Good day, ladies and gentlemen, and welcome to JSW Energy's Q3 FY2023 Results Conference Call, brought to you by Emkay Global Financial Services. <<operator_script>>. Kindly be aware that this call is being recorded. At this point, I hand things over to Mr. Abhineet Anand of Emkay Global Financial Services. Thank you, and the floor is yours, sir. Thanks, Suzanne. Good evening, all. To begin, I'd like to express our gratitude to the management for the chance to host this call. Joining us today from the management side are Mr. Prashant Jain, Joint Managing Director and CEO; Mr. Pritesh Vinay, Director of Finance; and Mr. Vikas Choudhary, Head, Investor Relations and Treasury at JSW Energy. The management will give opening remarks, and after that we can move to the Q&A. Over to you, sir.

Prashant Jain

executive
#2

Thank you, Abhineet. Good evening, ladies and gentlemen. And first of all, I wish you and your family a very, very Happy New Year. So, the quarter that just ended was a solid one where power demand is concerned, and in it we recorded 6.4% growth in power demand on a year-on-year basis. And across the nine months, power demand stood at a robust 10% year-on-year. During January of last year, for the first 20 days, power demand grew by more than 15%. So, taken altogether, we continue to witness a very healthy trajectory where power demand is concerned. Where generation is concerned, in quarter three we saw renewable generation rise to 14.1%, and across the nine months to 16.4%, which demonstrates that growth in renewables keeps improving. Total installed capacity stands at 410 gigawatt, and during the quarter we recorded capacity addition of 2.5 gigawatt. And across the first nine months it is 11 gigawatt, which contrasts with last year's full capacity addition of 15.5 gigawatt. It looks like we will fall a little short on capacity addition compared with last year. Now, in total, we have 165 gigawatt of renewable capacity, which is near 41% of total installed capacity.

Prashant Jain

executive
#3

For the quarter, merchant power prices declined 7%, averaging INR4.55 in quarter three. Volume fell 14% in quarter three. API4 price, by contrast, was up 37% at $227 per ton. That's what explains why the quarter fee looked so different: merchant power prices dropped even though demand rose a robust 6.5%, fuel prices were 37% higher, and that's where merchant volumes fell dramatically. In the current month, though, thermal coal prices have eased considerably and now stand at $170 per ton on the API4 Index. Turning to the company's operational performance, net renewable generation rose 3% during the quarter, while net long-term generation was flat at 4.2 billion units. Overall generation declined 5% to 4.3 billion units, mainly due to 230 million units of lower merchant sales in the quarter. If you recall, last year October was a truly exceptional month for the country, with prices much higher and power demand up 12%. Given that higher base effect and the extensive range, power demand growth was negative in the — up to one month this year.

Prashant Jain

executive
#4

Also, the other point — as I explained, since the tariff was lower and fuel price was higher, that created a delta of 230 million units of lower merchant sales. But over the first nine months, our generation is up 2% at 16.8 billion units, which is mainly — and one more important thing is that in the first nine months, our merchant sales rose 65% year-on-year, which is more than 450 billion <<inaudible>> units. Yet generation overall rises only 2% because no schedule was available for our unit numbers earned from Maharashtra. And there, the generation loss was INR550 million units. Apart from that, both on a long-term contract basis and on a short-term basis, the company has performed exceptionally well. On EBITDA for the quarter, it was INR727 crores, down 18%, mainly because of long-term — lower long-term sales. And for the nine months, EBITDA is up 5% at INR2,936 crores. Cash profit during the quarter was INR489 crores, which is a cash return on adjusted networth of 20%, which we have been retaining. Our receivable trajectory is robust.

Prashant Jain

executive
#5

It's lower by 8%, at 69 days. Our projects are moving along quite nicely, with very large commission on schedule for both hydro and wind projects. We've also gotten the LoA for our SECI contract for the battery storage project, which we'll be constructing over a timeframe of 18 to 21 months, and which is going to be commissioned by October 2034. That's everything from my end. With that, I'll open the floor for questions and answers. Thank you.

Operator

operator
#6

Thanks. <<operator_script>>. Our first question comes from Rahul Modi of ICICI Securities. Go ahead, please.

Rahul Modi

analyst
#7

Thank you for the chance, sir. Sir, I just had a couple of questions. The first one concerns some economics — if you could walk us through the BESS project that we've won, specifically what the storage would be, the tariff, the cost, and how the indirect economics would work. That's the first. Second, some progress on — over the coming 2, 3 years, you said the Ind-Barath project would be commissioned within the next 24 months. So, some details on that, on how you see it scaling up, and would you prefer — because as of now it's a low-cost project — so would you prefer to tell it on merchant, or what would the strategy be, like? Thank you.

Prashant Jain

executive
#8

Thank you, Rahul. Now, this project is being sold under a specific lease-rent type of structure, where 60% of the capacity is being sold for 12 years at roughly INR10,85,000 per megawatt per year — sorry, per month. That's how it will be structured, and following 12 years, the project gets transferred back to SECI. The 40% capacity belongs to us, and we're hoping to contract it with other DISCOMS, as well as supplying services into the ancillary market. There's a new ancillary market and policy framework that has been opened up, and there we see better potential to earn improved returns compared to what we get from SECI. That's how the project has been conceptualized. On returns, we can guide at this point that we will be getting close to mid teen or slightly higher returns than what's normally obtained in any generation project. And since we have a number of levers available to us at this point, this is what we'd like to give you as guidance.

Prashant Jain

executive
#9

Once the projects are commissioned and running and operating, then the numbers begin to show, and at that point we can see whether any positive surprises emerge. In this instance, though, we will be earning an equity IRR of the 15%, 16% kind on the project. Sir, just one follow-up on that. So essentially, sir, the DISCOM will provide you with grid power, and during their peak hours we will supply it back to <<inaudible>>. As far as I’m concerned, I’m supposed to make it available. The storage capacity should be made available. Whether they wish to use one cycle or they wish to use two cycles — which DiSCOM will contract the capacity with the SECI for — we are not aware about anything at this point of time. So how it is going to work depends upon the DiSCOM requirement. So we make the system available. They can give me the power in the day time and take it in the night-time. They can give me the power in the night-time and take it in the day time. It depends on them.

Rahul Modi

analyst
#10

Understood. And sir, just so I can get a sense of it, on projects like this, what sort of indicative tariff are you seeing come out?

Prashant Jain

executive
#11

So again, it really comes down to the business case and the business model. If a single cycle is used, the tariff will be different. When two cycles are used, the tariff will be just half of that. If three cycles are used, the tariff will be one third. So I hope that clarifies what I'm trying to explain to you. This is a two-hour storage system. You can even use up to eight or 10 cycles — that's up to you. So at this point in time, it's very difficult to say what this will translate into in terms of storage cost for the end user. It can fluctuate depending on the business case.

Rahul Modi

analyst
#12

Understood, sir. I have two additional questions. First, regarding strategy and progress, how do you expect things to develop over the coming 24 months in Bharat, given that it is a pithead plant? Second, sir, how do you expect the spread between coal prices on the imported business and the merchant to play out for us and for the overall market over the next six to 12 months? Thank you.

Prashant Jain

executive
#13

Sir, merchant tariffs have been getting stronger, and right now they're running at roughly INR6 to INR6.5 each day. Fuel prices, meanwhile, are easing. So that's where things stand. And, you know, thermal coal is tied directly to natural gas at this moment, because natural gas prices — demand for natural gas has shifted over to thermal coal in Europe, and because of that, thermal coal prices had stayed elevated ever since Ukraine came onto the scene. And now natural gas prices have eased and are back at pre-war levels, and that's what's showing up in thermal coal prices too. Now, they aren't at the pre-war level, but, yes, they're very close to that coal number. And if natural gas prices keep sliding and then rise to $3, then I'm quite confident that at some point, terminal prices — coal prices — can also reach $100. So that's the kind of situation, and merchant power prices are very hard to forecast. But what I can see right now is that power demand is very robust all through the year, and we're seeing a substantial uptick when it comes to power demand, and that's what's reflected in the higher capacity utilization as well as the higher merchant tariff.

Prashant Jain

executive
#14

The spreads have improved, and during January we're observing greater merchant volume than what we saw last January. So I do see a solid business case emerging for the merchant power producer over the next couple of months.

Rahul Modi

analyst
#15

Thanks. And finally, a few remarks about the Bharath acquisition — how are you seeing the progress there?

Prashant Jain

executive
#16

With the Bharath acquisition, the primary thing we're concentrating on is getting the plant site established and bringing both units into commission. There are plenty of choices and openings in front of us. One possibility involves vertical integration into polysilicon production, something we've been considering and assessing. A second possibility is examining certain captive needs of the Group for thermal power to serve our Eastern India requirement. A third possibility involves the PPAs that a lot of DISCOMS wish to enter into for thermal power — there are various ones, and those have already been invited by the DISCOMS. So we're assessing every single option, and accordingly we'll be making a decision, in due course, as this capacity gets commissioned, one that is a win-win for all the stakeholders.

Rahul Modi

analyst
#17

Okay, sir, thank you so much, and best of luck to you.

Operator

operator
#18

Thanks. Our following question comes from Atul Tiwari at Citi. Go right ahead.

Atul Tiwari

analyst
#19

Yes, sir, thank you very much. Sir, regarding those battery storage systems, what's the capex for this capacity of 500 MW?

Prashant Jain

executive
#20

So we’ll be disclosing that. We’ll let you know. Right now, we’re firming up a couple of orders. And so in the Q4 results, we will inform you of the total capital expenditure.

Atul Tiwari

analyst
#21

All right, thank you.

Operator

operator
#22

Thanks. We now have a question from Sumit Kishore at Axis Capital. Sumit, please proceed. Sumit, your line is in talk mode. Go ahead.

Sumit Kishore

analyst
#23

Good evening. My question concerns the purchase of the Mytrah RE assets. During the previous call, you said you anticipated that this deal would be finished or wrapped up prior to the close of Q3, and that the gross blocks stage for it would be, as I recall, first April 2022. So where does it stand at the moment?

Prashant Jain

executive
#24

Yes, I agree with that expectation, but there are 17 lenders involved, and most of them come from the public sector. Occasionally, a few issues arose around lender NOCs that were outside our control. Most of those matters, however, have now been resolved. Of the 17 lenders, 15 NOCs have been received, and two remain in the pipeline, which we expect any time soon — and by soon I mean within days, not weeks. That is the only item still pending, and once that movement occurs, we will be in a position to complete the deal. As you know, the balance sheet comes to us from first of April 2022 itself. The consolidation, though, will take place on the date of closing.

Sumit Kishore

analyst
#25

So the P&L won't be consolidated starting April 1, 2022?

Prashant Jain

executive
#26

No, no. Whatever the adjustment turns out to be, it will be made in the network and gross blocks. So consolidation will take place starting from the acquisition data.

Sumit Kishore

analyst
#27

And do you have anything new since the prior call regarding your pumped storage hydro projects?

Prashant Jain

executive
#28

So those are progressing nicely. At this moment — I should mention that a comprehensive project report has to be put together. After that report is ready, approval from the CEA is required, and a public hearing must also be held in order to obtain environmental clearance. A full — and detailed engineering work has to be carried out as well. So all of that is underway, across every one of the projects, and as we noted in our presentation, for the first project serving our captive needs at Vijayanagar, construction will begin within this current calendar year. So there, we have already advanced quite far when it comes to every type of approval, and we have already issued tenders and so forth. So at some stage during this calendar year, we will be — once matters are finalized, we will go to the Board, and then begin construction right away. However, prior to going to the Board, we are carrying out every kind of preparatory work, and this is what is happening across all the projects concurrently, for the 7.8 gigawatt that we have disclosed to the market, which equals 50 gigawatt hour or <<inaudible>> so.

Prashant Jain

executive
#29

Things are moving along nicely in every location, but because every one of these is a greenfield project, all of this work is happening at the same time. And on a year-on-year basis, you'll see various projects shifting into construction mode.

Sumit Kishore

analyst
#30

One last thing — can you give us an update on where things stand with the INR195 billion PLI scheme for solar manufacturing? How near are we to the bidding stage, and to a final decision being made, you know?

Prashant Jain

executive
#31

We’re no different from anyone else. We’re aligned with the industry as well as the government of India, and whenever something reaches the final stage, we’ll look to take part in it and see whether we’re competitive enough to secure something there or not.

Sumit Kishore

analyst
#32

Sure, thank you, thank you very much, and I wish you all the best.

Operator

operator
#33

We’ll now take the following question from Abhineet Anand’s line. Go right ahead. Yes, sir. My question concerns wind. The government has established a goal: from roughly 40 gigawatts that we currently have to about 140 gigawatts by 2030. Solar has picked up and done better. All of us have witnessed that during recent years. First, I mean, how realistic are those figures? And since your wind success rates are also stronger, how do you see those capacities being scaled up over the coming few years?

Prashant Jain

executive
#34

Abhineet, wind projects are hard to pull off given the kind of project they are, since you know they stretch across kilometers and kilometers even for a modest 300 megawatt project. That creates right-of-way and land acquisition hurdles plus access problems when you compare them with solar. So that's one issue. The second issue is that the tariff a wind project produces comes out much, much higher than what a solar project yields, because of where the technology stands, and that's where more and more difficulties arise when it comes to executing the PPA at those tariff levels and executing the project on the ground. So the government is mindful of this challenge. But however, the two need to be viewed differently, because with solar alone you cannot have grid stability, nor can the profile of the renewable energy be maintained. So wind is also required. Hydro is also required. So it has to be a blend, which is required for the country as a whole, and similarly thermal is also required. So that's — the direction being stepped in is, first, that reverse bidding has now been contemplated, that will be stopped and it will be a simple — single line competitive bidding.

Prashant Jain

executive
#35

We’re hoping that if this introduces a bit of discipline among project developers, and some prudence follows when it comes to tariffs, then it may become somewhat more appealing to secure stronger investment in the wind sector. Execution challenges are going to persist, and it remains to be seen how much capacity can be added each year. So the numbers can be achieved, but the timeline is up for discussion — it might take a couple of years longer — yet the numbers can be achieved.

Operator

operator
#36

And on that point—I mean, on the supplies side, which I think used to come earlier, because this whole thing—whether you're talking about Suzlon or Gamesa or some of the other players, India has been adding something like 1 or 2 gigawatts, maybe 2 or 3. So do we actually have enough solid suppliers to serve a market of 7, 8, or 5 gigawatts, whatever the figure turns out to be? What's your sense?

Prashant Jain

executive
#37

Right, right — availability of supply isn’t a constraint at all. Tariffs were the largest shortfall. So with the correct tariff level, projects can proceed — sufficient capital and sufficient equipment are on hand. Even so, execution difficulties will remain.

Operator

operator
#38

I really appreciate it.

Prashant Jain

executive
#39

It can be mitigated quite effectively.

Operator

operator
#40

Thanks. Thank you. Moving on, we have a question from Dhruv Muchhal, who is calling in from HDFC Mutual Fund. Dhruv, please go ahead.

Dhruv Muchhal

analyst
#41

Yes, sir. Thanks very much. I have one quick clarification.

Operator

operator
#42

Apologies for interrupting Mr. Muchhal. Sir, you’re coming through very quietly. Please speak up a bit.

Dhruv Muchhal

analyst
#43

Is that an improvement?

Operator

operator
#44

That's a lot better. Thanks.

Dhruv Muchhal

analyst
#45

Just to verify regarding that SECI battery project — the LoA has come in. So is there still a need to hold off on construction until the PPA arrives, or is this the final green light? Can we proceed now? In other words, is uptake fully assured at this point?

Vikas Choudhary

executive
#46

The clock really begins once the PPA gets signed. That's the reason, on the earlier question, I didn't ask — I haven't given out the capex figures. That's the point where we anticipate these will be wrapped up ahead of our Q4 results. And after that, we'll go ahead and place the order. Still, on our end, everything is fully prepared and in place, whether it's financing or anything else.

Dhruv Muchhal

analyst
#47

Understood, sir. The last item is simply that we're waiting on the PPA, and once it's finalized, the 18 to 24 months begin from that point.

Prashant Jain

executive
#48

Yes, 18 months — let's take that as our starting point.

Dhruv Muchhal

analyst
#49

That’s great — thanks a lot.

Operator

operator
#50

Thanks. Our next question comes from Atul Tiwari at Citi. Go ahead, please.

Atul Tiwari

analyst
#51

Yes, sir, thanks a lot for the chance to speak again. Sir, my question concerns that 225 megawatt solar project: with the project now finally commissioned, what does the gross block stand at? So what's the figure — could you share that number?

Prashant Jain

executive
#52

Yes, it's near — actually just a bit above INR1100 crores, yeah.

Atul Tiwari

analyst
#53

Alright, alright, thank you.

Operator

operator
#54

Thank you. After that — ladies and gentlemen, that brought our final question. At this point I’ll pass the conference back to management for their closing remarks.

Prashant Jain

executive
#55

Much appreciated. Thanks for the call, Abhineet. Enjoy your evening.

Operator

operator
#56

Thanks, operator.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete JSW Energy Limited transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

This call discussed

For developers and AI pipelines

Programmatic access to JSW Energy Limited earnings transcripts and 132,000+ others is available through the EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research

OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in JSW Energy Limited or any ticker on your watchlist.

StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.