JSW Energy Limited (533148) Earnings Call Transcript & Summary

January 19, 2022

BSE Limited IN Utilities Independent Power and Renewable Electricity Producers earnings 56 min

Earnings Call Speaker Segments

Operator

operator
#1

Good day, everyone, and welcome to the Q3 FY 2022 post-results conference call for JSW Energy Limited, which ICICI Securities is hosting. Just a reminder that every participant line will stay in listen-only mode, and once the presentation wraps up, you'll have a chance to ask questions. If you require help at any point during this call, please signal an operator by pressing star and then zero on your touchtone phone. Kindly be aware that this conference is being recorded. I'll now turn the conference over to Mr. Rahul Modi. Thank you, and the floor is yours, sir.

Rahul Modi

analyst
#2

Thank you, Aman. Speaking for ICICI Securities, I’d like to welcome everyone to this call covering JSW Energy’s Q3 FY 2022 results. Senior management from the company is with us here today. JSW Energy has kicked off the calendar year by posting a really strong set of results — congratulations to the whole team on that. I’ll now pass things to Mr. Ashwin Bajaj, Group Head, Investor Relations, who will introduce the management team and get the call going. So I’d like to hand it over to Ashwin now. Thank you. The floor is yours, sir. Best wishes.

Ashwin Bajaj

executive
#3

Thanks a lot, Rahul, and I appreciate you hosting the call. Good evening, everyone. I'm glad to have you join us for JSW Energy's Q3 FY 2022 results call, along with an update on the growth strategy we're leading with renewables. Joining us today are Prashant Jain, our CEO, and Pritesh Vinay, our CFO. Mr. Jain will begin with opening remarks, and after that we'll open the floor to Q&A. With that, I'll hand things over to you, Mr. Jain.

Prashant Jain

executive
#4

Thank you, Ashwin, and let me start by wishing all of you a very happy new year. Power demand rose 3.4% in the quarter, and across the first nine months it climbed 9.6%. Within that, generation during the first nine months rose 10.8% on the thermal side. Hydro stayed roughly flat, while renewable output grew 14.4% — clear evidence that renewable capacity is meeting a growing share of overall growth, something also visible in capacity additions, which I'll touch on shortly. As of 31st December 2021, at the close of the quarter, installed capacity totaled 393 GW. Net capacity added during the first nine months came to 11 GW, with 491 MW of that net addition in thermal. Everything else was in renewables, which shows how incremental demand is being served by renewable energy. Average merchant tariff for the quarter stood at INR 4.89, and for the first nine months at INR 4.07. In the same quarter last year those figures were INR 2.76, and INR 2.58 for last year's first nine months. We delivered a strong showing on hydro generation, which increased 13%.

Prashant Jain

executive
#5

All right, on total net generation, we saw a 3% decline, and the main reason for that is our 300 MW unit at Ratnagiri, which has been under maintenance from the first of September through today. We expect it to begin generating by the end of February. If you set that aside, generation has been really strong across every business vertical — thermal, hydro, all of them. We've also seen very healthy short-term sales. Thanks to lower raw material costs, higher short-term sales, and improved operational performance — specifically lower auxiliary power consumption and better heat rates — our EBITDA for quarter three came in at INR 882 crores, the highest Q3 EBITDA we've posted in the last five years. We've seen much the same pattern in profit after tax. Over the first nine months, we recorded net profit of more than INR 860 crores, which exceeds what we recorded for the entire prior year at INR 790 crores. We expect this performance to carry on going forward. Receivables fell 20%, landing at INR 1,356 crores, a 20% drop from INR 1,700 crore a year ago. As a result, net debt has declined to INR 6,000 crore, the lowest it has ever been. During the quarter, we brought net debt down by INR 500 crore. Our interest cost has fallen to its lowest weighted average, 7.82%, versus 8.24% in the same period last year and 8.04% in the prior quarter of the current year.

Prashant Jain

executive
#6

What all of this means is that our net debt to EBITDA has been dropping steeply — it's the lowest in the industry and also the lowest the company has seen, at 1.74x. On the projects side, our growth has been beating what we expected, as we talked about last time. The company has taken on 2.5 GW of projects that are under construction, with a capital outlay of INR 15,600 crore. Commissioning of the first project, 225 MW, happens in the current quarter. Starting with quarter one next year, commissioning will keep occurring every year. That shows what this company can execute. Among the SECI 9 and SECI 10 grids, we are the only company moving into commissioning, while others are still signing PPAs and dealing with various other formalities. For next year we expect capacity commissioning of between 1 and 1.3 GW, and that means capital expenditure above INR 8,000 crore-INR 10,000 crore next year and each year after. Another notable point: even though the company has been in CapEx mode for the last 3Q-4Q with a capital outlay of INR 15,000 crore, and we will be commissioning the first project in the current quarter, our net debt has been declining.

Prashant Jain

executive
#7

What this addresses is how uniquely positioned the company is in managing cash flow and the different instruments that have been put to use. As a result, the debt drawdown occurs when the project is commissioned, and that lowers the IDC while also enhancing the company's credit rating and profile. On the reorganization of the business, we have already made a filing before NCLT, in which the amalgamation for the merger of JSW Future Energy and JSW Neo Energy has been submitted. It is proceeding along the lines we expected. We anticipate that this exercise should be finished within a timeframe of the next six to nine months. Our hydro project is likewise progressing better than we had expected. Tunneling is already 60% complete. At the pace this project is moving, it will be the fastest hydro project ever built in this country. Even with COVID's 3 waves, with the various lockdowns and COVID restrictions, despite all of that, this will be the fastest project ever built in the country. With that, I am happy to hand the floor over for questions and answers. Thank you very much.

Operator

operator
#8

Thanks a lot. Ladies and gentlemen, we're now starting the question and answer portion. If you'd like to pose a question, you can press star and one on your touchtone phone. Should you want to take yourself out of the question queue, just press star and two. We ask that participants use handsets when asking a question. Ladies and gentlemen, we'll pause briefly while the question queue is put together. Our first question comes from the line of Vishal Biraia from Max Life Insurance. Please go ahead.

Vishal Biraia

analyst
#9

Hi there, thanks. Regarding the capital expenditure you've already incurred — roughly INR 1,600 crores — on the 2,500 MW currently being built: a few of those projects will begin commissioning from March onward. Why is that CapEx figure on the lower side? First, if you could split out this CapEx for us — how much has gone into the SECI projects, how much into the captive projects, and how much into Kutehr — that would be helpful. Thank you.

Prashant Jain

executive
#10

Pritesh, could you go ahead and answer that?

Pritesh Vinay

executive
#11

Vishal Biraia, thanks for that question. Look, there's CapEx spent and there's CapEx cash outflow, correct? When we show a spend of INR 1,640 crore in the presentation, that represents the cash already spent. Of course, that isn't the entire expense incurred, right? On top of that, we have commitments of roughly INR 5,200 crore. All told, if I look at the commitments we've made, right, they come to nearly INR 7,000 crore, which works out to more than 40% — 42%-43% — of the INR 16,000 crore total pipeline. Because obviously, the idea here is this: how do we. The point Prashant was also making earlier, you know, is that you don't spend everything upfront. Take solar panels, for instance: when we place the orders, we have to open an LC, which is a non-fund-based exposure, right? That doesn't involve any upfront cash outgo, right? You know, we'll be commissioning that particular project during this quarter itself, and revenues will start flowing from next quarter onwards. Once the LC is, you know, becoming due, there'll be an opportunity to look at, you know, taking an usance, another leg of usance and getting an additional 180-day credit period and all that before the actual drawdown of the term loan debt happens.

Pritesh Vinay

executive
#12

Since that generates a bit of interest rate arbitrage, right? The thinking here is this—and it's the same point Prashant was raising—that when you look at it from the standpoint of executing projects and managing them, we're also sort of, you know, putting in place the approaches that will be more efficient for, you know, trimming the costs and making sure the returns pick up some kind of kicker, one way or another, you know. That's the way we're approaching it. As for the split you asked about—I believe that was the second part of your question—if I look at, you know, the CapEx we've incurred over the nine-month period, what we've actually incurred comes to roughly INR 1,150 crores. Within that, on Kutehr by itself, we'd have spent approximately INR 300 crore. On SECI, taking projects 9 and 10 together, we'd have spent around INR 450 crore. On the group captive, which is 958 MW, we'd have spent approximately INR 320 crore, and the remainder would be for the routine CapEx we're carrying out at the plants already in operation. Yeah. That's roughly how it breaks down.

Vishal Biraia

analyst
#13

Alright. The next question is about where things stand with the pumped hydro storage projects.

Prashant Jain

executive
#14

Sorry, what was that update?

Vishal Biraia

analyst
#15

Uh, pumped—

Prashant Jain

executive
#16

I'll address that question. Regarding our pumped hydro storage projects, water allocation has already been secured for two of them. The first is located in Maharashtra, with a capacity of 1.5 GW, and the second is in Rajasthan, at 1 GW. Applications for environmental and forest clearances have already been submitted, and the techno-economic feasibility report is currently being prepared. After the techno-economic feasibility reports are completed, they will be submitted to CEA, and following that, we will begin construction on the projects. Across several other states—Karnataka, Andhra Pradesh, Telangana, Orissa, and Chhattisgarh—there are numerous additional projects adding up to 10 GW, which are at an advanced stage of allocation and various approvals. We expect that construction on the first project will begin around the end of the next financial year or in early FY 2023 to 24.

Vishal Biraia

analyst
#17

All right, then — for this specific project you're talking about, what would the CapEx come to?

Pritesh Vinay

executive
#18

Costs are going to vary from one project to the next. The range runs from INR 2.5 crore to INR 3.5 crore, or as much as INR 3.75 crore for each MW. These projects usually involve a six-hour peaking cycle that we design, and that works out to roughly 25% PLF. So you can picture that the efficiency will be greater than — you know — two times as much. Normally, when you put up a hydropower project at INR 12 crore a megawatt, you get 50%-55% PLF. With this, your cost will be 25% of that project — or under 25% — while delivering half the PLF. On efficiency, these will be twice as efficient — better than double.

Vishal Biraia

analyst
#19

Thanks a lot. I believe that wraps things up. Thank you.

Operator

operator
#20

Thanks. We'll take the next question from Apoorva Bahadur at Investec. Your line is open.

Apoorva Bahadur

analyst
#21

Thank you very much for the chance to speak, sir, and congratulations on the strong numbers. Once more, a follow-up on these pumped hydro projects: will PPAs be signed for them, or are they intended for green hydrogen production, considering that around-the-clock power will be needed?

Prashant Jain

executive
#22

There are plenty of opportunities and options we're currently pursuing. From what we're seeing, the likely path is that in place of PPAs we'll also have a range of services we can offer. To give you an example, take me sitting in my BKC office — as a building, we're hooked up to a specific DISCOM that supplies the electricity. But the reason I draw power from a DISCOM is that I only need it from 8:00 A.M. to 6:00 P.M., and only on five days a week. When I'm not drawing, I'm not paying. That's why I'm willing to pay an average tariff of INR 12. Now, as a renewable power company, I can't enter into that kind of PPA. But if I'm a renewable power company that has hydro pump storage, I can supply power at whatever time you want during that particular window. That opportunity exists. Those are the sorts of service solutions that will make up the future market, and that's where our work is focused.

Apoorva Bahadur

analyst
#23

We're also examining open access green power supply.

Prashant Jain

executive
#24

Yes, that’s one option besides green hydrogen.

Apoorva Bahadur

analyst
#25

All right, understood, sir. Turning to green hydrogen, I believe a few quarters ago we made an announcement — a partnership, let me recall — with some company in Australia. Have the plans been finalized, and is there anything you'd like to share regarding whether we'll be entering this market and what the scale of that entry would be?

Prashant Jain

executive
#26

At the moment, we're carrying out the scoping exercise, and the techno-economic feasibility work is underway. We're at the final stage of discussions across all of these efforts, including the techno and commercial talks with a range of technology providers. Things are progressing at a much quicker pace than we first anticipated. The results have been extremely encouraging. I firmly believe that before long we'll be taking a concrete investment proposal for the country to the board, and in all likelihood we'll be delivering the fastest project build ever, and a very large one, which will be constructed for green hydrogen as well as green ammonia and additionally some other chemical derivatives.

Apoorva Bahadur

analyst
#27

Oh, great. That's really nice to hear, sir. Sir, one final thing on the renewable capacity addition front. As a nation, I believe we've committed to as much as 450 GW of renewable capacity by 2030. Given how ordering is going right now, along with all the module problems, ALMM, BCD and so on, do you see that being reached?

Pritesh Vinay

executive
#28

That's a hard question to answer, since at the moment, you know, the Government of India has been trying to balance two strategic objectives. The first is the Make in India objective, and the second is the green energy objective. So far they have been, you know, working against each other, which has been a somewhat difficult situation for the pace of growth. Such a thing can be overcome very quickly once this kind of capacities are built up, and capabilities are built up in the country. Then doing 40 to 50 GW every year capacity addition is not a big deal. China has done it, India can do even a bit better than that.

Prashant Jain

executive
#29

Building that kind of capability — and it's really just about capability building — in India will take a maximum of three to four years. If you're talking about 2030, then yes, that is achievable. If you're thinking about the interim capacity target that's in place through 2024, yes, that one is tough. It won't be possible.

Apoorva Bahadur

analyst
#30

Yes, sir. Only one additional item, a fast one, if I can fit it in. Specifically, would you mind disclosing how much merchant power sales added to EBITDA during Q2 and 9M? That would be quite useful. Many thanks. That's everything from me.

Prashant Jain

executive
#31

So, Apoorva, when you have a moment, please take a look at the presentation we've posted — it's also on the website, and you should find the link in your inbox. There's a specific EBITDA bridge shown there, covering both the quarter and the nine months.

Apoorva Bahadur

analyst
#32

All right, I apologize — I didn’t catch that.

Prashant Jain

executive
#33

Yes. You will receive all of it that we require. Yes.

Apoorva Bahadur

analyst
#34

Thanks. Thanks, sir.

Prashant Jain

executive
#35

Yeah. Yeah.

Operator

operator
#36

Thanks. We move to the next question, coming from Vivek Ramakrishnan at DSP Mutual Fund. Your line is open — please go ahead.

Vivek Ramakrishnan

analyst
#37

Good evening. I wanted to ask about receivables. Receivables have dropped quite sharply. That's clearly a positive. Do you see this as something that can hold? Looking ahead, would you say counterparty risk is set to decline meaningfully, whether because you'll be supplying to JSW Steel or because of the SECI projects?

Prashant Jain

executive
#38

If you examine the past 4 years, it has been sustainable, while the deterioration has been taking place. We see no reason it would not remain sustainable. There are 2 reasons for that. First and foremost, one factor is the quality of our power when it comes to tariff, since that gives discoms an incentive to pay us promptly. The second is our management and the way we operate, so both of these account for it. Naturally, looking ahead, the incremental contributions will be arriving from the SECI contracts, so that will also be an added advantage.

Vivek Ramakrishnan

analyst
#39

All right, sir. That answers my question. Thanks so much, and best of luck.

Operator

operator
#40

Appreciate it. Our following question comes from Murtuza Arsiwalla of Kotak Securities, who is on the line. Kindly proceed.

Murtuza Arsiwalla

analyst
#41

I’ve got a couple of questions from—

Operator

operator
#42

Murtuza, we’re having trouble with your audio. Could you please switch to the handset now?

Murtuza Arsiwalla

analyst
#43

Yeah. Is it better now? Hello?

Operator

operator
#44

Yes. Could you join us from the network side, please? We’re losing your voice.

Murtuza Arsiwalla

analyst
#45

Hold on a second. Can you hear me better at this point?

Operator

operator
#46

Yeah, that's a lot better.

Murtuza Arsiwalla

analyst
#47

Alright, two questions for you. The first one concerns the

Prashant Jain

executive
#48

Yeah.

Murtuza Arsiwalla

analyst
#49

During the quarter, we were converted to captive status. Is there any benefit to having completed that? For the captive status, would it require you to, at least on an open access basis, go direct from state to consumer? Is there any benefit there? Second is on fuel cost and margin dynamics. Given how this has moved so far, it looks like you aren't taking the hit from higher imported coal. Can you give us some indication of how much inventory you have, your cost inventory, and how that situation is looking? You had some contribution coming from the short-term markets. Is that more sustainable for a few quarters, or are things not looking as precise?

Prashant Jain

executive
#50

Apologies, Murtuza — your audio kept cutting out, so I wasn’t able to follow you. Pritesh, would you like to pick up this question if you can see— Murtuza, if I caught the first portion of what you asked, which came through a bit more clearly, you were saying that you were pointing to the steps CEA has taken regarding classifying the unit to-

Murtuza Arsiwalla

analyst
#51

Yes. Yes.

Prashant Jain

executive
#52

So the target is IPP to CPP, correct?

Murtuza Arsiwalla

analyst
#53

Yes.

Prashant Jain

executive
#54

That part I might have caught, though it hadn't really registered with me. I'll accept that. On the second question—what would you say the advantage there is?

Murtuza Arsiwalla

analyst
#55

Yeah. Does doing that bring any benefits or drawbacks? And what exactly does that kind of classification involve?

Prashant Jain

executive
#56

As for the contractual piece, since keeping it under IPP status means I can't sell that power except at some kind of discount.

Murtuza Arsiwalla

analyst
#57

Alright.

Prashant Jain

executive
#58

Suppose I wish to sell power through open access — take an industry, X, that's engaged in some manufacturing activity. If I want to sell that electricity under an open access contract, then they would be required to pay open access charges as well as the cross subsidy surcharge, and that comes to more than — in Maharashtra, for instance, the figure falls between INR 2.5 and INR 3 — on top of the capacity charge and fuel charge. That acts as a deterrent for anyone contemplating it. If, on the other hand, CPP status applies, they hold 26% equity in the company, and those charges cannot be levied. Producing becomes economical for them. That is the sole distinction between a CPP and an IPP.

Murtuza Arsiwalla

analyst
#59

Okay, so does that mean we'll now need to divest 26% for the captive piece, or is it really more of a nominal divestment?

Prashant Jain

executive
#60

On the nominal, it's a.

Murtuza Arsiwalla

analyst
#61

Yeah.

Prashant Jain

executive
#62

Right, that definitely needs to be in there—just not on the listed company in that manner.

Murtuza Arsiwalla

analyst
#63

All right, all right. Sir, regarding the second question — if I'm coming through more clearly now — it's about the costs of imported fuel. Those have clearly risen. Even so, the figures you present continue to show a relatively contained level of fuel expense. So, how much low-cost inventory do we actually hold before the higher—

Prashant Jain

executive
#64

My apologies for that.

Murtuza Arsiwalla

analyst
#65

The prices for imported coal began to.

Prashant Jain

executive
#66

No, no, that's not the case. If you're familiar with our company, the entire fuel cost — 100% of it — gets passed through.

Murtuza Arsiwalla

analyst
#67

Okay.

Prashant Jain

executive
#68

That covers exchange, logistics, and index prices. We're insulated.

Murtuza Arsiwalla

analyst
#69

Okay.

Prashant Jain

executive
#70

A few of our

Murtuza Arsiwalla

analyst
#71

That's clear to me.

Prashant Jain

executive
#72

A number of contracts have already shifted over to the job work where

Murtuza Arsiwalla

analyst
#73

Alright.

Prashant Jain

executive
#74

The counterparty supplies the coal, and what we receive is just the fixed cost.

Murtuza Arsiwalla

analyst
#75

All right, all right — that's fair enough, sir. Thank you very much.

Operator

operator
#76

Thanks. Our following question comes from Rohit Kothari at GeeCee Holdings, who is on the line. Go right ahead.

Rohit Kothari

analyst
#77

Hello. Yes. Hello, Prashant. Prashant, might you shed a bit more light on this whole hydrogen venture of yours? I realize you plan to present it to the board, but the hydrogen, the electrolyzer, then the downstream ammonia, and whether you will also examine other downstream chemicals. Second, what size electrolyzer, or what investment range, are you considering in this area? Third, we have observed one or two other big business houses also announcing their hydrogen foray, and they have stated some target cost at which they would want to produce hydrogen to make it viable, since hydrogen at present is not as viable. Where do you see the end cost, or the cost range, at which this will happen? Fourth, will any of your hydrogen go toward in-house group purposes, or would there be captive use with JSW Steel? That is the fourth one. This concerns hydrogen. Just one further question: What is the long-term plan for the JSW Steel stock that you own, given it has appreciated, and would there be any long-term plan to liquidate a portion of it to fund any of your hydrogen forays?

Rohit Kothari

analyst
#78

If you’re able to, Prashant, please shed some light on this. Again, what a fantastic set of numbers, and a very focused strategy that your management has produced — I really have to congratulate you for that.

Prashant Jain

executive
#79

Thank you, Rohit. First off, there's a great deal of discussion happening at the moment regarding green hydrogen. Now, the key ingredient for making hydrogen is renewable power. Whoever is able to generate power at the cheapest tariff will likewise be able to make hydrogen at the cheapest tariff. That's one piece of it. The second piece concerns locations, which matter a lot. What I mean is that if you control specific sites where you plan to install the renewable technology, where you can capture energy most efficiently, and where you have the ability to put capital to work most efficiently in terms of the lowest achievable gross block per megawatt — if you also have the lowest achievable operations and maintenance costs, those three factors will shape your ability to generate renewable power at the cheapest cost. If, on top of that, your cost of funding is the cheapest, then you are the most efficient, and as a result you'll be in a position to pull that off. The fifth key criterion is how you will build a round-the-clock solution for delivering renewable power to make green hydrogen. That's because renewable power is only available 30% of the time across the year.

Prashant Jain

executive
#80

The average PLF is going to land between 30 and 32%. For solar, you're looking at 26%. With wind, it's 30%-35%. The average comes out at 30 to 31. So the question becomes: how do you deploy a round-the-clock solution, and how do you transmit that round-the-clock solution in the most efficient way, given that the PLF is lower at the specific location where your consumption point sits. The next piece, which matters as well, is what happens with the by-product — the oxygen that gets produced from it. That too will be a deciding factor in your ability to produce green hydrogen efficiently. Then the next piece is the supply chain around green hydrogen. What do you do with that green hydrogen? So whether it gets converted into ammonia, whether it gets blended into natural gas, whether it goes to a steel plant, whether it gets stored and then directed into mobility applications or other industrial uses such as refinery, which is being talked about. Now, the reason I am raising all these strategic intents is that these are the various aspects that determine what the cost of production will be for individual organizations doing this.

Prashant Jain

executive
#81

We think that for most of the building blocks I mentioned — roughly 9 to 12 of them — JSW Energy is positioned well enough that we don't have to sit around waiting for government policy intervention. So what we're saying is, thanks to our strategic advantage across all these 10, 12 blocks, we'll be able to begin construction on this project far, far sooner than others can, and at the lowest cost achievable and the lowest tariff achievable as well. That's going to help us accomplish a number of things. I apologize that I haven't given a point-blank answer on each individual aspect of your question, since you raised too many things, but I've tried to summarize most of what you asked. Yes, we hold plenty of strategic advantages in each and every aspect, and those will drive our cost block lower too — both in terms of capital allocation and the cost of production, and thirdly from the user's point of view. Now, we'd like to talk in detail once we go to the board and get approval at some point, which is at a very advanced stage. The second thing you also brought up — I'll give you some color on it — is that typically, to produce 10,000 tons of hydrogen, you need close to 100 MW of electrolyzer capacity.

Prashant Jain

executive
#82

That gives you a rough sense of the scale. For 100 MW of electrolyzer capacity, you'd need somewhere near 300 to 350 MW of renewables, and on top of that, various storage applications would have to be set up so power is available around the clock. Those are the kinds of figures to keep in mind. To produce roughly — say you're aiming for a 200,000-ton ammonia plant — you'd be looking at something like 35,000 tons of green hydrogen to feed it. That's how it works. As for the oxygen by-product that gets generated, for each ton of green hydrogen produced, you'd be generating close to 5.5 to 6 times that amount by weight as a by-product, which you'd have to dispose of and find a way to create value from. Those are the broad numbers, if that answers your questions.

Rohit Kothari

analyst
#83

Yeah, Prashant’s question is about the JSW Steel stake.

Prashant Jain

executive
#84

Yeah.

Rohit Kothari

analyst
#85

What might the long-term picture look like?

Prashant Jain

executive
#86

So we’ve already categorized those as non-strategic in nature. At some point, when we need money, we’ll certainly be glad to monetize them. If you look at how aggressively we’ve been doing capital expenditure, even with that, I have INR 2,200 crore in cash available with us. Our net debt is coming down thanks to the various attractive and very interesting tools we’re able to deploy. We’re able to source the, you know, the LCs to procure equipment in a large capacity and then convert them into usance, which is a much more efficient way to do that. Our debt comes onto the books only after the commissioning of the project, when it starts generation. These are the various innovative tools. At some point, we’ll certainly need more and more equity. At that point, we’ll use this as a buffer.

Rohit Kothari

analyst
#87

Understood. Thank you. Thank you, Prashant.

Operator

operator
#88

Thanks. Just a quick reminder for everyone on the line: if you'd like to ask a question, press star and one. Our next question comes from Anuj Upadhyay with HDFC Securities. Please go ahead.

Anuj Upadhyay

analyst
#89

Thank you for the chance to speak, sir. I have one point to clarify, sir, regarding the capacity addition. There is 2.5 GW currently under construction, and that capacity could start commissioning beginning in the next financial year and probably.

Prashant Jain

executive
#90

Starting with this fiscal year. The current fiscal year.

Anuj Upadhyay

analyst
#91

Alright, phase I. It'll likely run until, say, the close of FY 2024 or around the middle of FY 2025, roughly speaking. That timeframe applies to the 2.5 GW. In the presentation, though, we stated that our aim is to grow this to approximately 10 GW by FY 2025. So could you clarify whether there are any inorganic opportunities we're considering, or some other projects at a very advanced stage of discussion that might enter the picture in the very near term, so that execution unfolds across the next two to three years or so in order to hit that target? Second, regarding pumped hydro storage: any rough idea or estimates of the tariff we're looking at from this project?

Prashant Jain

executive
#92

To start with the first part of that question, as we've mentioned, we've already assembled a resource-site portfolio exceeding 20 GW. That's in hand, and we're in the process of turning those sites into projects. A number of additional projects are under discussion—bilateral ones as well—and execution planning is already done, whether the end use is captive consumption for green hydrogen, integration with pumped hydro storage offered as a solution, or the SECI bids. All of these constitute pipelines that have already been crafted, and we'll announce them in due course of time. What I can say is that against whatever we've planned at this point of time, we will only be accelerating. If certain capacity numbers have been talked about, then we will be achieving them sooner than later. On the inorganic side too, we have been pursuing opportunities very actively, but we don't want to grow either our book or our capacity through an inorganic route at the cost of our returns. You will not find us in a bidding war at SECI bids or at acquisition rates where the returns are not qualitative.

Prashant Jain

executive
#93

To us, growth matters above all, but it has to come with a qualitative return. That is the single most important point. We have consistently discussed how our free cash flow yield stands on an adjusted net worth basis and on a properly adjusted balance. Across the whole portfolio, PPA life runs beyond 18%-19% throughout its life. That is the way we have grown, and that is why, despite the difficult position of the sector, we have kept a consistent cash flow position. We believe we want to hold on to that aspect while still being able to accelerate what we have guided for.

Anuj Upadhyay

analyst
#94

Understood, sir. Regarding tariffs, sir, as far as the pumped storage project goes.

Prashant Jain

executive
#95

Like I mentioned a moment ago, I had laid out that these are the projects that will be moving ahead with different solutions. Because, you see, if you look at it — if you read our company strategy a bit differently — we are shifting from being a power company to one focused on services and products. Down the road, you will see us increasingly as a business offering services when it comes to delivering power at a specific timing, in a daytime block that you want. If you say, "I need power for only 15 minutes during this time," I will provide it. If you need a specific product such as hydrogen, ammonia or another chemical derivative, I will provide it. Building renewable power is going to serve as a baseline for us, but we will be offering various other solutions. Going forward, you will see that strategy shifting away from a commodity business or a plain power company into entering long-term PPAs.

Anuj Upadhyay

analyst
#96

That's fair enough, sir. I appreciate the chance.

Operator

operator
#97

Thank you. If anyone would like to ask a question right now, please press star and one. Our next question comes from Rahul Modi's line. Please go ahead.

Rahul Modi

analyst
#98

Thanks, and congratulations again on a really strong set of results. You've clearly been outspoken about the visible mismatch between demand and supply. We obviously saw that in Q3, when power prices reached nearly INR 20. How do you view the overall demand picture, sir, and how will our capacities serve it? As you noted, we're nearly fully contracted — that's the first point. Second, sir, earlier questions also touched on the size of the opportunity. We've now seen bids in the renewables segment be somewhat erratic. When do you expect a pickup over the coming couple of years? How much annual bidding do you foresee, and how much are you retargeting? You did say IRR is very critical, but from that standpoint, what's your view on the share of the opportunity size?

Pritesh Vinay

executive
#99

Consider it this way: during the first 9 months of this year, power demand rose 9.6%. In the same stretch a year earlier, there was a contraction of roughly 4%. Net that out on an adjusted basis, and you're looking at 5% demand growth — which is the 20-year average for the country. Now, I don't want to dwell on that, okay — the capital cycle CapEx has been revised, and everything else will be aiming at higher consumption, because urbanization keeps increasing, more homes keep getting built, and more industrial CapEx is taking place, so power demand will grow. Now, I keep saying that if power demand grows the way India has grown over the last 20 years and the last five years, then you're talking about 5% demand growth. Now, you've seen this year, and also last year and the year before, that thermal capacity addition isn't happening. Only existing NTPC or certain state projects are under development and getting commissioned. Now, those state-owned and central-owned utilities have also stopped building any new thermal capacity.

Pritesh Vinay

executive
#100

You can safely assume that no additional thermal capacity is going to be brought online. The thermal capacity we already have might be used to the fullest, and some of it will be retired depending on a range of other requirements. Going forward, only renewable capacity will satisfy the need, and that ties to what I said in my opening remarks as well, when I noted that 95% of the additional incremental generation has come from renewable capacity additions, and 95% of the additional new capacity is renewable too. What that means is that at a base load of 165,000 MW and a peak load of 185,000 MW, you are looking at 9,000 to 10,000 MW of incremental demand, and renewable resources will serve it. Now, there are some challenges, such as one participant asking, "Given the difficulties around manufacturing capabilities, taxation and various other things, how do you see whether this target will be achieved?" Yes, over the short term, two, three years, capacity addition could be a problem, and it could speed up afterward, you know, once sufficient capacity in India has been built. During that period, you may see shortages. That is what I have been referring to.

Pritesh Vinay

executive
#101

What you've been seeing is a bit of peak power. Today as well, the average tariff sits at roughly INR 4. But at certain times, you're seeing power tariffs of INR 8, INR 9. That's essentially what's happening, mainly on account of a situation of this kind.

Prashant Jain

executive
#102

You've seen those thermal tenders, for instance the one from Punjab — INR 4.50 ex-bus is the tariff for three months. That's the sort of tariff people are quoting with domestic coal. These things are a precursor to the shortage you're going to see in the next couple of years, which will get mitigated when India builds a lot of manufacturing capability in due course of time. At that point, adding 40 to 50 GW of renewable capacity every year to meet incremental 10 GW of power demand is not going to be a challenge. Yes, everything doesn't move in a linear fashion, but this will get evened out over a period of a decade. That's how my take is.

Rahul Modi

analyst
#103

Thanks a lot. Best of luck to you.

Operator

operator
#104

Thanks. We'll take the next question from Mohit Kumar at DAM Capital. The line is yours — please go ahead.

Mohit Kumar

analyst
#105

Hello there, and congratulations on such a strong quarter. My first question: with the increase in merchant prices we saw during the quarter, does it make sense to hold somewhat greater merchant capacity over the coming few years? Tied to that, where do things stand with RTC bidding? Are you taking part? If you choose to lock in that capacity over the long term, do you plan to secure it? Are you considering the RTC bids, or is it only captive?

Prashant Jain

executive
#106

When you say RTC, are you referring to renewable RTC, or are you referring to thermal?

Mohit Kumar

analyst
#107

Oh, I mean RTC thermal plus renewables — yeah, that mix together.

Prashant Jain

executive
#108

Let me say one thing: we do have capacity that runs on imported coal. With prices sitting where they are right now — the API 4 index at $165 — generating power at that tariff simply doesn't make sense at all. Take fuel cost, for instance: today, fuel costs alone come to roughly INR 5.25. So how do you serve the merchant market in an environment like this? This sort of merchant market is an extremely, extremely difficult one. That's the reason you don't find sufficient thermal capacity up and running, and on top of that, domestic coal isn't available for the merchant market. From a merchant business standpoint, this is a very challenging environment. That's why we've made a decisive move away from the merchant market. Whenever there's a really good stretch in which we can contribute well, we seize that advantage. At that moment, that's what we're doing. Ultimately, our entire plan is to integrate whatever open capacity we have with the long-term PPA. That's how we look at it.

Mohit Kumar

analyst
#109

When we consider long-term PPAs, we're looking at captive arrangements, and we can also take part in the renewable side of things.

Prashant Jain

executive
#110

We're completely open to captive and/or the DISCOM, but I doubt any DISCOM will sign a long-term PPA apart from thermal-renewable integrated bids. We took part in one bid, but sadly the rate there wasn't attractive. Now additional bids are coming up. For instance, Indian Railways has launched a bid featuring 150 MW of a thermal renewable RTC bid. SECI is also planning two more bids along those lines. In those, we'll be integrating our thermal plus renewable portfolio.

Mohit Kumar

analyst
#111

Got it, sir. The second question, sir, concerns JSW Steel holding 26% in the listed entity so that Ratnagiri qualifies as group captive. My understanding is correct, I think — right? So why would JSW Steel own 26% in the subsidiary? You could just as well hold it in the listed entity, right? Additional stake.

Prashant Jain

executive
#112

Under the Electricity Act in that country, a group captive customer has to hold 26% equity in the company. Only then do you qualify as a group captive customer, and at that point you don't have to pay a cross-subsidy surcharge or an additional surcharge, which runs somewhere between INR 2.50 and INR 3, depending on which state you're in.

Mohit Kumar

analyst
#113

Just to confirm, sir — JSW Steel holds 26% of the shares in the listed entity, which is what's needed for Ratnagiri to qualify as group captive. Have I got that right?

Prashant Jain

executive
#114

You're right, Mohit. JSW Steel holds a stake in JSW Energy already. Those shares function as its contra, you know — carrying the equivalent of 26% for those 3 units located at Ratnagiri. Yeah.

Mohit Kumar

analyst
#115

What prevents them from simply copying that approach here for renewables? What's the reason it has to be kept apart?

Prashant Jain

executive
#116

No, they will. If you examine how the assets are held, the Ratnagiri plant is owned directly by JSW Energy Limited.

Mohit Kumar

analyst
#117

Alright.

Prashant Jain

executive
#118

On a standalone basis.

Mohit Kumar

analyst
#119

Got it.

Prashant Jain

executive
#120

Okay, just to round out the question you didn't ask — we're also developing a captive renewable project for JSW Steel. Those are being held in separate SPVs, correct? In that SPV for a captive project, JSW Steel will hold a 26% equity stake in that SPV, right, in order to comply with the Electricity Act rules that Prashant mentioned.

Mohit Kumar

analyst
#121

Got it. One final item — the hydrogen pilot project. What sort of CapEx is involved, and what exactly are you aiming to accomplish? If you've already identified the projects, could you share those details?

Prashant Jain

executive
#122

Yes, we’ll share that in due course, as I explained quite a bit regarding the hydrogen project. We’ll let you know. This won’t be a pilot project — it will be a large commercial-scale project directly.

Mohit Kumar

analyst
#123

All right. Sir, since I was looking at the presentation, it concerned a few pilot projects.

Prashant Jain

executive
#124

No, no. This is going to be a large project at commercial scale.

Mohit Kumar

analyst
#125

And finally, regarding pumped storage — is that capacity going to be put forward for the SECI storage tender? Am I understanding that correctly?

Prashant Jain

executive
#126

Like I mentioned, several opportunities exist—for instance, employing pumped storage to produce RTC power for our own green hydrogen initiatives. There's a chance to provide power as a service business to satisfy demand, delivering it to the end consumer when they need it, and also to participate in the SECI bids. Those are the three opportunities available. Right now, what I'm saying is that allocation has already been secured by us. Project allocation and water allocation are in hand. We've begun the required regulatory approvals, and construction on these projects will likely commence around the end of the next financial year or in early FY 2023, 2024, once various approvals are obtained. We foresee enormous potential in these projects.

Operator

operator
#127

Thanks. Given the limited time remaining, we can only take one more question, and it comes from Sumit Kishore at Axis Capital. Please go ahead.

Sumit Kishore

analyst
#128

Good evening, and thanks for the chance to ask. Could you talk about how long it will take before the reorganization of JSW into the gray and green businesses is finished? And then, over the period after that, what strategic direction do you intend to take this reorganization in?

Prashant Jain

executive
#129

We expect the NCLT approval to come through within a window of 6 to 9 months. Our strategic aim is for all of the growth to originate in the renewable space. All the things we've been discussing — pumped storage, green energy, green hydrogen, green ammonia, chemical derivatives — all of that is going to sit under the renewable space.

Sumit Kishore

analyst
#130

Would you be looking at something like a vertical demerger, splitting those two businesses into separate entities that would each be listed?

Prashant Jain

executive
#131

To generate and unlock value for stakeholders, every option sits on the table, and that's the strategic intent.

Sumit Kishore

analyst
#132

Yes, certainly. The reorganization should be finished at some point during the next financial year.

Prashant Jain

executive
#133

That's true.

Sumit Kishore

analyst
#134

I really appreciate it.

Prashant Jain

executive
#135

Thanks.

Operator

operator
#136

Thanks. That brings us to the final question for today. At this point, I’ll pass the conference to Mr. Rahul Modi for closing remarks. Thank you, and over to you, sir.

Rahul Modi

analyst
#137

Thanks, Mr. Jain. Thanks, Pritesh, and to the whole team for a very thorough discussion and a lovely presentation. Thank you, sir, and all the best. Any closing comment?

Prashant Jain

executive
#138

Thank you, Rahul, for hosting this call, and thank you all for being here. If any follow-up questions come up, please don't hesitate to get in touch. Thanks, and good evening.

Rahul Modi

analyst
#139

Thank you.

Sumit Kishore

analyst
#140

Thanks.

Prashant Jain

executive
#141

Appreciate it.

Operator

operator
#142

Thank you so much. Ladies and gentlemen, that brings us to the end of this conference on behalf of ICICI Securities. We appreciate everyone for being with us, and you can go ahead and disconnect your lines at this point.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete JSW Energy Limited transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

This call discussed

For developers and AI pipelines

Programmatic access to JSW Energy Limited earnings transcripts and 132,000+ others is available through the EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research

OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in JSW Energy Limited or any ticker on your watchlist.

StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.