JSW Energy Limited (533148) Earnings Call Transcript & Summary

October 28, 2022

BSE Limited IN Utilities Independent Power and Renewable Electricity Producers earnings 34 min

Earnings Call Speaker Segments

Operator

operator
#1

Good day, ladies and gentlemen, and welcome to the Q2 FY ’23 earnings conference call for JSW’s Energy Limited, hosted by DAM Capital Advisors Limited. Just a reminder that all participant lines will remain in listen-only mode, and once the presentation wraps up, you’ll have a chance to ask questions. <<operator_script>> Kindly note that this conference is being recorded. I’ll now turn the conference over to Mr. Mohit Kumar of DAM Capital Advisors Limited. Thank you, and over to you, sir.

Mohit Kumar

analyst
#2

Thanks, Faizan. Speaking for DAM Capital, I’d like to welcome everyone to JSW Energy’s Q2 FY ’23 earnings call. Joining us from management are Mr. Prashant Jain, Joint Managing Director and CEO; Mr. Pritesh Vinay, Director, Finance; Mr. Ashwin Bajaj, Group Head, Investor Relations; and Mr. Vikas Choudhary, Investor Relations and Treasury Head. We’ll begin with a few brief opening remarks, and then we’ll move to Q&A. At this point I’ll turn the call over to Ashwin Bajaj. Sir, over to you.

Ashwin Bajaj

executive
#3

Thanks, Mohit, for hosting the call, and a very good evening, ladies and gentlemen. Welcome to JSW Energy's Q2 results call, where we'll detail our result as well as other renewable led growth strategy. Our management team is here as Mohit introduced. So, let me hand it over to Mr. Jain for opening remarks and then we will take questions. Mr. Jain?

Prashant Jain

executive
#4

Thanks, Ashwin, and good evening everyone. During the quarter that just ended, power demand rose 5.7%, which represents a slowdown from the 18% growth in power demand recorded in Q1 of this financial year, and across H1 the increase came to 11.8%. Power demand is still climbing at a solid rate in the present quarter, though we expect the year to finish at roughly 8% to 8.5% growth in power demand. Sector installed capacity now totals 408 gigawatt, with 4 gigawatt of net capacity added in quarter 2 and 8.3 gigawatt added over H1 in total. Every bit of that capacity brought online during the quarter was renewable, with 3.1 gigawatt from solar and 0.9 gigawatt from wind. Installed renewable capacity overall reached 165 gigawatt, more than 40% of total installed capacity. Merchant volume fell 18% in the quarter to 20 billion units, with the average tariff at 5.4 rupees per kilowatt-hour, below the prior quarter, and the H1 weighted average now works out to 6.59 rupees. Prices in the current quarter are also quite low, averaging close to 4.5 rupees to 5 rupees, reflecting better thermal power availability right now along with moderate growth in power demand.

Prashant Jain

executive
#5

Regarding the company, net generation came in at 6.7 billion units, 2% below the prior year, mainly because of a soft merchant market during the quarter and also because the Ratnagiri 300 MW unit was undergoing maintenance. EBITDA stood at INR1098 crores, an increase of 2%. Profit after tax rose 37% to INR466 crores, while cash profit reached INR681 crores, up 12%. We stayed on our receivables trajectory. It declined 19% to 66 days as of the quarter's end, and in the current quarter as well we have been — we are performing quite well on the receivable metrics, so we continue to maintain healthy receivable metrics. Turning to projects, our committed pipeline now stands at 10 gigawatt, and it will be finished ahead of our earlier guidance of FY ’25, and that is without the new domain we have launched, namely the battery storage and pump storage vertical. So the one gigawatt hour battery storage project for which we were recently the winning bidder in the SECI tender comes on top of this 10 gigawatt pipeline. Now, the projects are likewise progressing as planned and ahead of schedule, and beginning in the current quarter, commissioning of the SECI 10 projects will get underway, and then month by month we will see incremental capacities coming up.

Prashant Jain

executive
#6

We're also in a fairly solid position on the hydro pump storage pipeline, and that's progressing. Beyond that, we've picked up some new run-of-the-river hydro projects in Himachal Pradesh as well. For one project, we've already received the NOI award. There are additional projects in the pipeline around the country that we're evaluating, since we believe the new hydro power purchase obligation will bring incremental demand going forward, and once our Kutehr project is finished next financial year, we'll be assigning that execution team to take on new hydro projects going forward. That concludes my opening remarks. We're glad to take your questions and answers. Thank you.

Operator

operator
#7

Thanks a lot. At this point we'll open things up for questions. <<operator_script>> Our first question comes from Anuj Upadhyay at HDFC Securities.

Anuj Upadhyay

analyst
#8

Appreciate the chance to ask, sir. My question concerns where things stand with the Mytrah acquisition, sir — if you could share an update on that. Second, anything regarding the Utkal Ind-Bharat project. On the last call, we noted that we were probably taking another look at acquiring that project, and also, if you could give some sort of timeline for tying up the untied capacity at the Vijaynagar for our captive group plans. That's all, sir.

Prashant Jain

executive
#9

Thank you. Now, regarding Mytrah, the required conditions precedent are in the process of being fulfilled, and we anticipate closing that transaction during the quarter we are currently in. Then as for Ind-Bharat Utkal, the NCLT has already issued its ruling approving the plan, and together with the lenders we are proceeding to put that plan into effect as part of our decarbonization strategy. At this plant we are pursuing vertical integration so that we can move into the polysilicon market. That is the strategy we have, and on the foundation of this 700 megawatt power capacity, we will be working toward vertical integration as a manufacturer of polysilicon. The third item concerns the untied capacity. JSW Steel has already taken on a 5 million ton capacity expansion at Vijaynagar, with commissioning scheduled for some point in calendar year ’25. So in line with that, our untied capacity will be examined within the group capital model as we go forward.

Anuj Upadhyay

analyst
#10

Sir, could you say how much untied capacity is able to be parked for that 5 million tons of expanded capacity at Vijaynagar? Just a clarification on Ind-Bharat — you spoke about vertical integration. So are you saying that project will likely serve the need, the purpose of captive development? Is my understanding correct?

Prashant Jain

executive
#11

Yes, certainly. Where Quantum is concerned, that piece is still being figured out. Even so, most of the capacity that isn't tied up will be folded into expanding capacity.

Anuj Upadhyay

analyst
#12

All right, sir, thank you.

Operator

operator
#13

Our following question comes from Mohit Kumar, who is on the line with DAM Capital Advisors. Please proceed.

Mohit Kumar

analyst
#14

Good evening, sir. My first question concerns the battery storage win. So where does the LOI stand at the moment? And could you please share your strategy, or shed some light on how you plan to schedule your — the market capacity? I believe there is a 40% that you opened up to the market. And how do you see this open capacity being tied up, or would you rather participate in the SLB market?

Prashant Jain

executive
#15

We still haven’t gotten the LOI from SECI, and our understanding is that it will arrive sometime during the current quarter. Right now, we are entirely open to pursuing the ancillary market as well as tying up this capacity with some of the discoms. We have already — we have gotten some interest from discoms and also from certain corporates that want to take on this open capacity available with us, and we have factored both opportunities into this. I can also give you one color: the ancillary market is an equally exciting opportunity, and in some cases what we are seeing is more remunerative than what we do with the tied-up capacity.

Mohit Kumar

analyst
#16

Got it. And regarding the pumped storage side, naturally, you've assembled a sizable pipeline. At what point do you expect we'll be in a position to move forward on something? Does it hinge on securing a PPA, or on landing some hydrogen or a hydrogen order?

Prashant Jain

executive
#17

No, that isn't dependent on it. At this point, what we're mainly dealing with is the regulatory approvals that are in process. But just to give you a sense of it, the first project is going to be a captive one, and it will serve our Vijaynagar plant; we're obtaining the required regulatory approval for it, and we expect construction to begin at some point in the next calendar year, once we've secured that necessary regulatory approval, which is largely handled by <<inaudible>>.

Mohit Kumar

analyst
#18

And sir, what do debt-to-EBITDA and debt-to-equity look like following the Mytrah acquisition, and are we planning to raise some — do you believe we'll need to build up some capital in order to — support further growth?

Prashant Jain

executive
#19

As we covered on the previous call, taking the current pipeline for 3.2 gigawatts together with the projects already under construction, the Mytrah acquisition, and the newly acquired pipeline, all of that combined keeps us under the 4.5 to 4.6x debt to EBITDA level. So we feel quite comfortable, and we will still be generating plenty of cash, since at present we are producing cash profit in excess of roughly INR2,400 crores to INR2,500 crores, which is very, very healthy, and that figure is also going to rise as these projects get commissioned and the acquisition comes in, which will be sufficient to grow our pipeline. That said, should any kind of great opportunity come along where we believe there is a good transaction that can be value-accretive for all the shareholders and there is a chance to deploy that capital by making substantial growth strides, we would not be averse to raising capital, but given the current deployment requirement and the projects in the pipeline, no capital is needed.

Mohit Kumar

analyst
#20

And finally, regarding our appetite for bidding on solar and wind, I'd say at present we aren't taking part in solar. Is that an area we won't touch?

Prashant Jain

executive
#21

Let me flip that question around. The folks putting in bids—what's stopping them from building? So nothing we take on is something we can't build.

Operator

operator
#22

Up next, we have Nikhil Abhyankar from DAM Capital on the line. Please go ahead.

Nikhil Abhyankar

analyst
#23

I appreciate the chance to ask. I just wanted to check whether you're considering bringing on some additional capacity.

Prashant Jain

executive
#24

Right, so once this project wraps up, we'll add another pipeline. There are more opportunities that have already been laid out, and we're looking forward to those. At some point next calendar year, we'll be announcing that pipeline, and on top of that, we're also working on doing more C&I business with third parties. So naturally, beyond the 10 gigawatt, there will be an extra pipeline that gets announced next calendar year.

Nikhil Abhyankar

analyst
#25

Got it. Sir, also, following Q1 in last year’s annual report, you recorded some revenue from selling carbon credits. So I just wanted to ask: at that point, you said the inventory was approximately INR20 million. So in H1, have we recognized any revenue from it? And what inventory do we currently hold?

Prashant Jain

executive
#26

Following the war in Ukraine, prices for carbon credits fell sharply. Credits that had been changing hands above $7.5, $8 now sit at $2.5 as of right now, and we see this as temporary in nature and expect them to rise again. So as of right now, we're holding onto the inventory. We haven't sold any additional volume, or whatever we did sell is quite negligible. And so, Pritesh, what does the inventory stand at right now? Is it the same as what we had? Actually, it will have grown with the <<inaudible>> as well.

Nikhil Abhyankar

analyst
#27

Sir, what's the picture on reserves — have they gone up, and has the Rajasthan government taken part in the government liquidity scheme?

Pritesh Vinay

executive
#28

Could you ask that question one more time?

Nikhil Abhyankar

analyst
#29

Sir, did the Rajasthan government take part in the government liquidity scheme?

Pritesh Vinay

executive
#30

Nikhil, I’ll jump in on that. We may not have visibility into which states are taking part in the government’s liquidity scheme, but here’s what we can address: if you look at the receivables trend, as Prashant noted at the start, overall receivables are down 19% year on year on a DSO-equivalent basis. What’s more interesting, though, is that within that, the overdue amount has actually fallen 23%. And as of right now, after the quarter closed, we have no overdues at all from the Rajasthan discoms.

Prashant Jain

executive
#31

Or any other distribution company, for that matter.

Pritesh Vinay

executive
#32

Right, or any other discom as well. So for that reason, whether it comes down to their taking part in the government’s liquidity scheme or not, we might not be able to match that precisely. However, when it comes to our overdues, we currently have none at all.

Nikhil Abhyankar

analyst
#33

Got it, sir. And earlier, you also brought up our intentions to move into polysilicon. So when might we be in a position to announce something concrete on that front? Or does it hinge on some PLI scheme being introduced by the government?

Prashant Jain

executive
#34

We're focused on what the project involves, since this is a completely new field for the country. A number of barriers exist. There are technology barriers, there are talent barriers. And there are various other challenges when it comes to engineering and other matters that are putting those building blocks in place. So in due course, we'll be announcing as and when we're ready with that. And of course, we will certainly be taking part in the PLI scheme as and when the final scheme is — when the bidding gets started.

Nikhil Abhyankar

analyst
#35

Got it, sir. That covers everything from me. I’ll rejoin the queue now. Thanks.

Operator

operator
#36

Our next question comes from Anuj Upadjyay, who is on the line from HDFC Securities.

Anuj Upadhyay

analyst
#37

Appreciate the chance to speak once more, sir. I'd like to follow up on that initial question about the polysilicon matter. Perhaps just to clarify one point, sir: do we intend to roll out a fully integrated manufacturing model spanning everything from polysilicon all the way through to module manufacturing? And if that's the case, what quantum are we actually targeting here? Also, are we holding off until the PLI schemes are rolled out so we can settle on that quantum? Or are we still — meaning, are we comfortable enough to move forward regardless of the PLI benefits?

Prashant Jain

executive
#38

A lot of elements will play into these decisions. That’s the reason we indicated we’d speak about it at the appropriate time. We therefore have to recognize that PI has a big, ambitious renewable energy expansion plan, and the output won’t serve only power generation—it will also support the electron-to-molecule business, and that will demand a substantial amount of polysilicon, plus ingots and wafers, and there are enormous export opportunities ahead, because following the new Inflation Reduction Act announced in the United States and Europe’s decarbonization strategy, there will be a very large need for polysilicon going forward, in both the European and American markets. So we are mapping out the details regarding our own needs, and also to satisfy domestic demand as well as to capture export opportunities. And there are also various PLI contours, and all of those will be the deciding factor; after that we will determine how much polysilicon capacity there is and how much ingot and wafer capacity there is and how much cell and module capacity there is. Naturally, some capacity will be end-to-end, and some capacity will be solely polysilicon or solely ingot and wafer.

Prashant Jain

executive
#39

So even we are holding that steady with various variables, and then we will make an announcement once we are — we have taken part in the PLI scheme.

Anuj Upadhyay

analyst
#40

Understood, sir.

Operator

operator
#41

Thanks. We’ll take the next question from Rahul Modi at ICICI Securities. The line is yours — go ahead.

Rahul Modi

analyst
#42

Thanks for taking the question, sir. Sir, forgive me if I'm going over something that's already been covered or if I missed it. Could you shed some light on what we have planned for pumped hydro storage over the coming 3 to 5 years? And what capex has been earmarked, and when do we expect that capex to begin? Thank you.

Prashant Jain

executive
#43

At present, we already hold a portfolio of 50 gigawatt hours in pumped storage. And, as I said earlier, at some point during the coming calendar year, the first project will get underway, where we face no problems regarding the lineup — it is just the PPA, meaning the regulatory approval, which we will finish over that period. After that we will begin, and the first project will then require 3 years to be commissioned. In the same way, for all our other projects, the final DPR is being prepared. So it must be approved by CEA before we launch the project. The second aspect is that you must acquire the land — whatever private land there is — and if a forest clearance is needed, then you have to obtain that forest clearance, though for most of our projects there are considerable project implications, yet you must acquire the land and you must secure environment clearance. So all of these projects will take anywhere from 12 months to 24 months before we — before you break ground. Thus, we expect the first project to break ground in calendar year ’23. And from calendar year ’24 onward, there will be various projects that will be breaking ground.

Prashant Jain

executive
#44

This is going to be exciting. At the same time, we'll be adding more pumped hydro projects to our portfolio. As we explained previously, the grid is going to need a large portfolio of pumped hydro projects. So going forward, this deal will serve as a very significant intermittency solution for the grid, and we'll be deploying it over a period of time.

Rahul Modi

analyst
#45

Sir, that's really useful. So regarding that first project you mentioned we'd be kicking off in CY ’23, what capacity would it be, and could you tell us what the total cost is expected to be? You also said the PPA isn't needed — has it already been signed with a particular house? How does that mechanism actually work?

Prashant Jain

executive
#46

Basically, then, this is a solution that's integrated, and it's going to serve the group captive requirement, and so — and it'll come in at close to 1 gigawatt hour.

Rahul Modi

analyst
#47

And how much would that run us?

Prashant Jain

executive
#48

So as soon as we're signing the PPAs and all of that, we'll be making announcements about everything. But generally speaking, I can give you a sense of it. The pump hydro projects fall in the range of INR4 crores per megawatt to INR6.5 crores per megawatt. And pump storage projects typically run between 5-hour storage and 8-hour storage. It depends on the type of project and all of that. So you can work out the math yourselves to get to it.

Rahul Modi

analyst
#49

Okay. And sir, will you be drawing on your own renewables to supply the power? Or at the outset will this mainly come from the grid — or from your captive coal plants?

Prashant Jain

executive
#50

The first project is going to be integrated to meet our own requirements.

Rahul Modi

analyst
#51

All right, that's great. Thanks a lot.

Prashant Jain

executive
#52

Looking ahead, we're developing our own microgrid, and eventually we'll launch a solution that includes a solar park and a wind park, plus a transmission corridor of our own that's tightly integrated with the pump storage — and after that, we'll bring out a large IDC <<inaudible>> solution.

Rahul Modi

analyst
#53

Understood, sir—thanks so much.

Operator

operator
#54

Thanks. We'll take the next question from Anshuman Ashit at ICICI Securities. The line is yours — go ahead.

Anshuman Ashit

analyst
#55

Thanks very much, and apologies if I've overlooked this, but sir, a letter of intent for the Chhatru hydroelectric power plant was also received by you not long ago. So could you share some specifics with us on that — the timelines, the DPR preparation, and the cost we can expect?

Prashant Jain

executive
#56

For this particular project, private parties had already been assigned it previously, and a DPR is already in place. On top of that, environmental clearance was also secured. At this point, we're going to carry out the work, and the DPR has to be revalidated. The environmental clearance must be reinstated, and after that we'll take part in various bids, or in a kind of PPA, with those DISCOMs that are interested in sourcing hydropower. And as I mentioned, there are a couple of additional projects already in the pipeline that will also be coming up, so as the country's largest private sector hydro power producer, we're building this sort of portfolio that will go into a PPA and then into construction going forward. We've already established a very strong capability to execute projects in the most efficient manner, after operating the plants in the most efficient manner. With our Kutehr project, where we began groundbreaking in October 2019, despite the pre-Covid days, we're running ahead of schedule. We've finished close to 5% of the tunneling. We expect this will be the fastest-ever project built in the country in recent times by any hydropower plant developer.

Prashant Jain

executive
#57

So given that type of capability, along with the hydro power purchase obligation, we're feeling pretty optimistic about the different opportunities out there — and that's the reason we're pursuing all of this.

Anshuman Ashit

analyst
#58

Is there any part of that generation that we will need to share with the Himachal Pradesh discom, or provide to them at no cost?

Prashant Jain

executive
#59

The Government of India has already issued a regulation under which free power given to the state is now set at 12% for the entire life of the project, and the project life has also now been decided by the Government of India under the policy at 40 years. So it is one single norm for all old power projects as well as future ones.

Anshuman Ashit

analyst
#60

Alright, and sir, I was just hoping to hear your perspective on where coal prices are headed for FY ’23. And with that in mind, do you think merchant prices will be favorable enough for us to sell on the exchanges? If you could shed some light on that.

Prashant Jain

executive
#61

I'm sorry, but I won't be able to offer any sort of guidance on coal prices, since these are unprecedented times with many variables and factors at play. In the current situation, it's very tough to make a call, but given the way natural gas prices are coming down now, if that trend continues, thermal coal prices will drop immediately. So, naturally, if that price stays elevated, thermal coal prices will stay elevated. So everything hinges on the geopolitical situation in Europe and also natural gas prices. Otherwise, from a demand and supply perspective in a normalized business environment case, thermal coal price should not be more than a dollar <<inaudible>>.

Anshuman Ashit

analyst
#62

Sir, do the merchant prices as they stand right now work in our favor for selling on the exchanges?

Prashant Jain

executive
#63

Nope.

Anshuman Ashit

analyst
#64

All right, got it, sir. Thanks very much.

Operator

operator
#65

Thanks. Everyone, that brings us to the end of the Q&A for today. At this point, I'd like to pass things back to management for some closing remarks.

Ashwin Bajaj

executive
#66

Thanks, operator. And thank you all for being with us today. If you have any additional questions, please don't hesitate to get in touch. Good evening.

Operator

operator
#67

<<operator_signoff>>

Read the full transcript via the API

You're viewing the first half of this call. Get the complete JSW Energy Limited transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

This call discussed

For developers and AI pipelines

Programmatic access to JSW Energy Limited earnings transcripts and 132,000+ others is available through the EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research

OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in JSW Energy Limited or any ticker on your watchlist.

StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.