirement stands at close to 25 to 30-gigawatt annually, which will happen in due course of time.

Prashant Jain

executive
#20

And within that, there’s a really small slice available to us. So our preference is to focus on the niche segments.

Aniket Mittal

analyst
#21

That's useful, thanks. Still, you'd describe it as mainly coming from a wind angle. And sir, just so I can get a sense from your conversations—those 550 megawatts you intend to sign for PPA—going by the <<inaudible>>, are there discounts that have been shortlisted for this?

Prashant Jain

executive
#22

Yes, those exist, though I’m not able to discuss them. That falls outside what I can address — confidentiality binds me there, and SECI is the party handling it. Once SECI executes a PPA with me, then I’ll be in a position to disclose it. Still, I can give you a bit of color: the particular discount has already granted its approval. And it is now in the signing process.

Aniket Mittal

analyst
#23

Okay, so my next question is probably more from a group captive angle, and the opportunities over there. Maybe first on the thermal side — I just wanted to get a sense of the pending CP we have with JSW Steel Dolvi: what would the quantum of that PPA be? And when do we get it — when do we expect it to become operational?

Prashant Jain

executive
#24

Alright. There's one point in my opening remarks that I genuinely overlooked, and I apologize for that. On a company-wide basis, we've been running at 82% of the capacity tied up under long-term PPAs, and that figure has now risen to 87%, reflecting the acquisition we recently completed in Asian color as well as the added capacity at Dolvi. At Ratnagiri, the total PPA-contracted capacity will now stand at 1,145 megawatts against 1,200 megawatts of installed capacity, which leaves just 55 megawatts of open capacity there. At Vijayanagar, we have 310 megawatts of tied-up capacity out of 860 megawatts, so 550 megawatts there remains open. That's where we stand as we head into the next financial year. Operationalization will come through across various quarters, but you can reasonably be confident that for the majority of next year we will be operating at 87%. And looking further ahead, within a 2 to 3 years' time frame, I see our capacity becoming fully tied up — 100% tied up. What I mean to explain is that both Vijayanagar and Dolvi will be 100% tied up within that 2 to 3 years' time frame.

Prashant Jain

executive
#25

And any incremental capacity we're putting in place is 100% tied up, whether it's a key group captive, or Kutehr, or any new project, since project execution will happen only once we secure the PPA. So the company is turning into a 100% PPA tied-up company. And that's really what we see.

Aniket Mittal

analyst
#26

Yes, sir — one quick correction on that. So your understanding is that once the Dolvi tie-up is completed, which is expected next year, Ratnagiri would then have 55 megawatts of open capacity?

Prashant Jain

executive
#27

That's correct. With the Board's approval as it stands, we have secured it. Now, the key point is that regarding the PPA, it will likely be executed within this quarter. But open access is the concern. So delivery under open access will occur in stages, as their units are commissioned. From what we've been told, they will commission in Q1 of next year. In Q4 of this year and Q1 of next year, they are bringing their facilities online in phases. And it will probably be ramped up by Q2. So you'll see in Q4 of this financial year and Q1, Q2 of next year, this entire capacity being ramped up. That's why I say for the majority of the year, you will see this PPA secured.

Aniket Mittal

analyst
#28

Got it. And sir, regarding Vijayanagar, where are we seeing the visibility come from for the tie-up there?

Prashant Jain

executive
#29

One opportunity is a thermal RTC paired with SECI's 5,000-megawatt renewable tender. The second opportunity we're examining is group captive as well, where JSW Steel intends at some point to expand its capacity at Vijayanagar. So that's why, from a 2 to 3 year perspective, we expect to be able to secure the full capacity.

Aniket Mittal

analyst
#30

Alright, one quick point on growth captive. I believe you said there are roughly 1.1 gigawatts of obligations you intend to secure through the captive. Could you give us some sense of the timeline — how this might unfold? And also, what the model would look like? In other words, would it mostly be on a regulated basis, considering the arrangement involves a group captive?

Prashant Jain

executive
#31

So the timeline, as I mentioned, is that by March 2023, the full 1,800-megawatt capacity ought to be commissioned, landing in and around that single quarter, give or take. As for the tariff, you'll see it once the parties finalize things. But the format will resemble the SECI-controlled PPA format. It's a single-tariff type of structure, much like what SECI has. Because with all the group captive transactions we've done, we've done them at arm's length, either on the CRC formula basis or according to prevailing market conditions. And right now, for renewable contracts, our prevailing market conditions match the SECI PPA. So the structure will be similar to that.

Aniket Mittal

analyst
#32

So — all right. I mean, that was honestly the uncertainty I had, considering that if it were handled at a group captive level, how would the tariff be determined in that situation now? Would it...

Prashant Jain

executive
#33

We’ll share it with you whenever we find it.

Aniket Mittal

analyst
#34

Sure. Sure. And if I could just sneak in one final question. I was hoping for some color on how the merchant market is progressing for you. I believe there's been a sharp pickup in merchant prices happening in January. So I just wanted to get a sense of the possibility of any new contracts you signed, as well as what the dark space are that we're looking at right now?

Prashant Jain

executive
#35

Yes. On that point, my comment is that the market is very volatile and highly unpredictable. So what we have been observing is that an economic recovery is underway, and so are merchant tariffs. But I am not certain how long they will keep going on a sustainable basis. And I am not certain when you will see average prices rising. So that is why, if you might have noticed, as a company we are moving from merchant capacity to long-term capacity. So yes, we will be in a position to capitalize on whatever we can do in due course, as and when any kind of opportunity arises, but that does not split our long-term strategy of keeping any capacity open for merchant. So our focus is to tie up as much as possible and have as much as possible assured cash flows for our projects.

Operator

operator
#36

Mohit Kumar from DAM Capital has the next question.

Mohit Kumar

analyst
#37

And sir, three questions. First, regarding the SECI wind project: suppose we manage to sign the PPA within the next 1 month or 2 months — could we get this commissioned during the next fiscal, roughly 12 to 13 months from now? Or do you think it would take longer than that?

Prashant Jain

executive
#38

Look, as I mentioned, we have a 24-month obligation from the PSA signing date to finish the project, and we're pretty confident we'll deliver inside that timeline. And one favorable aspect I can walk you through is that with renewable projects, whatever the format, commissioning is required to happen in modular fashion. So under the PPA terms, even within a 50-megawatt block, you're able to finish and declare COD. That means quarter by quarter we'll be seeing progress and those sorts of things continuing to take place. And once PPAs get signed — and presumably what we'll put out as a company disclosure in the time ahead — we'll give investors a progress report and let you know beforehand what kind of schedule we're looking at for which quarter. What commissioning schedule we expect for that particular project. So we'll keep you updated on it. But one thing I can assure you of is that it will be well ahead of schedule, and it will come in a modular format.

Mohit Kumar

analyst
#39

Just one clarification, sir. Is there an option under the PPA to begin supply before 24 months? And what type of tariff would that be?

Prashant Jain

executive
#40

The tariff stays the same. You’re able to do it whenever you want. Its outer limit is 24 months. You can commission it earlier, and the tariff remains the same. And you can do it in a modular format of 50-megawatt.

Mohit Kumar

analyst
#41

Got it, sir. Got it, sir. Second, regarding the service with JSW Steel, we're going to — we will supply an increasing number of projects with steel or group companies. And I believe the group company must hold a 26% stake in that company — in that specific project, correct? So does that mean JSW Steel would need to purchase an increasing number of shares of JSW Energy in order to comply with that norm for group captive?

Prashant Jain

executive
#42

Meeting that standard is definitely necessary. And at this point, we’ll need to see whether existing arrangements are in place—whether the shares are already held by them, or whether a transfer comes from the other interfering promoter—and that will be carried out to reduce that exposure. For new-build solar and wind projects, the equity will likely be taken at the SPV level rather than at the main listco level. With existing thermal projects, it sits at the listco level, but since the assets belong to the JSW parent, both the Vijayanagar and Ratnagiri assets are owned by the listco. When we develop renewable projects, though, it happens at the SPV level. So in that case, the equity will be held at that SPV level from the outset. As a result, they will be subscribing to the fresh capital that gets issued.

Mohit Kumar

analyst
#43

And then thirdly, about Kutehr — sir, is that 4.5 tariff locked in for 25 years? Or can you share some kind of…

Prashant Jain

executive
#44

This is a regulated tariff, so the regulator will set the final tariff, and that decision will rest on total expenditure in line with the CERC regulation. According to our estimates, it should come in near INR 4.50 or below that.

Mohit Kumar

analyst
#45

All right, got it, sir. So in your view, the cost-plus project isn’t a big one—is that correct?

Prashant Jain

executive
#46

Right, right.

Mohit Kumar

analyst
#47

Sir, finally on this, sir, if I look roughly 24 to 36 months ahead, could you list the sorts of growth projects we're considering right now — even the 5 where we are nothing, where we've done absolutely nothing over the last 24 to 36 months. So aside from wind and — wind and hydro, is there anything in your mind, is this something we truly want to deploy our capital into and grow our profits with?

Prashant Jain

executive
#48

So stay with us, and you'll notice that quarter-on-quarter is a differentiator — something we've achieved in the tough to challenging environment over the last couple of quarters. We also delivered what we promised. And we did it differently from the industry. And as we promised, we're on the execution table for close to 2,200 megawatts or 2,100 megawatts of the renewable project. Some have already started, some are getting started, ready to just take off with this. And then quarter-on-quarter, you'll see the progress. And as I said, the opportunity is huge. We operate in a niche segment, niche — we're very selective. And you'll continue to see that our order book, or the growth book, is also going to be built up. So keep following us quarter-on-quarter, and you'll be surprised.

Operator

operator
#49

The following question comes from Rahul Bhangadia of Lucky Investment.

Rahul Bhangadia

analyst
#50

Apologies if this subject has come up on some earlier calls, but you just said you'll be selective — selective about which project you move forward with. Could you give us some idea of what equity IRRs or ROEs you're targeting, and what debt-equity mix you're referring to, across all the projects you mentioned earlier in this call — the entire INR 10,000 crores to INR 11,000 crores that you plan to invest over the coming 2, 3 years?

Prashant Jain

executive
#51

Typically, we target a structure of 25% to 30% equity with the balance as debt. And generally, we aim for a mid-teens equity IRR. That's the approach we've been taking. So we're not comfortable assuming an absolutely low-interest environment. We're not keen to assume that you can run the assets at 11%, 12% of equity IRR. We're not comfortable with P50 or P75 generation profiles — we're only comfortable at a P90 generation profile. So that's how we've been very conservative. And that's why we've been able to survive in a difficult environment. And that's why our receivables are at a 7-quarter low, whereas the industry's receivables are at a 7-quarter high.

Pritesh Vinay

executive
#52

Also, Rahul, if I could build on what was said regarding your other question about how the projects are leveraged. On Slide #5 of the presentation we posted, SECI 9 is going to be financed at a 70/30 debt-equity ratio, and Kutehr at INR 6,733 crores. As Prashant mentioned, in the quarters ahead, once the group captive projects are finalized and we discuss them, we will likewise cover the indicative leverage profile for financing those projects.

Prashant Jain

executive
#53

And it shows what we can do over the last 10 years — the first greenfield hydro project has reached financial closure, or rather approval has come through, door-to-door, for the 22-year term loan, and on more attractive interest rate terms. So that's the way we've been running things. And no hydropower project has ever been built with a PPA upfront. We were the first to do that in the country.

Operator

operator
#54

We’ll now take the next question from Rahul Modi at ICC Securities.

Rahul Modi

analyst
#55

Thanks for the time and the thorough responses. Sir, just a couple of questions. Sir, has there been any movement on the Ind-Barath NCLT approvals?

Prashant Jain

executive
#56

We’re keeping our fingers crossed too, and we’re working together with NCLT. So right now, things are moving slowly because of the ongoing pandemic and the large backlog in front of them. And — so I’m not sure how long it will take, but we’ll keep working with the various authorities.

Rahul Modi

analyst
#57

Okay, so about the JSPL loan you brought up in your opening remarks — you said it's been repaid. What amount did you close on that this quarter? And was the whole thing paid in cash? So you're saying that because of...

Prashant Jain

executive
#58

Yeah, yeah. It's a 100% cash deal, plus the accrued interest — 100% was repaid. Pritesh?

Pritesh Vinay

executive
#59

Yes, yes, yes. So Rahul, at the close of the quarter, the outstanding balance is 0. Just to give us tens of tons at the start of the financial year, roughly INR 261-odd crores was owed. So within the 9-month period, they have paid out everything, including the interest on that. Yes. So there's nothing outstanding from December onwards.

Rahul Modi

analyst
#60

All right. Great. Then, sir, one final thing — I'd like to get a sense of whether there's any reason behind selling the 18 megawatts of plant at Salboni to JSW Cement?

Prashant Jain

executive
#61

The sole reason, Rahul, is what I mentioned earlier — we couldn't synchronize the plant owing to the discount approvals that were required. And the asset — we couldn't get it commissioned. So — and that asset had been built for JSW Cement. And that is exactly what shows our — the prudence as well between the related party: if some investment has been made by a company in which minority shareholders are present and the asset hasn't been put to use, the counterparty has stepped forward and is ready to take over that asset, even if it isn't being fully used. So that is what the 2 parties have done. And that is what shows the credibility between our counterparty.

Operator

operator
#62

Shantanu Mantri from MKVentures has the next question.

Shantanu Mantri

analyst
#63

Yes. Sir, it's genuinely impressive to watch the deleveraging happen. Net debt now sits under INR 7,000 crores, so we're very pleased about that. Sir, I just wanted to check something: that figure of INR 6,719 crores leaves out working capital and acceptances, so what would that amount come to?

Pritesh Vinay

executive
#64

So Shantanu, when the quarter wrapped up, the outstanding acceptances plus <<inaudible>> came to roughly INR 623 crores.

Shantanu Mantri

analyst
#65

Yeah, yeah, yeah. All right.

Pritesh Vinay

executive
#66

During this quarter, that figure rose by roughly INR 23 crores. At the close of September, I believe it stood at approximately INR 600 crores.

Shantanu Mantri

analyst
#67

Okay, okay, okay. And sir, for the next question, let's say we've got this INR 10,000 crores to INR 11,000 crores of investment coming up over the next, say, 36 months. So if I do a quick rough calculation, with a 70-30 debt-equity split, that's roughly INR 3,500 crore of equity being infused. And so would it be — I just wanted to understand whether the cash flows from the current thermal assets will be enough to cover this equity requirement?

Operator

operator
#68

My apologies for interrupting you, Mr. Mantri, but we’re picking up some noise from your background. While management responds to your question, please mute your line.

Shantanu Mantri

analyst
#69

Yeah, absolutely.

Prashant Jain

executive
#70

Basically, we've been producing roughly INR 2,000 crores to INR 2,200 crores of free cash from the business we already run, and that will go toward this growth in order — and also, if you look at our current debt-to-EBITDA and debt-to-equity profile. We're able to lever up the balance sheet even at the parent level and then deploy that money as equity at the subsidiary level. So there's ample headroom available. If you run the numbers, any project in the power sector is done at 5.5x debt-to-EBITDA and 3:1 debt-to-equity. And with a 0.48x debt-to-equity and 2x debt-to-EBITDA, you have enough headroom that such leverage ratios aren't a worry. And — so what's needed right now is to grow the balance sheet.

Shantanu Mantri

analyst
#71

Yeah, yeah. Yes, sir. And sir, one final question. So, as you can see on the balance sheet, we hold a few investments, such as in JSW Steel, and this is, like, what the stock price of JSW Steel is now. So is there any chance of monetizing those investments, say, given a big opportunity in the renewable space? So freeing up some of those investments — is that on the cards?

Prashant Jain

executive
#72

When the time comes that I require funds, I'll review the different possibilities. Right now, I have sufficient capital and — to expand the business. So if such a need arises, we're receptive to every type of opportunity.

Operator

operator
#73

Our following question comes from Aniket Mittal, who is on the line from Motilal Oswal.

Aniket Mittal

analyst
#74

Sir, I believe most of what I wanted to ask has already been addressed, though I'd just like to get a feel for the receivables side of things — clearly you've handled that quite well this quarter. Still, when I look at the total receivables figure, my sense is it remains somewhere in the region of 80 to 90 days. So, put it this way: looking from the year-end vantage point, or as you move into the following year or thereabouts, do you expect that figure to come down further?

Prashant Jain

executive
#75

Yeah, yeah, yeah. I’m pretty sure this is going to come down even more. And if you take INR 1,693 crore, as we speak it’s under INR 1,200 crore. But the situation is fluid. What I can say is that we’ve managed to outperform the industry, and we’ll keep outperforming the industry. But if things get worse for the industry, our receivables get worse too. At the same time, though, we’re collecting all the late payment surcharges, since we operate under merit order dispatch. And that is something we can demonstrate. Even through the pandemic, our long-term PPA sales rose. And here I’m referring to the distribution companies. So at our Barmer plant, thermal generation is 28% higher this quarter than in the previous quarter. My long-term thermal PLF stands at 77%, versus 71% a year earlier, despite merchant volume being almost negligible. A year ago, my merchant volume was substantial. So you can see that we’ve been running on a quality basis. Despite a 7% rise in the wage bill for 3 years in a row, our O&M costs have kept declining. And that’s — and our — we’ve achieved the lowest auxiliary power consumption in several decades, and our plants are running at the best efficiency parameter in the country.

Prashant Jain

executive
#76

We've done a great deal of digitization and brought a lot of innovation into how we operate through this difficult period. And at this point we're fully prepared, in a new avatar, to pursue growth. That's exactly what I told one of the investors who was asking — you will be positively surprised by how we perform in the quarters ahead.

Aniket Mittal

analyst
#77

Okay, and sir, just so I understand — you said the INR 1,600 crores figure has now come down to INR 1,200 crores as of right now. Of that amount, how much would be overdue if you return it in 45 days?

Pritesh Vinay

executive
#78

So Aniket, roughly 40% of that would be overdues. Just to give you a sense of it, Prashant mentioned earlier that on a year-on-year basis, our total receivables are down 22%. But in fact, overdues are down 30% year-on-year. So the limited point I'm trying to make is that a lot of the incremental collections that have come in have actually gone toward bringing down the overdues. So the -- so it's a very good quality improvement in receivables. Yes. At peak, we've seen maybe at the end of the June quarter, which was the first quarter of the full lockdown, the share of overdues in total receivables as high as 60%.

Prashant Jain

executive
#79

Also, for most of the long-term overdue amounts that were disputed, we've received favorable orders from various regulatory bodies. So those will materialize over the next 1 or 2 or 3 quarters. That's why we expect the trend to be much better going forward.

Aniket Mittal

analyst
#80

Yes, sir. Sir, I believe during your opening remarks you noted there could be a chance that our average cost of debt moves lower once another interest reset takes effect. So how should we think about that cost — I mean, how far can it get <<inaudible>>?

Prashant Jain

executive
#81

You'll see that next financial year, below 8%.

Aniket Mittal

analyst
#82

Understood, sir—we'll get it below 8%. Got it. And sir, just one question on this—regarding the figures we reported this quarter. One thing I noticed was that, looking at hydro generation for the quarter, it's actually down, I believe, around 4-odd percent, yet EBITDA has risen roughly 15% year-on-year. So is there something that flips?

Prashant Jain

executive
#83

This is a two-part tariff business, so generation doesn't really factor into it. As long as I'm above the design energy, I get recovered through the full recovery of my cost. That's why it's protected, first of all. So generation only serves an optical purpose. Other than that — you need to look at the EBITDA, and my EBITDA is better thanks to lower O&M cost and certain recoveries that I'm getting. 2 years ago, generation was lower. Because of that, I received a compensation in the following year's tariff. That is what shows up in higher power costs and higher EBITDA. So in any year in a hydro business, if my generation is lower, that EBITDA shortfall gets compensated the next year in the tariff. So that's how it works. So on a normalized basis, you are protected for your EBITDA.

Pritesh Vinay

executive
#84

And building on Prashant's comments, Aniket, Karcham also recorded some incentive income thanks to higher BAFs in the quarter. That comes from the greater visibility. So that played a part as well.

Operator

operator
#85

Our next question comes from Mohit Kumar at DAM Capital.

Mohit Kumar

analyst
#86

I've just got a single question regarding receivables. Sir, could you tell us what the receivables from Raj WestPower Ltd were as of March '20, September '20, and December '20?

Prashant Jain

executive
#87

Apologies — could you say that again, Mohit?

Mohit Kumar

analyst
#88

Could you give me the receivable figure for Raj WestPower as of March '20's close, September '20's close, and December '20's close?

Pritesh Vinay

executive
#89

Mohit, I’m sorry, but we don’t disclose receivables by entity or by customer. So unfortunately, that isn’t something we can provide.

Mohit Kumar

analyst
#90

All right, so just to get a sense of direction — could you explain what the Rajasthan payment is? Does it compare favorably with the other states? Or how does it work — is there anything you're able to say about that?

Prashant Jain

executive
#91

From our standpoint, we have no issue at all with how all the discounts we work with have handled their payments. Naturally, hiccups do occasionally arise with our customers, and that is because of their cash flow position. When such a hiccup occurs, though, we collect a late payment surcharge under our PPA, and that surcharge exceeds our cost of capital, so we find ourselves in a happy situation.

Mohit Kumar

analyst
#92

And the second thing is whether we should expect a big payment in Q4 as a result of the discount liquidity scheme?

Prashant Jain

executive
#93

Look, we're discussing our receivables, and those receivables are on track — they keep declining consistently and performing better. We then expect that trajectory to improve going forward, thanks to the resolution of certain disputes where favorable orders are coming our way. And should there be an improvement in the liquidity of the discount, then certainly that will be icing on the cake.

Operator

operator
#94

Moving on to the next question...

Pritesh Vinay

executive
#95

Could we have the final question, please?

Operator

operator
#96

Yes, sir. The final question comes from Ashutosh Chaubey with Centra Advisors. <<operator_script>> We're not getting any response from that participant's line.

Ashutosh Chaubey

analyst
#97

Hello? Can you hear me?

Prashant Jain

executive
#98

Sure, Mr. Chaubey, we’re able to hear you now. Go ahead, please.

Ashutosh Chaubey

analyst
#99

Hello? Hello?

Operator

operator
#100

Sir, the current participant’s line isn’t responding.

Ashutosh Chaubey

analyst
#101

Hello?

Prashant Jain

executive
#102

Mr. Chaubey?

Ashutosh Chaubey

analyst
#103

Hello?

Prashant Jain

executive
#104

Yes, we're able to hear you. Go right ahead.

Ashutosh Chaubey

analyst
#105

Yes. So I wanted to ask, now that we know in recent years the cost of solar has come down by as much as 90%. So when signing the PPA, is there any clause that protects India from all these sorts of duties — that is — yes, that's the safeguard duty, which is on Chinese imports of solar panels and solar glass? So is there some kind of — is there some kind of clause in the fee when you signed the PPAs at INR 2 or INR 2.5 that as and when prices go up, going forward, the cost of power signed in these PPAs will also go up? Is there some kind of a clause?

Prashant Jain

executive
#106

No, no. That's not—I can address that, since I'm speaking in general terms here, because we haven't carried out any PPA where the solar projects go, we've only—in the next couple of days we're just going to do a hybrid. With solar, when a project developer submits a bid, she—they're making assumptions about panel prices and about the duty structure as it stands now. On that basis, every cost is theirs, and any changes are theirs, and they have to place a bid. The sole item that can be permitted to alter the tariff is a change in law. Change in law means any modification of the duty structure made by the central government. Then you can go and argue that at bid time, this was the duty structure or the tax structure in force, which has altered my economics, and because of that, this is the impact. Then, subject to the regulator's approval, you'll have it approved. Apart from that, any other price movement falls to the project developer's account—whether that's the interest rate, whether that's panel prices, or any other aspect.

Ashutosh Chaubey

analyst
#107

Alright. Got it, sir. Sir, could you give me a number — just a rough number — for what your regulated equity would be?

Prashant Jain

executive
#108

I’ll have the IR department give that to you offline.

Ashutosh Chaubey

analyst
#109

Sir, honestly, I’ve been attempting to reach the IR department for a while now. I tried getting in touch 2 to 3x, but nobody got back to me from their end.

Prashant Jain

executive
#110

They’re going to come up to you.

Ashutosh Chaubey

analyst
#111

Okay. I've also sent the same thing, I don't know, 3 or 4 times.

Prashant Jain

executive
#112

That's not an issue. They'll reach out to you and have a conversation with you later today. Thanks for sharing your feedback.

Operator

operator
#113

Our final question comes from Varun Thapar at Optum Investment.

Analyst

analyst
#114

I just wanted to ask about the net transition at Vijayanagar and the short-term sales at Ratnagiri, which have gone down on a Y-o-Y basis. What would be the reason for that?

Prashant Jain

executive
#115

So, Vijayanagar — net generation declined over the long term, mainly due to a capital shutdown last year at a captive unit belonging to JSW Steel. As a result of that, we were running and supplying power to them. That explains why you're seeing that difference.

Analyst

analyst
#116

All right. And the short-term sales for Ratnagiri have declined?

Prashant Jain

executive
#117

Short-term sales are lower because the market conditions are poor.

Analyst

analyst
#118

And moving ahead, what guidance would you give for Vijayanagar — I mean, on the capacity side?

Prashant Jain

executive
#119

As I mentioned, 87% of the long-term capacity is secured under PPAs. The remaining 13% depends on a favorable merchant market, and right now we don't have particularly strong visibility on that front where Vijayanagar is concerned. So whenever a solid opportunity arises, we'll be in a position to take advantage of it. Still, our approach is to lock in this capacity, and we believe we can accomplish that within the next 2 to 3 years. Ratnagiri is essentially finished, while Vijayanagar is still outstanding and will require another 2 to 3 years.

Operator

operator
#120

Appreciate it. Since nobody else has anything to ask, at this point I'd like to pass things back to the management team for their closing remarks.

Abhishek Puri

unknown
#121

Alright. Thanks, everyone, for being here, and if anything else comes up, don’t hesitate to reach out to IR. Thanks.

Operator

operator
#122

Thank you. That brings this conference to a close on behalf of JSW Energy and Axis Capital Limited. We appreciate your participation, and you're welcome to disconnect your lines now.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete JSW Energy Limited transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

This call discussed

For developers and AI pipelines

Programmatic access to JSW Energy Limited earnings transcripts and 132,000+ others is available through the EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research

OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in JSW Energy Limited or any ticker on your watchlist.

StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.