JSW Energy Limited (533148) Earnings Call Transcript & Summary
October 29, 2021
Earnings Call Speaker Segments
Operator
operatorGood day, ladies and gentlemen, and welcome to the JSW Energy Limited Q2 FY 2022 earnings conference call, hosted by DAM Capital Advisors Limited. As a reminder, all participant lines will be in listen-only mode, and following the presentation's conclusion there will be an opportunity for you to ask questions. If you need assistance during the conference call, please signal an operator by pressing star then zero on your touchtone phone. Please note that this conference is being recorded. I now hand the conference over to Mr. Mohit Kumar from DAM Capital Advisors Limited. Thank you, and over to you, sir.
Mohit Kumar
analystThanks, Faizan. Speaking for DAM Capital, I’d like to welcome everyone to JSW Energy’s Q2 FY 2022 earnings call. Joining us from management are Mr. Prashant Jain, Joint Managing Director and CEO; Mr. Pritesh Vinay, CFO; and Mr. Ashwin Bajaj, Group Head, Investor Relations. We’ll begin with some short opening remarks, and after that we’ll take questions. At this point I’ll pass the call to Ashwin. Please go ahead, sir.
Ashwin Bajaj
executiveYes. Appreciate it, Mohit, and thank you for hosting today's call. Good evening to all of you. I'm Ashwin Bajaj, and I'm glad to welcome all of you to our Q2 FY 2022 call. As Mohit mentioned, Prashant Jain and Pritesh Vinay are with us on this call. I'll pass it to Prashant for his opening remarks, and after that we'll take questions. Prashant, over to you.
Prashant Jain
executiveThanks, Ashwin. In quarter two, power demand rose 9.9%. Likewise, in quarter one we observed power demand higher by 16.4%. Across the whole of H1, power demand growth came in at 13%. For the first time, peak power demand reached 200 GW during July. Over the first 27 days of October this year, power demand is higher by 3.3% year-on-year. Looking at FY 2019, it is up 14.4%. We're witnessing a strong trend in power demand, and the day-ahead market in the merchant segment mirrors that as well. In the quarter, merchant volume for the country rose 22%, reaching 6,000 million units. At JSW Energy, overall net generation grew 2% in the quarter. Total thermal generation rose 4%, while hydro generation fell 1%. On long-term sales, the figure was flat at 6,200 million units, while short-term sales in the merchant market climbed 116% to 236 million units. The same pattern carried into October. Over the first 25 days, we were the biggest seller of power across the entire merchant market.
Prashant Jain
executiveFor the quarter, EBITDA rose 10% to INR 1,080 crores, driven mainly by higher short-term sales along with recoveries in late payment surcharges. Profit after tax came in at INR 339 crore, though on an adjusted basis PAT stands at four hundred and fourteen crore. PBT posted robust growth of 24%, reaching INR 604 crore. Receivables continued on a downward trajectory — 19% lower year-on-year and 7% lower quarter-on-quarter. Net debt also declined 1% during the quarter, to INR 6,500 crore, with a weighted average interest cost of 8.04%. Turning to the company's growth, all renewable projects are on track for 2.5 GW. At our Kutehr project, we have finished over 50% of tunneling for 10 km, ahead of schedule. Given the pace of construction, if everything comes true, it will be the fastest-ever project built in the country for any hydropower plant. As for the solar and wind plants, all equipment has already been ordered, and construction work is underway for our 225 MW solar power plant. Solar panels have already started arriving, and they are being installed at this point of time.
Prashant Jain
executiveCommissioning on that project gets underway beginning in Q4 of the current financial year. On the green hydrogen side, scoping efforts are already in motion — specifically around choosing the technology, engaging with OEMs, and working alongside the partners who will either source hydrogen for steelmaking or use ammonia directly. Our belief is that once this scoping exercise wraps up, the pilot project will be ready sooner rather than later. We've likewise begun taking tangible steps on intermittency solutions, which we covered during the last call. Consistent with that, and as part of building a sizable pipeline of intermittency solutions, the initial 1,500 MW hydro pumped storage project MoU was executed with the Government of Maharashtra. A number of other similar projects are under development too. JSW Energy is going to pursue lithium-ion battery storage solutions along with hydro pumped storage solutions so as to deliver an integrated answer for round-the-clock green power. In addition, the company has already brought on its legal advisor, tax advisor, and financial advisor for the reorganization of our gray and green energy business. Within a couple of weeks, we anticipate a final scheme being put in front of the board, and after the board gives its approval, implementation of that scheme will begin in order to unlock the value.
Prashant Jain
executiveHaving said that, I'd now like to begin the question-and-answer portion, and before I wrap up my comments, I want to take this chance to wish you and your family a very Happy Diwali in advance. Thank you.
Operator
operatorThank you so much. We'll now start the question-and-answer portion. Anybody who would like to pose a question can press star and one on their touchtone phone. Should you want to take yourself out of the question queue, you can press star and two. We ask participants to use handsets when asking a question. Ladies and gentlemen, we'll pause for a moment while the question queue assembles. A reminder to the participants, anyone who would like to pose a question can press star and one at this time. A reminder to the participants, anybody who would like to pose a question can press star and one. The first question comes from the line of Mohit Kumar from DAM Capital Advisors. Please go ahead.
Mohit Kumar
analystYes. Good evening, sir. So first, regarding the gray and green reorganization, what timelines are you considering? Once the board approves, what steps follow — you know, when would we as investors learn more about it? And a related question: this hydrogen initiative will sit within green. Which projects are you looking at over the next 12 to 24 months that you believe could be — you know, where you could actually begin some work?
Prashant Jain
executiveI'll take the second question, and I'll have Pritesh handle the first one. As part of the business reorganization, everything will fall under the total green business — whether that's renewable generation from hydro, solar, or wind, or intermittency solutions through lithium-ion battery storage or hydro pumped storage, along with the green hydrogen and green ammonia initiatives. The only gray power business will consist solely of the thermal business, which at present is Ratnagiri, Vijayanagar and Barmer. That's how the reorganization will take place. Any other future venture as well, one that relates either to generation or to any other specific initiative that is ESG compliant and green, will belong to the entire green vertical. Pritesh, would you like to
Pritesh Vinay
executiveYeah.
Prashant Jain
executiveOn the timelines, what's your answer?
Pritesh Vinay
executiveSure, Prashant. Mohit, if you step back for a moment and take a look at how our corporate structure stands today, we of course have the thermal business in the parent company. Then there's another wholly owned subsidiary — a Barmer entity, which is a thermal asset. We also have a separate JV, a transmission asset. Hydro sits as a 100% sub, and that sub in turn holds a sub for the Kutehr project. Then we currently have this entity called JSW Future Energy — previously named JSW Solar — which has essentially been the vehicle for all our wind and solar initiatives up to now, into this. When we shared this last time, the entire rationale behind the reorganization was to have a single vehicle, within, you know, just one step below JSW Energy, that would house all the green initiatives. As Prashant rightly clarified, that covers not only from a generation standpoint, but all the new energy initiatives, both on the storage side as well as on the hydrogen side. I wouldn't be able to preempt and give a specific answer to what you've asked. Typically, as is the norm with these kinds of things, the idea is to determine what will be the most efficient route from an income tax, stamp duty, Companies Act, other regulatory approvals, etc., standpoint, so that it gets done in the most efficient manner.
Pritesh Vinay
executiveUsually, some parts will involve a scheme of arrangement via an NCLT process and so on, you know. I can offer a very general answer, but as Prashant was mentioning, the advisors have already laid out options that the board has, you know, taken note of. Hopefully, in due course, you know, we ought to be able to return to the board with a complete proposal once we have made sure that all the i's are dotted and t's are crossed. After that, we will be making the required disclosures to the stock exchanges.
Mohit Kumar
analystSir, just to clarify one thing — for the Kutehr project, have you signed a PPA with Haryana?
Prashant Jain
executiveThat's still being finalized, Mohit. We're hoping to reach that line — the crossing line, you know — hopefully sooner rather than later. It comes down to procedure, not principle.
Mohit Kumar
analystGot it, sir. Sir, one more question regarding merchant capacity: with the new steel plant from JSW Steel up and running, as you know, do you expect that merchant capacity of ours to come down?
Prashant Jain
executiveAt this moment, 13% of total capacity remains available, and we're glad to have that 13% open as we speak. That said, yes, as a long-term strategy, whenever we identify opportunities to lock it up, we will certainly do so.
Mohit Kumar
analystGot it, sir — thank you, and wishing you the very best.
Prashant Jain
executiveThank you.
Operator
operatorThank you. For anyone who wants to ask something, you can hit star and one. Our next question comes from Apoorva Bahadur at Investec. Go ahead.
Apoorva Bahadur
analystYes. Hello, sir, and thanks a lot for giving me the chance to speak. So you mentioned the proposed separation of the gray and green businesses, with all the ESG compliant businesses staying in green. Now, should I take that to mean this will also open the door for us to move into gray businesses should the need arise — particularly, say, the Barmer expansion, which was kind of an unresolved matter?
Prashant Jain
executiveRight now, the strategy we've laid out is that we're focused solely on the renewable power business, and that's what we intend to keep. If at some point the two companies are separated and that umbilical cord gets cut, then at that moment I won't be in a position to comment on it.
Apoorva Bahadur
analystAlright, sir, that makes sense. And then, second, on this point — with the government permitting private coal mines to sell some coal to third parties, does that benefit us at all in Barmer, or is no sale possible from there?
Prashant Jain
executiveSure, that makes sense and it’s helpful. A sale is legally allowed at this point. We’re coordinating with the relevant government authorities to review that.
Apoorva Bahadur
analystWhat size would that be, assuming the sale goes ahead and when it does?
Prashant Jain
executiveRight now, 3 million tons of lignite is sellable under the environmental clearance. That's the opportunity. It depends on various approvals, and on whether the Government of Rajasthan agrees.
Apoorva Bahadur
analystAlright, one final question from me, and it concerns the battery storage side of things. Are any opportunities starting to take shape at this point? And are we taking part in any of the government tenders?
Prashant Jain
executiveThere's a big opportunity ahead that will take shape over time. At the moment, some tenders are in the process of, you know, being finalized, and they'll soon come into play. But as things stand right now, the costs are quite high, and these are going to be exploratory tenders. For meaningful capacities to actually arrive, though, at least two years will be needed. Along with that, we'll be seeing plenty of storage applications, but I see greater potential in hydro pumped storage than in battery storage solutions, given the shelf life as well as the environmentally friendly nature. Third is cost competitiveness. After a hydro pumped storage project gets built, its life spans 100 years, while a battery storage system's life is just six to seven years. A lithium unit only has a certain number of cycles available for charging and discharging, so for them the cost ends up high.
Apoorva Bahadur
analystAll right. So with that in mind, for the MoU we've signed with Maharashtra, what kind of timelines might we expect for a possible execution?
Prashant Jain
executiveThese projects are the ones that will get built for the grid. I mean, there will be quite sticky projects coming along. This particular project isn't for the Government of Maharashtra. We've signed a MoU for allocation of the project. We're now taking environment clearances, and various land acquisition has been started. Over a period of time, these kinds of projects will see the light of day. Because once large capacity of renewable capacity is coming up, then the intermittency solution needs to be solved.
Apoorva Bahadur
analystThat seems logical. Would the capital cost be comparable to what a standard hydro project would run?
Prashant Jain
executiveNope.
Apoorva Bahadur
analystReduced.
Prashant Jain
executivePossibly 20%-25% of that.
Apoorva Bahadur
analystRight, okay. Thanks very much, sir.
Operator
operatorThanks. Just a quick reminder for everyone: if you'd like to ask something, hit star and one. Our next question comes from Sumit Kishore at Axis Capital. Please go ahead.
Sumit Kishore
analystGood evening, and thank you for the chance to ask. My first question concerns JSW Energy's leading position as a seller in the merchant market. What share of your power is sold on the exchanges, and what portion goes through bilateral contracts?
Prashant Jain
executiveWe've been moving a big volume, you know. Take last quarter — if you look, the total merchant market came to 6,000 million units, and we sold close to 235 million to 236 million units. That was only 4% of the total size. In October, we sold more volume than we did during the entire last quarter. On the individual IPP side, we were the largest.
Sumit Kishore
analystAll right. That part was about exchanges, right? I just want to make sure I understand.
Prashant Jain
executiveEverything went through the exchanges — 100%. All of it was sold on exchange. When the market is strong and lively, we move 100% of what we can produce, and at times our facilities even operate at 104% or 105% of capacity as well.
Sumit Kishore
analystMm-hmm.
Prashant Jain
executiveOctober was a solid month for us.
Sumit Kishore
analystSo with long-duration contracts probably coming to exchanges shortly — the regulator has cleared the path — do you figure the bilateral market is basically behind you at this point, since LDC would offer an option on the exchanges for, say, a few months up to a year?
Prashant Jain
executiveI don't believe that going forward you're going to see just the merchant market. Once all this capacity has crystallized over a period of time, India will have only a long-term market. I completely disagree with some of the theories being floated around that the PPAs will be permanently finished and that it will be only a merchant market after that. I think all of this happened because of certain overcapacity that came up with no PPAs during the 2005 to 2008 timeframe, when people conceptualized projects based on the merchant market. A lot of funding happened for those projects, and people came up with those projects. Now, over a period of time, those projects have been tied up, and now the balance of some of the capacity will get tied up, whichever is pending, because most of the projects that were under construction, they died down and they are sitting in NCLT as a bad debt at this point of time. Some of the projects that are operating, their capacities are getting tied up. Like if you look at JSW Energy, it was having 55% tied up capacity and 45% was merchant. Today we are only 13% merchant, and we will also tie up.
Prashant Jain
executiveFor the past 5 years, nothing has been constructed on the merchant side, and at this moment no one is constructing it either. After all this capacity is completed and locked into contracts, at that point a merchant market will no longer exist in this country. Only the long-term market will remain. Who would build a merchant-market power plant for 25 years, put money in today, and then sit around waiting for a merchant to make a decision? No lender provides funding, and no individual contributes equity. That whole idea is a myth that certain people are putting out.
Sumit Kishore
analystIn your view, the short-term market's share—which makes up 11%-12% of the total market—will continue to sit within that range. You know—
Prashant Jain
executiveThat'll get locked in too. Every bit of it, since if you have the option, any seller out there would rather commit his capacity when a long-term buyer is available. All of these players are going to lock things in. Take a look at where we stand. The Government of India ran the Pilot Scheme auction 2 years back. At INR 3.25, nobody came forward. Every PPA got signed after this October crisis hit. Once the shortage arrived, just look at the situation. In this country, only 10 GW of capacity has been added each year — the renewable kind — which works out to 2 GW. Real power demand has been rising 9 to 10 GW. Across the last 5 to 7 years timeframe, something like 35,000 to 40,000 of overcapacity got absorbed. That was capacity sitting around in the merchant market. Now, with this sort of economic recovery showing up, first off, all that open capacity is going to be taken up. They'll secure the coal linkages, they'll secure coal through commercial mining or from the mines that will supply coal from captive mines, which the Government of India has permitted. On that basis, people are going to try to lock in that capacity.
Prashant Jain
executiveAs soon as that capacity gets locked up, the merchant market is going to dry up, and you won't see any new investment coming in on the merchant side. That's really the whole point.
Sumit Kishore
analystSo why haven't we seen 25-year long-term PPAs or auctions taking place to soak up that capacity already, over these last couple of years as well? We really haven't heard of a single 25-year PPA being signed.
Prashant Jain
executiveI apologize — the connection isn't clear on my end. I wasn't able to catch what you said.
Pritesh Vinay
executiveSumit, we're getting a lot of echo. I'm not sure whether you're on speakerphone. Would you mind using the handset instead, so we can hear you clearly? Thanks.
Sumit Kishore
analystHas it improved at this point?
Prashant Jain
executiveCorrect.
Sumit Kishore
analystApologies for that. What I was saying is that over the last 12 months, we haven't yet seen any states request 25-year PPAs. Are you essentially suggesting that within the next 12 to 24 months, multiple states will come out with a requirement for 25-year PPAs?
Prashant Jain
executiveLook, as soon as those shortages begin to appear, folks are going to enroll in it. My view is that what took place in October is only the very beginning of the shortages we'll see. That's because nothing has been invested in the power sector.
Sumit Kishore
analystGot it.
Prashant Jain
executiveThe issue isn't the coal shortage we've been seeing. It's the load that has come onto the thermal power plant. Look, we have 100 GW of renewable capacity operating at 19% CF nationwide, which means you're talking about 19 GW of actual supply being delivered by renewable power. 45 GW of hydropower running at 49 to 50% PLF gives you another 21 to 22 GW. Effectively, out of 225 GW of thermal power plant, approximately 45 GW is out of function due to gas non-availability, as well as those thermal plants with the state government that don't have enough coal. Where will the 200 GW of peak power demand be met from? Now the coal crisis happened because demand really picked up and coal prices in the import market rose substantially. The plants that depended on imported coal stopped operations because importing coal at INR 8 a unit of power and supplying it to the market wasn't viable for them. That's why some of the power plants stopped. Once they stopped, on one side generation was going down, and on the other side domestic coal requirement was going up.
Prashant Jain
executiveThird, there's 65 to 70 GW of captive power that industry generates using imported coal. The big refineries, the large steel plants, the cement plants—they bring in coal from abroad. They began moving to domestic coal. More and more strain landed on domestic coal. Coal India has been raising output this year versus last year. The strain fell on Coal India since the captive players and the importers, all of them shifted there. The real issue is that capacity isn't sufficient.
Sumit Kishore
analystUnderstood. Now turning to the quarterly results, there are just two questions. On the roughly INR 150 crores in the September quarter, could you perhaps break down this other income a bit — how much of it is treasury income? And what is the total liquid cash balance, including liquid investments, on the balance sheet? The second one is about tax. The tax rate appears elevated, and is there anything we should take note of?
Prashant Jain
executiveI’ll have Pritesh take that one.
Pritesh Vinay
executiveYeah, Sumit, apologies — we lost you briefly while you were asking the first part of your question. I caught the other two parts: one about other income and one about the tax rate. What was the first part?
Sumit Kishore
analystHow much do we have in cash, cash equivalents, and liquid investments on the balance sheet, and what makes up that other income? Does it all come from treasury?
Pritesh Vinay
executiveOkay, got it. So the cash balance at the close of the quarter stood at roughly INR 1,777 crore, correct? That figure also appears in the presentation. On the tax rate, you're right that it looks elevated. Here's how to think about it: two things are going on. First, the hydro business is naturally seasonal—earnings come in heavier during the first half due to the season and hydrology, then reverse in the second half. What happened in hydro is that, as you may remember from our Q1 disclosures, we completed a $700 million US bond issue in May. When those proceeds arrived, we used them to prepay the rupee term loans that were outstanding, and one-time charges had to be recorded for the prepayment costs as well as for absorbing the unamortized cost of that loan. That came to roughly INR 92 crores and hit in Q1. Because of this, the effective tax rate at the hydro entity is rising, since Karcham already falls under 80IA.
Pritesh Vinay
executiveYou know, one thing was that a tax shield couldn't be obtained because of this provision that was made, or the one-time hit taken, in hydro's books. That's going to normalize over the course of the year. If I were to kind of help you think through this, at the end of the day, what should the effective tax rate look like on a consolidated basis? Here's what's going to happen: if you look at the last few years, on average on a consolidated basis, our effective tax rate sits in the ballpark of about 25%, plus or minus something in any given year. We should largely be in that range for the whole year as well.
Sumit Kishore
analystAlright. Alright.
Pritesh Vinay
executiveHopefully that clears up the tax piece for you. As for the other part of what you asked, that's about what makes up the other income, correct?
Sumit Kishore
analystYes.
Pritesh Vinay
executiveSo within other income, there are basically two material pieces. The first one: we won that case in the Supreme Court involving the LPS charge at MSEDCL, and because of that, INR 57 crore of income has been booked from it. This is essentially an old case that centered on the rate at which LPS has to be paid, where MSEDCL and what the PPA said differed in view. We had already won at the appellate stage, but MSEDCL then appealed to the Supreme Court, and the Supreme Court has ruled on it. That's one. The second piece is that dividend income from JSW Steel came in higher this time, owing to the shares we hold in JSW Steel. Out of that, roughly INR 89 crore is accounted for within other income from this. Those are the two biggest ones. Yeah.
Sumit Kishore
analystAlright, so most of that INR 150 crores in other income comes down to those 2 items.
Pritesh Vinay
executiveFor the most part, that's right. Since when you mention 150, my guess is you mean the half year, correct?
Sumit Kishore
analystNope — for the September quarter, that figure stands at INR 1,499.
Pritesh Vinay
executiveThat's correct. You've got it right.
Sumit Kishore
analystYeah. Exactly. Thank you so much. Thanks for taking my question.
Pritesh Vinay
executiveRight.
Operator
operatorThanks. A quick reminder for everyone: if you'd like to ask a question, just press star and one. Our next question comes from Subhadip Mitra at JM Financial. Please go ahead.
Subhadip Mitra
analystGood evening, and thanks for having me. My first question concerns the domestic coal supply crisis we've been seeing — and at least the latest data appears to indicate that coal supply is finally falling into place while demand is leveling off. Plant coal stockpiling is probably beginning to occur. From where you sit, do you believe we've turned the corner and that this coal supply crisis might gradually ease from here?
Prashant Jain
executiveNo, that's not it at all. This isn’t a coal crisis — it’s exactly what I just described. What we’re looking at is a power capacity crisis.
Subhadip Mitra
analystGot it.
Prashant Jain
executiveFirst, demand has eased due to the festival season. Second, a lot of import-based power plants came online because certain states agreed to purchase power from those plants at a higher tariff, so they began with higher fuel costs. They then started boosting supply. That is the main reason. Those two factors are the main reasons behind the moderation you have observed. Once demand begins rising again, more and more capacity will be needed. Look, even right now, as in this year as well, you are seeing what kind of capacity. You will ultimately see 10 GW of renewable capacity, effectively 2.5 GW. Power demand has risen by 10,000 MW. Every year power demand grows — where will the capacity come from?
Subhadip Mitra
analystThat point is accepted.
Prashant Jain
executiveCoal isn’t the issue here.
Subhadip Mitra
analystThe problem there is really on the demand side rather than with coal itself. That's what you're getting at, correct?
Prashant Jain
executiveThe problem isn't coal. It's capacity.
Subhadip Mitra
analystRight, that's a fair point. And second, on the path of international coal prices — do you have any sense of whether you see that flattening out going forward?
Prashant Jain
executiveThermal coal prices have begun to decline already. As of October 15, the API4 index stood at $280. At present, it sits at $140. That is a drop of just 50% over the last 14 days, and thermal coal prices are falling.
Subhadip Mitra
analystThere's one more thing — we've also observed a power crisis over in China. Based on what we read, at least in the international media, that's going to have a cascading effect when it comes to module supplies, and you know, module production as well as costs. I just wanted to get your take on how you see module pricing and supply playing out?
Prashant Jain
executiveHonestly, it's a really difficult call for me to say what the trajectory will be, and what's actually happened is that over the last six months, seven months, module prices have risen from $0.18 to $0.29 as we speak. That's exactly where we've consistently been extremely worried about the sort of predatory competitive bidding that certain players have been resorting to, placing bids at INR 2, INR 2.40 simply to fill the book, and those bids are not sustainable at all. That's exactly the issue — the bid takes place, yet the projects don't get executed. That's where the shortage is arising across the board. Ultimately, the Government of India has taken the initiative to build large capacity within the country, and then, under the new PLI scheme, close to 10 GW of new polysilicon through to module capacity will be built up. I believe that 10 GW of capacity will be up and running within the next 24 to 36 months. After that, we will see a great deal of stabilization, because India can produce very low-cost thermal power at the pithead, and with that power, low-cost polysilicon can be produced, and then we will be out of this problem.
Prashant Jain
executiveMy view is that this 10 GW capacity will rise to between 30 and 40 GW, and that is the amount of capacity we require. A few of the big players are each independently looking at 10 GW on their own. With this initial PLI scheme, I think the direction has, you know, been set. Over the coming three to four years, we will have substantial capacity within the country. Until then, we will simply have to live with this price variation, which will be resolved in due course.
Subhadip Mitra
analystThanks. That was genuinely useful. And finally, as you mentioned earlier, the present situation — let's call it a crisis — on the power supply side, along with the way merchant prices have been climbing, ought to push DISCOMs toward returning to the medium-term or long-term PPA market. When you talk with the various DISCOMs, are you seeing any steps by them when it comes to planning their medium-term or long-term power?
Prashant Jain
executiveMy sense is that PPAs will begin to be signed for whatever capacity remains uncommitted. On the thermal side, no additional incremental capacity is going to come. Incremental capacity is going to arrive solely from renewables. That is entirely tied to PPAs. No new project gets built absent a PPA. Funding won't even come together. What exists is only the current open capacity, and that will definitely be locked up within a couple of years.
Subhadip Mitra
analystGot it — thanks for taking my question. That was very helpful.
Operator
operatorThanks. We’ll take the next question from Anuj Upadhyay at HDFC Securities. Go ahead, please.
Anuj Upadhyay
analystThanks for giving me the chance, sir. I apologize if this has come up already — I joined a little late. I'd just like to ask whether we took part in the price increase that happened recently in the spot market, that rally we saw beginning in the last week of September and running through the middle of October, and whether we gained from it. And how are things actually shaping up at present? Do we have — I mean, international coal prices remain viable. We imported and sold in the current market on this front. Second, could you please expand a bit on the MoU we signed with the Government of Maharashtra covering 5 GW of wind and 1.5 GW of hydro pumped storage?
Prashant Jain
executiveWe had solid coal inventory at a very low cost. We were able to benefit from that, you know, the favorable conditions during September and October. At the moment demand is subdued, but after the festival, I think demand will rise again. Plants powered by imported fuel are the ideal place to take advantage of the merchant market, since that is where supply-side constraints are at a minimum. As imported fuel prices moderate, that is even more helpful for a company like JSW Energy. Regarding the MoU, what we have signed, as we have been explaining, is about securing resources — specific locations where we would like to build power projects over time, because in India the hardest part is acquiring land and obtaining the right of way and connectivity, and that is what we have been building. So we have been doing this across various states — Rajasthan, Tamil Nadu, Karnataka. Now we have done a similar thing in Maharashtra as well. The pumped storage project is the allocation of a particular site that we have identified, and there we will be building 1,500 MW of hydro pumped storage.
Prashant Jain
executiveAt the moment, we've begun work on things like environmental clearance and land acquisition, so to speak. Over time, we'll construct this project, and the output will go to SECI to address the grid's intermittency issues. For instance, just now you're seeing a fresh RFQ floated for a storage solution amounting to 4,000 MWh. In that manner, grid-based solutions will keep emerging, where the grid supplies power during certain off-peak hours and draws power at peak hours. That is how stabilization of the grid will happen. Round-the-clock solutions will be coming. The reason is that grid-based solutions make economic sense. A solution at the individual project level does not make economic sense. That's the approach behind how we are building these kinds of projects.
Anuj Upadhyay
analystUnderstood, sir. Do you have any perspective on how long execution might take, or on the tariff angle for these two items?
Prashant Jain
executiveSure, it’s going to take time. As bids come in, you’ll see that we’re able to take part. Because once the resources are in hand, you can move very fast. Execution itself is not what takes time. What really consumes time is securing the resource, securing the land, securing the connectivity, and securing the clearances. That is what takes longer. Execution takes no time at all. Bids continue to arrive. First you win the bid, and then you begin looking for the assets, the connectivity, and the land acquisition, and after that we do not build the project — which is the difference between most companies and us. We began building the projects right after we secured the bid. Now it is moving into commissioning. The turnaround time is a few months.
Anuj Upadhyay
analystUnderstood. Thank you, sir. That was actually what I was going to ask as well.
Operator
operatorThanks. Our final question comes from Sandeep at Edelweiss. The line is yours — go ahead.
Sandeep Agarwal
analystHi there, sir — Sandeep here. Thanks for giving me the chance. I have two sets of questions. First, regarding our 600 MW of merchant capacity, my understanding is that we've deliberately left it open so we can benefit from merchant prices. The merchant prices have been volatile, I realize, but in your view, what's the probable trajectory here over the next, say, six months to one year? Will it land somewhere in the INR 3 to 6 range? How do you see it? That's my first question.
Prashant Jain
executiveI can't really tell you what the prices are going to be, but what I can say is that the power shortage is going to be with us for a couple of quarters. Ultimately, prices are a function of demand and supply, and my view is that not enough investment has happened in the power sector over the last couple of years, and because of that, we're going to see the power shortage going forward, and that will feed straight through into merchant prices.
Sandeep Agarwal
analystIn the end, that's going to result in the PPAs being signed again. That's how it should be interpreted, correct?
Prashant Jain
executiveThat's possible. I mean, when was the last time you saw a situation where, even with a PPA at X price in place, a DISCOM agreed to purchase at a significantly higher price from a company they hold a PPA with? Provided a special approval was granted. Does that ever occur?
Sandeep Agarwal
analystYes, that's correct. I accept your point. You know, they had that sort of obligation. That's what they stated. That was another matter. Sir, my second question is, you know, do you actually anticipate a peak deficit that currently stands at only about 0.5% or 1%? Do you anticipate that we are returning to 2011 times, when the peak deficit was roughly 10% to 11%? Because, you know, with India being an evening peak country, you know, renewables have a limited role to play there. And thermal, since we are not investing, you will see that in 2023, 2024, you will hit that peak deficit.
Prashant Jain
executiveI'm quite convinced we're going to witness that power shortage, since we haven't invested enough.
Sandeep Agarwal
analystAlright. So at this point, essentially.
Prashant Jain
executiveThat's exactly the point I'm making as well — the deficit is going to grow. When a shortage exists, you'll see the deficit rise. Those two things are just opposite sides of the same coin.
Sandeep Agarwal
analystRight, absolutely, I'm with you there. What I was getting at is when should we expect that to show up? Do you think we'd be able to see it in FY 2022 to 2023? When would that likely begin to have an impact?
Prashant Jain
executiveNo, I think we're already starting to see that.
Sandeep Agarwal
analystAlright.
Prashant Jain
executiveWe’ll keep watching, since, you know, apart from renewables, where is that investment actually going? How fast is the investment moving? 10 GW, which works out to 2,000 MW annually. Demand is rising by 10,000 MW each year.
Sandeep Agarwal
analystOkay.
Prashant Jain
executiveYou know, if you look at the plot from 2010 to 2020, you can see how much capacity we've added and how much demand has gone up. But that's not about installed capacity — we need to look at generation capability. If over the last 10 years we've built 100,000 MW of renewable capacity, over those same 10 years, that's equivalent to just 19 GW. We keep talking about capacity increases, but we're not looking at the actual ability to generate — how many million units. Meanwhile, demand is rising much faster. Over the last 7 to 8 years, close to 45,000 MW of overcapacity has been absorbed. Since 2013 onward, we've been a power surplus country when it comes to capacity, and that's exactly where you've seen this kind of NPA problem, along with the subdued merchant market and all of that. All this overcapacity has been absorbed over the last 6 years, 7 years. So now, to get past this, you need to set up at least 35,000 MW of renewable capacity every year. You're meeting the incremental demand. You'll keep having the kind of scenario you're having now. If you don't build that kind of capacity, then you'll face a shortage.
Sandeep Agarwal
analystRight. Right. Understood, sir. Many thanks.
Prashant Jain
executiveI appreciate that.
Operator
operatorThanks. That was the final question for today, ladies and gentlemen. At this point I'd like to pass the conference back to management for their closing remarks. Thank you.
Prashant Jain
executiveYeah. Thanks to all of you for being with us tonight, ladies and gentlemen, and please don’t hesitate to get in touch with us if you have any additional questions. Thanks once more.
Operator
operatorThanks. Everyone, that wraps up this call on behalf of DAM Capital Advisors Limited. We appreciate your participation, and you're free to hang up now.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete JSW Energy Limited transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →This call discussed
For developers and AI pipelines
Programmatic access to JSW Energy Limited earnings transcripts and 132,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in JSW Energy Limited or any ticker on your watchlist.
StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.