JSW Energy Limited (533148) Earnings Call Transcript & Summary

July 30, 2021

BSE Limited IN Utilities Independent Power and Renewable Electricity Producers earnings 62 min

Earnings Call Speaker Segments

Operator

operator
#1

Good day, ladies and gentlemen, and welcome to the Q1 FY 2022 earnings conference call for JSW Energy Limited, hosted by JM Financial. Just a reminder that all participants will be in listen-only mode, and after the presentation concludes there will be an opportunity for you to ask questions. If you need assistance during the call, please signal an operator by pressing star then zero on your touchtone phone. Please be aware that this conference is being recorded. I'll now hand the conference over to Mr. Subhadeep Mitra from JM Financial. Thank you, and over to you, sir.

Subhadeep Mitra

analyst
#2

Thanks, Margaret. Hello everyone, good afternoon. Speaking for JM Financial, I'd like to welcome all of you to JSW Energy Limited's Q1 FY22 earnings conference call. At this point, I'll turn the call over to Ashwin Bajaj, Group Head, Investor Relations at JSW Energy. Ashwin, the floor is yours.

Ashwin Bajaj

executive
#3

Okay. Thanks, Subhadeep, and I appreciate you hosting today's call. Good evening to all of you. Ashwin Bajaj here. I'm glad to welcome everyone to the JSW Energy results call covering Q1 FY 2022, along with an update regarding our strategy for net growth in renewables. Joining us on this call is our management team, represented by Prashant Jain, CEO of JSW Energy, and Pritesh Vinay, CFO of the company. We'll begin with opening remarks and afterward open the floor for Q&A. So with that, I'll hand things over to you, Mr. Jain.

Prashant Jain

executive
#4

Thank you, Ashwin. Good evening, ladies and gentlemen. During the quarter that just ended, power demand was very robust — we saw growth of 16.4% for the quarter, driven mainly by the lower base effect from the lockdown in the prior year, an effect that has been easing over time. In April, power demand growth stood at 38%, then moderated to 6.3% in May. For June, it was 8.6%. Then in July, power demand has been rising at a rate above 13%. We expect robust power demand growth this year, given the strong economic recovery and the lower base seen the year before. That was also reflected in our total net generation growth for the quarter versus the prior year, at 4%, and the same 4% showed up in long-term net generation growth. Thermal generation rose 13%, while hydro generation fell 15% because less water was available. As a result, EBITDA was almost flat, but profit after tax came in 23% higher if I exclude the exceptional item — INR 92 crore of additional cost, mainly tied to the green bond the company issued.

Prashant Jain

executive
#5

Taking that into account, profit after tax came in at INR 261 crore. We also started running our Karcham Wangtoo plant at a higher capacity this quarter, and the CEA approved that in 2 phases. An extra 45 MW has been in operation from that point, and that figure will rise to 91 MW in the coming financial year — by that I mean the coming season. Receivables fell 30% year-on-year during the quarter. On a quarter-on-quarter basis they rose by INR 600 crore, which reflects the seasonal pattern of the hydropower business given the extra selling we do. Add to that weak collections in April and May because of the second COVID wave. We see this easing, and it should return to the usual receivables cycle within two quarters. Net debt for the company rose by a further INR 360 crore, mainly because of CapEx and also because of less cash on hand from the higher receivables. Beyond that, the company paid down over INR 200 crore of debt in the quarter. Strong liquidity has also been kept up. On the projects we are carrying out, the SECI 9 PPA is now fully signed. In total, 810 megawatt of PPAs are signed with SECI.

Prashant Jain

executive
#6

Previously, during May, we signed 540 megawatts. Then in July, as I indicated on the last call, these 270 megawatt PPAs were signed with West Bengal and Chhattisgarh. Regarding SECI X, the 450 megawatt PPA will be executed during the present quarter, as has been laid out. The 958 megawatt group captive PPA with JSW Steel has been signed. Beyond that, connectivity approvals for the whole of SECI nine and SECI X projects are already in hand. We have also placed orders for every solar module and the wind turbines with the top OEM manufacturers. Construction is moving ahead at full pace, and as we explained, the 225 MW solar plant will be commissioned within this financial year. Starting next financial year, each month 100 to 150 MW of capacity will be commissioned across the SECI projects. We feel quite pleased with the progress we had outlined for our 2.5 GW of renewable power capacity. Beyond that, two developments exist within the renewable business. First, yesterday we signed a collaboration agreement with FFI, a 100% subsidiary of FMG Group, a listed company and a major iron ore producer and exporter, with a market cap near INR 80 billion, net income above INR 5 billion, and strong liquidity cash flow.

Prashant Jain

executive
#7

The company has been putting relentless effort into green hydrogen and green ammonia projects aimed at industrial use and mobility. JSW Future Energy and FFI have come together in order to combine a large pool of capital, industrial application, and technology to build green hydrogen and green ammonia for a range of industrial uses and mobility in India. To give you some background, roughly 6 million tonnes of grey hydrogen is produced in India at this point of time, and it comes primarily from natural gas, coal, and fossil fuel. That grey hydrogen serves the chemical sector, refineries, fertilizers, and steel plants. Green hydrogen, which is produced by a water electrolyzer that consumes green power to make green hydrogen and green oxygen, can replace the grey hydrogen. There is a large synergy between the steel plants and the point where hydrogen is used by the electrolyzer as well as the heating of the ammonia that produces hydrogen. Hydrogen is used in all our DRI plants, in our annealing furnaces, and in galvanizing lines. Incidentally, the JSW Group is already running large electrolyzers to produce grey hydrogen for various applications. That gives us an immediate application to begin replacing the grey hydrogen with green hydrogen.

Prashant Jain

executive
#8

Beyond that, there's a substantial use case in substituting fossil fuel for mobility, where hydrogen fuel cells are able to power long-haul locomotives, excavators, dumpers, trucks, and cars, and ammonia can likewise be used to run ships. FFI has been building all of these kinds of technologies and products, and together JSW and FFI will be assessing them across various applications to make use of this. The Government of India and NEPIO have been at work on a green hydrogen mission and on policy making. Industry has been asked to submit comments. A green hydrogen policy framework will be in place very soon. The framework is laid out to follow similar lines to how hydropower and renewable power were developed, through establishing a green hydrogen obligation framework in which industry will be mandated to use green hydrogen in place of grey hydrogen over a period of time. That will boost penetration. The most important thing here is that this is a proven technology. The only issue is that the cost has to come down. To give you some color, grey hydrogen today is produced at between $1.7 to $2.5 per kg, while green hydrogen can be produced at between $3.75 to $4.5 per kg.

Prashant Jain

executive
#9

Bringing this technology to a large scale can achieve that cost reduction, along with better efficiency and lower power costs. These developments will take shape across a five-to-seven-year period. That is where we see enormous potential to displace the 6 million ton market, which will expand into a 20 million ton hydrogen market by 2050. Green hydrogen presents a massive opportunity. Beyond that, mobility offers yet another market — and mobility is the future. That is the area where the company will collaborate with FFI to develop a range of projects. One more development: at the current board meeting, the board granted in-principle approval for reorganizing the green and grey businesses — the green power and grey power business — so the company gains flexibility to draw capital or strategic investors who are making particular choices to focus solely on either the green power business or the grey power business. The board has tasked a board-appointed committee with selecting financial advisors, legal advisors, and valuers to propose various options and schemes, which the board will consider in due course. That concludes my opening remarks, and I would now like to open the floor for any questions and answers, if there are any.

Prashant Jain

executive
#10

Thanks. Operator, let's go ahead and open it up for questions.

Operator

operator
#11

Thanks a lot. We're moving into the Q&A portion now. If you'd like to pose a question, you can hit star and one on your touchtone phone. Should you want to drop out of the queue, just press star and two. We ask that participants use their handsets when asking a question. Anyone who wants to ask something, please press star and one now. Ladies and gentlemen, we'll pause briefly while the queue comes together. Our first question comes from Aniket Mittal of Motilal Oswal Financial Services. Please go ahead.

Aniket Mittal

analyst
#12

Yes. Thanks for giving me the chance. My first question, sir, concerns the green energy technologies you are examining. You brought up the framework of agreement with Fortescue. Could you give a bit more detail on how you see this technology becoming viable over a period of time? Second, regarding the capital expenditure itself, is there any capital commitment you intend to make on this technology?

Prashant Jain

executive
#13

With bigger operations, costs will come down. Five years ago, solar power cost was over INR 6, and now it's under INR 2. The learning curve shifts with the scale of commercial production, and that's exactly what will happen here. It's the same story as with electric vehicles. This is a proven technology. The only thing is there are three components, as I mentioned. First, 60% of the cost of this green hydrogen comes from power, and power costs keep falling consistently. If we deploy certain technologies that raise efficiency, the power cost drops. When power cost drops, green hydrogen cost drops. The second part is the electrolyzer cost, which will fall thanks to large-scale production. The third is electrolyzer efficiency, currently running close to 64% to 65%, which is expected to rise to 80%. These are the three elements that will play out with large-scale production over a period of the next five to six years, and green hydrogen cost will be lower than grey hydrogen cost.

Prashant Jain

executive
#14

Just as we see today, green power costs less than grey power. We’ve already gotten to that point. What will drive the change is the size of the operating scale—that’s the key factor. On capital expenditure, to give you a rough sense, green hydrogen electrolyzers currently run about $600 to $700 per kilowatt hour, and based on estimates that have been made, that figure will fall by 80% over the next 10 years. That’s how the learning curve is projected. Within the next five to seven years, the costs will reach parity. Until then, these will be offset through an RPO obligation or green power and green hydrogen obligations. Five years ago, solar power was sold at INR 5, INR 6, and a solar power purchase obligation existed, which is why PPA agreements were in place. Green hydrogen purchase agreements will emerge, and then within a five-year timeframe, this cost will come through. These points relate to industrial applications, which will be in the refinery and fertilizer segments.

Prashant Jain

executive
#15

In mobility, this might take a bit of time, but our view is that with large-scale operations such as mining, locomotives, and ships, those are the segments where it will make economic sense in probably 4 to 5 years' time.

Aniket Mittal

analyst
#16

I just want to confirm something, sir: under this agreement with SECI, are there any capital commitments at this point — say, over the next 2 years? My understanding is that it's still more of an assessment process on your side. But looking ahead those 2 years, would any kind of capital investment or commitment be involved?

Prashant Jain

executive
#17

Yes, definitely. That's on the way. Once our scoping exercise is finished, we'll conceptualize a range of projects, and those will then go before the respective boards; the boards will then decide to review those opportunities, evaluate them, and consider those capital commitments. Whenever the respective boards of both companies consider it, we will let you know.

Aniket Mittal

analyst
#18

Alright, thank you. Sir, perhaps just one additional question so I can grasp how the ordering pipeline currently stands on the renewables side. I believe, sir, it is quite clear that our emphasis has been on wind and hybrids, particularly in the bids we have seen lately. Just to get a sense, in your view, what volume of bids do we expect from SECI and other states for wind and hybrid projects over the coming 15 to 18 months? That would give us a picture of the opportunity you have there.

Prashant Jain

executive
#19

My view is this: normally, when demand rises 5%, that means roughly 9 GW of demand that renewable sources will need to cover. Meeting that calls for somewhere around 25 to 30 GW of renewable capacity. That's the sort of volume I expect agencies to bring forward each year.

Aniket Mittal

analyst
#20

Specifically regarding wind as well as hybrid?

Prashant Jain

executive
#21

Honestly, it's really hard for me to say how much of that will be hybrid versus how much will be standalone. If you look at it on a consolidated basis, you can think of 25 to 30GW per year.

Aniket Mittal

analyst
#22

All right. That’s all. Thanks. I’ll get back in the queue.

Prashant Jain

executive
#23

Appreciate it.

Operator

operator
#24

Thanks. If you'd like to ask a question, just press star 1. Our next question comes from Subhadeep Mitra of JM Financial. Please go ahead.

Subhadeep Mitra

analyst
#25

Thanks. Sir, about that earlier question—you said someone could look at an annual pipeline of 20 to 30 gigawatts when it comes to tenders based on tariffs. In your view, since we have Basic Customs Duty and ALMM taking effect starting next year, do you see any capacity constraints in the short term that could arise, given that domestic solar manufacturing capacity is likely capped at 6 or 7GW?

Prashant Jain

executive
#26

You can approach this in a couple of ways. First, importing panels remains possible, but the panel price will be higher, and that gets passed through into a higher tariff in the bids. That's likely what you've noticed and seen: the tariff secured before the 40% duty was announced came in at close to INR 2 in the bids — actually INR 1.99 — and then rose to INR 2.43. So there's effectively a 21% rise in the tariff, which has already taken place and which mirrors that higher duty. In addition, new capacities are emerging for manufacturing panels in India, where cells can be brought in, since the duty on cells is lower than the duty on panels. There's also incremental cell manufacturing capability coming up, which will be on stream in production in calendar year 2022 and will import wafers, where the duty is zero. It's going to be a hybrid situation, where some capacity gets imported in panel form, some capacity gets imported in cell form with panels manufactured in India, and some capacity takes the form of importing wafers and cells while the panel is manufactured in India.

Prashant Jain

executive
#27

That is how this blended tariff will be reached — which is exactly what you're observing, a 21% increase in tariff. We really need to see how domestic capacity gets ramped up. With this duty in place, I believe that capacity ramp-up is going to happen fairly quickly. There will be upward pressure on solar power tariffs going forward.

Subhadeep Mitra

analyst
#28

Got it, thanks for clarifying. And second, as you said, with tariffs beginning to rise, my understanding was that a lot of DISCOMs were hesitant to sign solar PPAs because of the race to the bottom on tariffs—everyone wanted to hold out for the next tender, which might offer a slightly lower tariff. Now that this trend has reversed, are you seeing any traction in incremental PPAs being signed?

Prashant Jain

executive
#29

I think they'll be signed at this point, since that was the issue that had been occurring with solar PPAs. In my view, the tariff isn't what's causing the trouble — it's the trend and the fluctuation. That's the reason you can see that for our SECI-9 PPA of 810 MW, 100% of the capacity has been tied up and the PPAs are signed, and in the shortest span of time, something that hadn't even been witnessed in solar bids. It's more about the fluctuation and more about the variation. That is what has acted as a deterrent to the signing of solar PPAs, which I believe will get signed because the tariff will begin moving up.

Subhadeep Mitra

analyst
#30

Got it. One last thing to clarify regarding the SECI-9 PPA signing — you mentioned that the back-to-back PPAs with the respective DISCOMs have been signed as well.

Prashant Jain

executive
#31

Yes, those are signed and in effect now.

Subhadeep Mitra

analyst
#32

You're right. Thanks very much, sir. That's all from me.

Operator

operator
#33

Thanks. We’ll take the next question from Mohit Kumar at DAM Capital. Mohit, please go ahead.

Mohit Kumar

analyst
#34

Yes. Good evening, sir, and congratulations on a solid set of results plus the many new initiatives you've launched. My first question, sir: you've laid out a 10 gigawatt target through FY 2020. Within that 10GW, how much is typically captive PPA? And my second, related question: how does the pricing work on it?

Prashant Jain

executive
#35

First off, the figure isn't 10 gigawatt — by FY 2030 we're discussing 20 gigawatt of capacity. Second, every one of these PPAs comes through competitive bidding, whether that's captive or third party. We have to take part, and there's no guarantee we win it or lose it. On captive too, sourcing from JSW Steel wasn't our pick. JSW Steel ran a competitive bid, we took part, we emerged as L1, and that's how we landed it. We also won the SECI bids by finishing as L1. Whether we get it isn't something we control.

Mohit Kumar

analyst
#36

Got it. In the quarter, operational capacity rose to 1,045 MW. Do you sell that surplus capacity on the merchant market?

Prashant Jain

executive
#37

These are the bilateral agreements that serve as the basis for our sales, and the PPA will be signed in due course.

Mohit Kumar

analyst
#38

So this 45 MW is on top of that, correct? It comes in addition to the PPA.

Prashant Jain

executive
#39

Yep, that's exactly what I said.

Mohit Kumar

analyst
#40

Yes, sir. One last thing on this, sir, regarding hydrogen. Does this agreement with FFI apply only to us? Would you be open to going after the PLI scheme that will most likely appear in the next eight to nine months, particularly for electrolyzers?

Prashant Jain

executive
#41

We aren't saying anything about manufacturing.

Mohit Kumar

analyst
#42

All right. Got it, sir. Thanks, sir. That's all. Thank you.

Prashant Jain

executive
#43

Appreciate it.

Operator

operator
#44

Thanks. Our following question comes from Pravin Maheshwari, who is on the line from Edelweiss. You have the floor.

Pravin Maheshwari

analyst
#45

Yeah. Hi there, sir. Good evening. Appreciate the chance to ask. Sir, you brought up on the green energy side, the green hydrogen side, that the mobility segment will probably need some time, perhaps around 9 to 10 years. Now on the other hand, we're just seeing the EV ramp-up that we're looking at. Maybe over the next 7 to 9 years, there could be meaningful EV adoption. I just wanted to get your thoughts on this, whether the two will co-exist or whether green hydrogen sort of threatens to eclipse the EV side, really.

Prashant Jain

executive
#46

Thanks for that question. Look, the key thing we have to grasp at this point is that this technology is proven and well established — it's already widely used for making green hydrogen. A market for it exists within the country. In today's conditions, there are two requirements. First, we need a policy environment that allows this technology to be developed at mass scale to replace gray hydrogen. That's the one side I spoke about — just as gray power was replaced by green power through a policy intervention with a certain purchase obligation, in the same manner the new policy framework is being put in place, and the Government of India has already begun the consultation process, with stakeholder consultation under way, and in all likelihood, within a 12 to 18 month window, that policy will be in force. The second thing is bringing down the cost, and that will happen as the size of such a market grows. Only then will commercial production and more and more investment come into this area, and that will bring the cost down. That's why I said that with these two initiatives, within a five-year time frame, green hydrogen will reach cost parity with gray hydrogen.

Prashant Jain

executive
#47

There are two areas it will be focused on. This sector is going to develop in the same way you've watched renewable power develop, or the way you've watched electric cars develop. Six years ago, electric cars weren't economically viable. Now they are economically viable, and you can do commercial production and then sell them. The same holds for renewable power. It will happen in the same manner with green hydrogen. With mobility, it's going to take time, because you need to see the hydrogen going into the fuel cell, then the fuel cell generating electricity, and then that electricity running the car. Okay. Now technology is being developed so that the car is powered directly from the hydrogen, or the engine is powered. The real efficiency will be coming up, and for that, we believe some more time is going to be needed. However, for certain commercial applications as well as long-haul mobility applications, it will be 100% economically viable within a five-year time frame.

Pravin Maheshwari

analyst
#48

Right. So that means, in a sense, those two things are able to coexist, let's say, over the next five to seven years.

Prashant Jain

executive
#49

Green power and gray power will likely coexist for more than 10 years, maybe even 15 years. I don’t expect a full switchover to happen overnight. Even electric cars won’t fully replace IC engine cars over the next 10 or 15 years. Yes, penetration is speeding up a lot, because as soon as cost parity is reached, replacement or transition occurs very fast. For example, today our power demand rises 5% each year. The additional power that renewable sources will generate is happening only because cost parity has already been reached. Whether it comes from gray fossil fuel or from green power, it is the same, but renewable power’s tariff is lower, so doing that is cheaper. The only issue is if transmission cost is higher due to intermittency. That intermittency is also being addressed through new technological intervention, which you will see in the next one or two quarters and which we will discuss. That is also going to change the future globally and in India as well. We are taking certain decisive steps to address this intermittency and solve that issue for the grid.

Pravin Maheshwari

analyst
#50

Understood. The second point concerns the recent dollar issuance of roughly $700 million — I simply wanted to get a sense of the hedging expense and up to what level we're hedged. That's the first item. Just seeking clarity, given that more dollar-denominated loans may come in the future.

Pritesh Vinay

executive
#51

Yes, Swarnim, as you know, the bond carries a coupon of 4.125%. Its duration is 10 years. What we did was execute a call spread across the full 10-year tenor, covering the whole $707 million. This was structured as a 10 NC 5 bond, correct? That means it's callable after five years. What we've done is cover spot up to 80% over those first five years. Right? Beyond that, there's a range. So, since at the five-year mark there's an option for liability management, depending on where markets, levels, and spreads stand at that time. On an all-inclusive basis, the cost in INR terms comes to roughly 8%.

Pravin Maheshwari

analyst
#52

Alright.

Pritesh Vinay

executive
#53

There are two reasons for that, Pravin. The first has to do with the fact that those existing INR loans, all of which are tied to bank MCLR, are basically floating rate loans. Right? Considering where we stand with inflation picking up again, it's widely understood that rate curves ought to steepen from here on. Right? What we've basically done is this: by taking this step, first, there's a headline cost reduction, since the INR loan carried a rate above 8% and we've replaced it at the prevailing MCLR plus spread. Even more important is this — we've locked in that 8% for the coming 10 years, in an environment where rates are rising. That's the other benefit, one that can't really be quantified, so to speak.

Pravin Maheshwari

analyst
#54

Got it, sir. Thanks. I really appreciate the chance.

Operator

operator
#55

Thanks. Our following question comes from Abhinav Anand at Emkay Global. The line is yours — go ahead.

Abhinav Anand

analyst
#56

Yeah. Thanks for the chance to ask. On that coupon bond you've raised, would it be fair to assume that, for all the RE power you're going to bring in, the average cost would come out at roughly the same level?

Pritesh Vinay

executive
#57

Well, Abhinav, I wish I could give you a more definitive answer here, because at any given moment there are various components at play. Let me lay out the possibilities for you. For instance, this one was a BB+, so it wasn't investment grade. Now, depending on who your counterparties are — if SECI, say, or another sovereign entity is the counterparty, you could potentially get a 1-notch better rating, and that means a tighter coupon. Right? The unknown piece is where you think the 10-year U.S. Treasury will sit at the next moment when you're looking to tap the market. What the credit spreads will be, and what term premia will be outstanding at that time. There are too many moving parts, but clearly, with everything else held constant, given that our counterparties on this particular bond were non-sovereign entities, and it was therefore a BB+, the expectation is this: if we potentially tap future issuances for a renewable project, particularly with SECI as counterparties, those are likely to be investment-grade bonds, and the coupon there should be even tighter than this one. Everything else held constant. To put it in perspective, had it been a SECI bid like what we have done, and under the same conditions, it would have been anywhere between INR 3.5-INR 3.75 versus INR 4.125.

Abhinav Anand

analyst
#58

Alright. Then, second, I believe Prashant sir brought up the tariff increase, correct? He mentioned Basic Customs. Doesn't the Basic Customs Duty take effect starting 1st of April 2022?

Pritesh Vinay

executive
#59

Right.

Abhinav Anand

analyst
#60

On the current tariff — and please correct me if I've got this wrong — but the bigger worry, I'd say, is the tariff as it stands today, since solar module prices around the world have risen, driven by the way prices in China have climbed, correct?

Prashant Jain

executive
#61

It's both — you have to grasp the timing of when the bidding takes place. Once that PPA is signed and goes into effect, you're given 18 months to finish it. If any bidding is going on right now, then three months from now the PPA gets signed and you receive 18 months to complete it. At that point, the duty will apply.

Abhinav Anand

analyst
#62

All right, thank you. That covers the questions.

Operator

operator
#63

Thanks. Our following question comes from Apoorva Bahadur at Investec. The line is yours — go ahead.

Apoorva Bahadur

analyst
#64

Hello. Thanks a lot for giving me the chance to ask. Sir, early in the presentation, you mentioned that the board has given its approval to the reorganization of the green and grey power businesses. Could you shed some light on this — what timelines are expected, and what kind of outcome is likely there?

Prashant Jain

executive
#65

This involves splitting two business verticals apart, and various advisors will then review that separation. We expect the options to be finalized and brought to the board within the next 90 to 120 days. After the board gives its approval, the required steps will be taken, which means various stakeholder approvals, including lenders and shareholders, and we may need to approach the NCLT to carry out this reorganization or restructuring of the business. That will be step A. Step B will then come at the right point in time, when we need to decide whether any strategic investor is coming into the green power business, or any IPO of the green power business, or a demerger of green power and grey power. There are a number of options on the table, and we will be evaluating all of those options in due course of time. For that, we are first keeping the structure ready and all necessary approvals in place, and then accordingly all those options will be packaged.

Pritesh Vinay

executive
#66

Yes. Apoorva, let me add something there if I can. And beyond what Prashant said — you also asked which scenarios are likely, so here's the thing. It's a little early to say anything on that, because this evaluation — the board's approval is for evaluating different options for reorganizing and for going into the merits of each one, correct? What are the transaction costs? What sort of approvals, and so on? There's stamp duty, there are tax implications. There are compliances with the Companies Act, SEBI, LODR requirements, and so forth. A very holistic view has to be taken. What we have received approval for at this point is only to go ahead and begin working with advisors, and so on, to start evaluating the merits and demerits of the various options. Once that exercise is done, as Prashant said, we'll return to the board and present. That's the point at which the things Prashant was discussing will kick in. I just wanted to make that very clear. That said, from an intent standpoint, there is no ambiguity whatsoever, because as things stand today, if you look at our corporate structure, we have JSW Energy, and then we have Hydro as a separate 100% owned sub.

Pritesh Vinay

executive
#67

Future Energy is a 100% subsidiary, and at this point it's basically the vehicle for all the wind and solar initiatives. What's the most efficient way to house potentially all of them together, so that if an opportunity comes up to bring in a potential investor for all the exposure to the green assets, only one can have the flexibility to do that. That's the broad thought process. I just wanted to make it very clear that the approval now is to start evaluating various options and go into details of the merits of multiple options available.

Apoorva Bahadur

analyst
#68

Got it. Hydro assets will fit within power, correct?

Pritesh Vinay

executive
#69

To repeat, the reason I gave that earlier response was simply this: it is too early to get ahead of what will probably occur. The thinking is, what are the advantages and disadvantages of the various optionalities, and is that the path the board would wish to take? At this point, I would not want to take away the board's discretion by attempting to guess what will probably happen.

Apoorva Bahadur

analyst
#70

All right, absolutely. Appreciate that. I just have one additional question regarding the deal we have with FFI. I get that this is really a longer-horizon wager and we're all watching how the price of clean hydrogen trends. With luck it drops into the band where it turns viable. What kind of business model should we expect here for JSW Energy?

Pritesh Vinay

executive
#71

Apoorva, we couldn't hear you clearly. Would you mind asking that again?

Apoorva Bahadur

analyst
#72

Absolutely. I was inquiring about the arrangement we have in place with FFI. After green hydrogen costs reach a workable level, I wanted to get a sense of what kind of business model JSW Energy would be looking at in that situation?

Prashant Jain

executive
#73

Look, consider one thing: will it be economically viable from day one? The key question is whether you can match the price of grey hydrogen — if you can, then no additional grey hydrogen will be produced in the country going forward. That's how it works. You were generating renewable power, and it cost more than grey power or thermal power. Those projects became economically viable. The tariff at which PPAs were being signed was INR 6, INR 5. What I explained is that the government, both globally and in India, is introducing a green hydrogen purchase obligation, under which industry will be required to buy green hydrogen or green ammonia for various industrial applications. There will be economic viability from day one for whatever projects are being undertaken. Within a five to six year timeframe, green hydrogen's cost will reach parity with grey hydrogen. At that point, all incremental capacity will come from green hydrogen. That's what we mean.

Apoorva Bahadur

analyst
#74

Understood, sir. Our focus will be on either generating green hydrogen ourselves or providing the green power needed to generate green hydrogen.

Prashant Jain

executive
#75

Yes, it really is a mix of both.

Apoorva Bahadur

analyst
#76

And the electrolyzers will be operating too.

Prashant Jain

executive
#77

Yes, certainly.

Apoorva Bahadur

analyst
#78

All right, I understand—thanks very much.

Operator

operator
#79

Thanks. Our next question comes from Rahul Mody at ICICI Securities. Your line is open.

Rahul Mody

executive
#80

Thanks so much, sir, for all those thorough answers and for laying out some direction for us. I have just a couple of questions. Regarding bidding, whether SECI or non-SECI, when do you expect it? Over the past 4 to 6 months, we've noticed bids coming out somewhat slowly. When do you think this will really take off in a meaningful way? Naturally, all of us want that 20 gigawatt to begin getting tendered. What's your internal thinking on that, sir?

Prashant Jain

executive
#81

You're seeing quite a good number of bids out there. The issue is on the solar side — there's been a bit of sluggishness when it comes to converting those bids into PPAs. I think that's also going to ramp up over time, because what SECI is doing now is a very different structure. First, they sign in-principle PPAs with the respective DISCOMs, and then they come out with the bids. That's what's eliminating the risk of signing the PPAs. I believe you'll see a pickup going forward. It's going to be very rapid.

Rahul Mody

executive
#82

Okay, so what do you think about this recent Andhra situation? Andhra has been talking a lot about cutting costs when it comes to power purchase costs, but that has also come at the expense of backing down a lot of renewable power. Any views on that, sir? How do you see the business model for renewable energy going forward? Do you see us getting into a degeneration kind of situation? How would that work, in your view, sir?

Prashant Jain

executive
#83

From my perspective, every power purchase agreement carries sovereign obligation documents, and all adjudicating authorities in this country have upheld them. I don't see any risk at all in any power purchase agreement, regardless of the tariff at which it was signed. Certain DISCOMs have caused some hiccups previously, but ultimately the law of the land prevailed, and people are obtaining the requisite relief from the higher adjudicating authorities. That's what you sometimes confront as a challenge in a developing technology. For instance, when you build a technology, when a learning curve is occurring and costs are declining, then certain authorities adopt a different view. Given how the PPAs have been structured, they cannot be reneged. That's the first point. The second point is that going forward, there are another two, three things happening. Number three, the new agreements being done are being done by SECI, which is a part of the Ministry of Power. That's number 1. Which is changing the quality of PPA. That's number 1, which is happening. Number 2, there are 2 structural reforms in this country taking place and which are in the very advanced stage.

Prashant Jain

executive
#84

First, the smart metering idea—that's already in place. It isn't just a smart meter for tampering or theft. It's meant to implement a prepaid meter construct, and that will roll out across this country over the next three to five-year time frame. With that digital meter, power flow will stop automatically whenever your meter hasn't been charged through a simple mobile phone SMS. That's point number 1. Point number 2 is the other structural reform that the Government of India is now pushing. Whatever subsidy a state government announces for the DISCOM will go straight to the consumer. As soon as that happens, the DISCOM will have enough cash flow. These two reforms will change everything. You don't even need privatization if these two things are taken care of. The whole economics is going to shift over the next three to five-year time frame as well, in addition to the legal sanctity of the PPAs.

Rahul Mody

executive
#85

Understood, sir, and thanks a lot — that was a really, really useful reply. Many thanks indeed, sir. Wishing you all the best.

Operator

operator
#86

Thanks. We’ll take the next question from Sumit Kishore at Axis Capital. The line is yours — go ahead.

Sumit Kishore

analyst
#87

Good evening, Prashant. Thanks very much for the chance to ask. My first question is this: after quite a while, we've seen net debt go up at JSW. I think we're back on the CapEx path. Could you please give more detail on how much CapEx has been spent on the Kutehr project so far? How is the project progressing? When will it be commissioned?

Prashant Jain

executive
#88

Pritesh, would you like to-

Pritesh Vinay

executive
#89

Alright, I'll take that. Hi, Sumit — on the CapEx front, and just to keep things a bit light, I want to remind everyone listening that I recall my very first call after I stepped into this role back in October 2020. Prashant noted on that earnings call that we were at the tail end of the deleveraging cycle. Then the December quarter and the March quarter came and went — two more quarters — and we continued bringing net debt down. That's the lighter note. Yes, we're two quarters behind the curve and starting to deleverage. On the Kutehr project specifically, we've already spent more than INR 650 crores so far. Construction is fully underway. We've already committed approximately INR 1,800 crores when it comes to ordering, placing orders, and so forth. As we've guided the markets, our targeted COD is September 2024. We're actually pursuing internal targets to commission well ahead of that — at least at this point, September 2024 doesn't look to be at any risk at all. Construction on the project is moving along well. Over 30% of the tunneling work is already done. All the phases, all the sites are open.

Pritesh Vinay

executive
#90

Every one of the civil packages is now fully underway. The electromechanical packages have also gotten started. Yeah, that's on the Kutehr side, Sumit.

Sumit Kishore

analyst
#91

Okay, thank you, Subhadeep Mitra. A good chunk of that CapEx was really directed toward this project during the quarter too, wasn't it?

Pritesh Vinay

executive
#92

No. We've also been putting money into the renewable projects during the quarter. I'd say it may well be a combination of the two, since if we're telling you that construction is fully underway at the renewable sites too, we've already begun spending, particularly on the solar projects. From this quarter — in fact, the present quarter, the second quarter when we report — you'll begin to see a larger CapEx outflow, because, as we said in both the presentation and the release, for the solar panels, for instance, the ordering has already been completed. We have finalized orders for the wind turbine equipment. Over this quarter, we will in fact begin making advance payments as per the contract terms. Cash outflow will begin rising substantially from this quarter forward.

Sumit Kishore

analyst
#93

Sure. Actually, starting with next quarter, it would be helpful if you could begin providing the capital working progress figures for both hydro renewables, so we can get a clearer picture of how things are progressing. My second question: for the 958 MW group captive PPA that was signed, at what tariff was it signed, and who were the other bidders? What tariff did they bid at?

Pritesh Vinay

executive
#94

I don't know what the other bidders had bid the tariff. Dr. JSW Steel can answer you that. We have already disclosed our blended tariff for the entire 2.5GW Of capacity.

Sumit Kishore

analyst
#95

Apologies — could you tell me what the tariff is for 958 MW?

Pritesh Vinay

executive
#96

Regarding the blended tariff, which we've already disclosed, it's INR 3.30 — that's the blended tariff for 2.5 gigawatt.

Sumit Kishore

analyst
#97

Alright. For my third question, the SGD sunset happened yesterday, and it doesn't look like any new duty has been announced to take its place. How do you view this interim period ahead of the April 2022 Basic Customs Duty taking effect?

Pritesh Vinay

executive
#98

Like I said a moment ago, there are three models that every developer is going to be working from. For our part, with regard to the projects we're taking on, the panels are beginning. We'll be getting the panels, and the first shipment arrives during the first week of September. Whatever capacity we're building at 225 MW, all of the panels will be received ahead of December of this calendar year. So far as what's been announced up to now, there won't be any duty incidents. Should the Safeguard Duty continue or anything of that sort, our view is that it would apply to us. Moving forward, as I've laid out, there's a strategy that people are building around. Either they pay 40% duty and import the panel, or they import the cell and have the panels contract manufactured in India. They import the wafer and carry out cell and panel manufacturing on a contract basis. A lot of capacity is being built, and you can do contract manufacturing or you can do all three. Depending on each developer, there are a number of options through which those strategies will play out.

Sumit Kishore

analyst
#99

Okay. To go over that again, of the 2.5 GW currently being built, leaving out the hydro project, how would that split between wind and solar look at this point? Our view is that it shifts over time.

Pritesh Vinay

executive
#100

Out of that 2.5 GW, hydro accounts for 240 MW, solar makes up 225 MW, and everything else — nearly 2,000 MW — is wind.

Sumit Kishore

analyst
#101

Okay, so this is really my final question. I was at a session run by NITI Aayog, and they said that because coal-based power capacity in the country is so dominant — that and thermal capacity — the idea is to ramp up output of blue hydrogen, which is what they called it, and to make better use of the fixed investments before shifting straight over to the green hydrogen economy. Do you have any views on that?

Prashant Jain

executive
#102

I have no doubt this will unfold quicker than most people expect. The widespread assumption was that thermal generation capacity would continue to be built up in this country. The policy framework won't allow that. Given the RPO obligation, a DISCOM can't purchase power at INR 2 and sign a PPA even if it wants to. Their RPO obligation must rise — that's a requirement on them. The direction is unambiguous. Second, no capital is available, whether from lenders or from the capital market, to construct that kind of capacity. The direction is unambiguous. Whether and when someone accepts reality is a matter for each individual.

Sumit Kishore

analyst
#103

Sure. Thank you so much, and I wish all of you the very best.

Prashant Jain

executive
#104

Appreciate it.

Operator

operator
#105

Thanks. Women and gentlemen, because of time limits, that was our final question today. I’ll now pass the conference to Mr. Subhadeep Mitra for closing remarks.

Subhadeep Mitra

analyst
#106

Thanks. Speaking for JM Financial, we appreciate the chance to host this call. At this point I'd like to pass things over to Mr. Ashwin Bajaj for any closing remarks. Over to you, sir.

Ashwin Bajaj

executive
#107

Yes. Thank you, Pritesh, and thanks to all of you for being with us. If you have any additional questions, don't hesitate to reach out to us. Thank you.

Operator

operator
#108

Appreciate it. Speaking for JM Financial, that brings this conference to a close. Thanks for being with us, and you can go ahead and disconnect your lines at this point.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete JSW Energy Limited transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

This call discussed

For developers and AI pipelines

Programmatic access to JSW Energy Limited earnings transcripts and 132,000+ others is available through the EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research

OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in JSW Energy Limited or any ticker on your watchlist.

StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.