JSW Energy Limited (533148) Earnings Call Transcript & Summary
October 20, 2023
Earnings Call Speaker Segments
Operator
operatorGood day, ladies and gentlemen, and welcome to the Q2 FY 2024 Earnings Conference Call of JSW Energy Limited, brought to you by Batlivala & Karani Securities India Private Limited. Please be reminded that every participant line will be in listen-only mode. Once the presentation ends, you will have a chance to ask questions. If you require assistance at any point during this conference, please signal an operator by pressing star and then zero on your touchtone phone. Kindly note that this conference is being recorded. I now hand the conference over to Mr. Rajesh Majumdar from Batlivala & Karani Securities. Thank you, and over to you, sir.
Rajesh Majumdar
analystAlright. Good evening, everybody, and thank you for giving us this chance. Today's conference call for JSW Energy Limited is being hosted by the management group, which includes Mr. Prashant Jain, JMD and CEO; Mr. Pritesh Vinay, Director of Finance and CFO; and Mr. Vikas Jadhav, Head IR and Treasury. To begin with, sir, congratulations on a really strong set of results. So, without further delay, we'll now turn the call over to Mr. Prashant Jain so he can deliver his opening remarks. Thank you, sir.
Prashant Jain
executiveThanks, Rajesh. Good evening, everyone — and yes, it's late on a Friday night. The power sector has been making headlines for positive reasons lately, and to begin with, power demand rose 13% during the quarter, and year to date it was up more than 7%. In October, month to date, power demand is higher by over 19%. Overall, we keep witnessing a really strong pattern of exceptionally high power demand, and as a result, we're seeing a very large power deficit — the sort of deficit we witnessed during the 2004 to 2006 period. Recall that back then, grid capacity was tiny, close to 80 GW-85 GW, whereas now it stands at 200 GW. A power deficit of this magnitude at a grid size like this translates into a substantial shortage of power capacity. In the quarter, we saw total capacity addition of 3.5 GW, and year to date, 9.3 GW, and at present our total installed capacity is 425 GW. Merchant volume for the quarter was higher by 26%, and year to date, 20%, while the power tariff for the quarter averaged 5.9.
Prashant Jain
executiveOn the company side, power generation rose 29% to 8.6 billion units, driven by greater renewable output as well as increased merchant sales. The company posted its highest-ever EBITDA of INR 2,008 crore, along with record cash profit of INR 1,180 crore and profit after tax of INR 850 crore. For short-term sales in the quarter, our merchant tariff came in at INR 8.17, compared with the INR 5.90 exchange price for the quarter that I mentioned earlier. That shows the company's ability to strike bilateral contracts at a tariff 35% above what the exchange offered to merchants, which also added substantially to this higher EBITDA. In the quarter, we commissioned 86 MW of SECI X capacity, bringing total year-to-date commissioned capacity to 216 MW. Every one of our existing 2.4 GW projects is progressing on the schedule we guided in earlier quarters, and we expect all of that capacity to be commissioned in the current quarter, the current financial year, and the next financial year, in line with the scheduled timelines. At Ind-Barath, boiler light-up has been completed, and the turbine is ready for synchronization within the next seven days. The transmission line, however, has one or two bottlenecks that are being resolved.
Prashant Jain
executiveWe anticipate that unit one will be commissioned next month. Unit two is going to be commissioned in quarter four, as scheduled. In terms of eligibility as well as generation, Mytrah delivered a very good, exceptional performance. Generation rose by 27% year-on-year, and that contributed significantly to the EBITDA. I had guided for the company that we are running ahead of the schedule in terms of the integration as well as the EBITDA improvement program, which we guided to the Street. In the current financial year, you will be seeing that a lot of the hard work has been done, and then that will be flowing into the bottom line of the company ahead of the schedule. Receivables improved 10% year-over-year, both for the consolidated as well as including the Mytrah. That performance is going to further improve in next three to six months timeframe. The net debt of the company stayed at INR 24,260 crore, and with the debt-to-EBITDA of 3.3x without CWIP and 4.6x with CWIP. Weighted average interest cost reduced from 8.66% to 8.51%. There is an interesting development which we have now to share with all of you is we have been guiding for the next batch of our growth.
Prashant Jain
executiveWe've said publicly that there's 10 GW of visibility, with commissioning happening by December 2024. Now, JSW Energy has entered into an MOU with JSW Steel to develop 6.2 GW of renewable capacity, 2.7 GWh of storage capacity, and 85,000 tons to 90,000 tons of green hydrogen for making green steel. That 85,000 to 90,000 tons of green hydrogen will come with an additional 1.8 GW of renewable capacity and 1 GWh of storage capacity. All of this is to be completed by 2030. In total, that means within the group roughly 9 GW, or 8 GW, of renewable capacity, 3.7 GWh of storage capacity, plus the green hydrogen and green oxygen. We'll be deciding on the pricing mechanism in due course. What I can tell you is that, historically, whether third party or group captive, we've been executing all our projects at IRRs of at least mid-to-liquidity. With that, I'd like to open the floor for questions and answers. Thank you.
Operator
operatorThanks so much. At this point we'll open things up for questions. If you'd like to ask something, just press star and one on your touchtone phone. Should you want to drop out of the queue, press star and two. We ask that participants use their handsets when posing a question. Ladies and gentlemen, we'll pause briefly while the queue fills up. Participants, you can press star and one to ask a question. Our first question comes from Atul Tiwari at Citigroup. Please go ahead.
Atul Tiwari
analystYes, congratulations on the strong results. I just want a quick clarification regarding the merchant sale. Is it fair to assume that it came from the Vijayanagar and Ratnagiri projects?
Prashant Jain
executiveThat is correct.
Atul Tiwari
analystOkay, so what was the actual size of this INR 8 merchant sale? Like, how many units did that involve, and so on? Sorry — your results just came out, so I haven't had a chance to go through the PPT yet.
Prashant Jain
executiveYou're referring to — during this quarter, what was the total number of MUs sold in the merchant market?
Atul Tiwari
analystRight, so what was the landed price on imported coal for you, if you could give a hint on that? Those are the data points I need.
Pritesh Vinay
executiveLet's start with imported coal. The API4 Index — the benchmark for 6,000 Kcal high GCV coal — actually fell 65% year-on-year in this quarter, averaging around $113 per ton versus the same period last year, right? You'll be able to derive that, because — just to restate what we've shared previously — at Ratnagiri we do a blend of low GCV and high GCV. At Vijayanagar, since it's inland and there's extra inland transportation cost involved, we typically try to use maximum high GCV coal. So, looking at the standalone financials, you'll be able to compute the implied fuel costs. We won't be able to disclose that separately. On your first question, we sold roughly 660 million units in total in the short-term markets during the quarter.
Atul Tiwari
analystAll right. So with the power market looking tight at this point, I mean, do you already have bilateral contracts in place for the third and fourth quarters too, or are you planning to kind of?
Pritesh Vinay
executiveThis happens continuously, Atul, since it cuts both directions. For instance, states are usually—what's the word—hesitant about committing to longer-term bids. Seven-day, 15-day, and 30-day arrangements have shown up, yet nothing past 30 days has really appeared. Yeah. Still, I figure it's only a question of timing, and looking back historically, the third quarter typically comes in softer.
Prashant Jain
executiveI think, Prashant here. The reason why I explained this point is not from the point of view about the differential we have garnered. The point that I told is that power shortage is for real. That's why most of the DISCOMs are trying to lock in the power instead of waiting to secure it into the Day-Ahead Market, because there is no reasonable assurance to get the availability of power. The reason is to explain this point is to look at from that point of view, not from the point of view of the any other way.
Atul Tiwari
analystYeah, I completely agree with that. Just one additional point on it. Since Ind-Barath unit one is scheduled to be commissioned next month, have you already locked things in on the bilateral side, or would you rather keep it entirely merchant — what's the situation with the PPA? I realize you've mentioned in the past that you wanted to keep it open and try to take advantage, but is there any thinking on that?
Prashant Jain
executiveWe'd prefer not to comment on that aspect, since we make decisions day by day, and whatever serves our interest is what we'll do, based on how the market looks. The key thing is that this market is really tight, and it's going to stay tight for many months, quarters, and years.
Atul Tiwari
analystI agree with that. Do you have anything to say about the coal arrangement for Ind-Barath? I mean, have you been able to secure anything from CIL or another source?
Prashant Jain
executiveThe coal comes from mines close by, and we already hold that coal through different auctions. Supply through January is already locked in, and anything past that is tied up too. For this year, whatever volume we produce, we will have the coal, already secured from Coal India or its substitutes.
Atul Tiwari
analystAnd that includes the SHAKTI tranches, all handled via the auction mechanism?
Prashant Jain
executiveYeah.
Atul Tiwari
analystAlright. Alright. Alright. Thanks, sir. Appreciate it.
Operator
operatorThank you. At this point, ladies and gentlemen, if you'd like to pose a question, please press star one. Our following question comes from Lavina Quadros, who is on the line with Jefferies. Please proceed.
Lavina Quadros
analystYeah, hi. Congrats on a solid set of results. I just wanted a bit of clarity regarding Mytrah. How is that acquisition ramping up, and does it line up with what you had predicted of INR 1,450 crores?
Prashant Jain
executiveI believe in our acquisition presentation we actually pointed to higher figures than that, where we discussed normalized EBITDA of around INR 1,650 crore, to be delivered by FY 2025. Whatever ramp-up plan we had guided for regarding the added energy as well as lower O&M costs, we are ahead of schedule on it. That is what I was explaining — by the close of the financial year, you will find that most of what we guided for FY 2025, you will see in FY 2024 itself. It's performing quite well.
Pritesh Vinay
executiveBuilding on that, Lavina — and as Prashant mentioned during his opening remarks, he brought up the performance improvement asset optimization plan. To give you a sense of it, in this quarter specifically, Mytrah's generation rose 27% on a like-to-like, year-on-year basis. That increase was driven mainly by greater machine availability, which was up nearly 700 basis points year on year, and availability for the wind capacity came in at roughly 97% during the quarter. In a similar vein, on the solar side, actual generation beat the P90 generation — it reached close to 165 million units. When you examine the delta increase in Mytrah's generation improvement, nearly half stemmed from focused interventions aimed at achieving higher throughputs, securing greater availability, and proper spares management along with O&M management, and so forth. All of this produces better generation and therefore better revenue, along with optimization of O&M costs. So even at the EBITDA level, as Prashant noted, if you revisit the transcript or recording of our fourth-quarter fiscal 2023 call, when the Mytrah acquisition was consummated, we had guided toward reaching that normalized EBITDA run rate roughly 18 months after the acquisition.
Pritesh Vinay
executiveIf you look at it from a run rate perspective, we're in fact ahead of those timelines, and improved EBITDA captures all of that. Mytrah, you know, posted an EBITDA of roughly INR 557 crore in this quarter. Beyond that, we've of course spoken at length about the gains from lower financing costs stemming from a benchmark debt refinancing as well as debt resizing. So, as Prashant said in his opening remarks, the weighted average interest rate for this quarter, on a sequential quarter-on-quarter basis, has in fact come down, even though, you know, the rate cycle has not turned and MCLR keeps pressing upward. The reason was that the full effect of the debt refinancing at Mytrah was coming through. To add to that and close the loop, as Prashant also brought up, is the receivables situation within the Mytrah portfolio. Year on year, Mytrah receivables are in fact lower by 50%, you know, versus the same time last year. All in all, I think, operationally and financially, the integration and optimization layout of the Mytrah acquisition has been very robust.
Lavina Quadros
analystThanks. And finally, regarding green hydrogen, could you say a bit more about that? I mean, the plan is getting bigger, and you’ll need to bring in the electrolyzers. Is there anything else you want to mention on that side, on the ecosystem?
Prashant Jain
executiveLavina, I’d ask that you allow us a bit more time. With this MOU, the overall aim is first to lift visibility from 10 GW–20 GW, and also the electron-to-molecule business. Now that this has been put in place, perhaps within a couple of months you will see us discussing every single item in detail. That said, our first green hydrogen plant is already under construction. Equipment has already been ordered. We are proceeding with alkaline technology. We are importing it from the Chinese manufacturer, and construction has already begun, and we expect that by March 2025, this will be up and running.
Lavina Quadros
analystAll right, that's excellent. Thanks very much.
Operator
operatorThanks. Our following question comes from Anuj Upadhyay at Investec. The line is yours — go ahead.
Anuj Upadhyay
analystYes. Thanks to all of you for giving us this opportunity. Would you be able to go into more detail about where things stand on the PSP side?
Operator
operatorPardon the interruption, sir, but your audio isn’t coming through very clearly. Please speak using the handset.
Anuj Upadhyay
analystHas it improved at this point?
Operator
operatorThat's a good deal better, sir. Please continue.
Anuj Upadhyay
analystAll right. Can you give us more detail on where things stand with PSP? An LOI has been signed — we've got that LOI covering 2.4 GW — so where exactly are we in the development process? Does this involve Maharashtra alone, or does that 2.4 GW also include other states?
Prashant Jain
executiveYes. Thank you, Anuj. Work has already begun at every one of these sites, and what we're focused on at the moment is securing the regulatory approvals and placing equipment orders. Equipment ordering is at an advanced stage, and on the regulatory side we're dealing with forest and environment clearance. For one project, the EC is already — you know, it's in the final stage. The meeting has wrapped up, and we'll get the EC during this quarter, while the forest clearance should also come through next quarter. Once the EC and FC are both in hand, we expect to begin construction early in the next financial year. The project equipment will have been ordered by that point as well. Beyond that, there are 6 projects in total sitting at a similar advanced stage of regulatory approvals, along with plant ordering. Since we foresee a large number of bids arriving quickly later on, we want to be fully prepared. There are 6 projects in total where we're pushing very aggressively. They add up to a value of 7.8 GW of capacity, but with average storage time of around 6.5 hours.
Prashant Jain
executiveAll of that work is happening at the same time on Environment Clearance, Forest Clearance, land acquisition, and equipment ordering as well. We'll have those items ready, and the moment we can lock in the bids for supplying that storage capacity, we will begin construction right away and issue the notice to proceed to the equipment manufacturer. That's where things stand with the PSPs.
Anuj Upadhyay
analystCan you pin down the amount we’re waiting on from the EC next year, sir — the one we think, you know, we expect to start construction on? What would that amount be?
Prashant Jain
executiveConstruction won’t begin unless and until the bid is won and financial closure is completed. Please understand, what are the various enablers for starting the PSP project? First, you receive the allocation; second, you obtain regulatory approval; third, you win the bid; and fourth, you complete financial closure. Those are the items. What we’re doing is: the allocation part is finished, we’re finishing the regulatory approvals, and then keeping the — you know — ordering ready. Now, there will be the two milestones we need to achieve before putting that into construction: winning the bid and completing financial closure. Once we win the bid, then at that point in time, the turnaround time will be very, very short to put them into construction. We’ll be able to tell you as soon as we win more bids.
Anuj Upadhyay
analystOkay, sir. One last thing — are all seven of those projects located in Maharashtra, or do we also have some in other states?
Prashant Jain
executiveWe have projects in other states as well — Karnataka, Maharashtra, UP, and Rajasthan. Seven projects there are at advanced stages.
Anuj Upadhyay
analystAlright, if I could just ask one more thing — it ties into the module manufacturing side. From what we heard last quarter, you're likely moving the base to a different state, possibly Rajasthan. Any update on that, sir?
Prashant Jain
executiveThis is located in Rajasthan. The land has already been acquired, the boundary work is complete, and the equipment has been ordered. We have also obtained an incentive package from the Government of Rajasthan, and construction is now underway. Under the March 2025 schedule, it will be up and commissioned.
Anuj Upadhyay
analystOh, alright, sir. That's going to be for 1 GW, is that right?
Prashant Jain
executiveCorrect, yes.
Anuj Upadhyay
analystAlright. Thank you, sir, and I appreciate the chance to speak.
Operator
operatorThanks. Ladies and gentlemen, if you'd like to ask a question, please press star and one. Our next question comes from Sumit Kishore at Axis Capital. Go ahead, please.
Sumit Kishore
analystGood evening, Prashant and Pritesh. I’d like to start with the MOU you signed with JSW Steel. That 6.2 GW of generation capacity essentially accounts for 60% of the growth you’re making in going from 10 GW to 20 GW by 2030. So is this really just putting formal shape around the share steel would contribute to your capacity buildout after 2024?
Prashant Jain
executiveRight. So that represents 62% of the capacity, and on top of it, an additional 1.8 GW is set to come up for green hydrogen manufacturing as well. Correct. Altogether, we have visibility into roughly 8 GW, and beyond that we'll be pursuing SECI projects, perhaps acquisitions, and we may hold a C&I portfolio too. All of it sits in front of us. Whatever proves remunerative, we'll keep locking it in. You can genuinely see that 80% has clear visibility, and that portion will sit within our control.
Sumit Kishore
analystOkay. So since you've got 80% visibility there, do you have any sense at all as to whether that 20 GW figure is going to be upgraded?
Prashant Jain
executiveSumit, my thought is that we should revisit this perhaps 1 year or 1.5 years down the road. Should it become clear that our guidance needs revising and that we ought to roll out a strategic 3.0, then we will definitely do so. Speaking for myself and my own level of confidence, yes, there is a chance we will perform better, given a stronger balance sheet, improved cash flows, and greater visibility. Right now, we are staying with our strategy 2.0.
Sumit Kishore
analystOkay, so regarding the energy storage projects referenced in the MOU — the 2.7 GWh — will those be supplied from your pumped storage hydro capacity, or will they be new battery energy storage system projects? What's the question?
Prashant Jain
executiveIt's going to be a mix, and it really depends on what the needs are. From JSW Steel's standpoint, we're seeing 3.7 GWh, 1 GWh for hydrogen, and 3.7 GWh paired with the RE generation. But one thing's certain — it will be a combination.
Sumit Kishore
analystOkay, so the 2.7 GWh — that's distinct from the storage piece you'd need to pair with the renewable power setup for green hydrogen, correct?
Prashant Jain
executiveThat is correct.
Sumit Kishore
analystOkay, okay. So on the JSW 2.0 strategy, you had spoken about EBITDA of roughly INR 20,000 crore by FY 2030 — that's close to a 6x-6.5x jump from the INR 30+ billion rupee run rate you were at. If I just think out loud here, that figure has upside thanks to this MOU you've signed, since new projects have been added to the count.
Prashant Jain
executiveYou're right about that.
Sumit Kishore
analystAlright, and could you also give an update on the battery energy storage system project — where things stand? Have you finalized the battery arrangements and so on? How near are we to actually getting the project implemented? You had flagged it for completion before the end of CY 2024. A related question on the SIGHT program: has there been any movement on bids being submitted, and when do you expect progress on that front?
Prashant Jain
executiveWe're fully prepared, honestly. There's been a slight holdup when it comes to getting the PPA signed, since SECI is still securing some approvals. This is the first project of its kind, with the Central Government providing some subsidy to the DISCOMs that take advantage of it, and there are procedural elements involved in that. That's why the PPA signing has been delayed, though it could happen at any moment. The moment the PPA is signed, we'll move straight to awarding the contract. We'll carry out the project according to schedule, since it won't take much time and everything else is already in place. At this point we don't foresee any challenge regarding project execution or the timeline we've guided for, but the procedural delays are there.
Sumit Kishore
analystRight. So how's that SIGHT program coming along, in terms of, you know, new opportunities that are coming up there?
Pritesh Vinay
executiveRegarding the site — yes, that's still a work in progress. As and when that National Green Hydrogen Mission tender wraps up, we'll certainly take a close look. My understanding is that the bids had initially been slated for some point in September, and then things got pushed back. So let's wait and see on that front. Yes, I'd say that's another possible optionality for us. With the MOU we've signed alongside JSW Steel, we find ourselves in a comparatively stronger position to take part in the SIGHT tenders, since we now have an end-use project that makes us eligible. SIGHT is really almost a PLI-equivalent kind of scheme, isn't it? We'll be watching that closely and actively as and when it comes up.
Prashant Jain
executiveThe majority of those discussing green hydrogen simply lack any available buyer. This MOU changes that—there is a buyer, there is an application for manufacturing green steel, and that places us in a genuinely competitive advantage.
Sumit Kishore
analystRight. And last thing, regarding that pumped storage hydro project at 300 MW and 2.4 GWh, where the LOA is in place — what precisely is the status of work on the ground at this point? What's—
Prashant Jain
executiveI already gave this explanation to the person who spoke before me. I believe Amit posed a comparable question. In case he didn't catch it, I'll go over it again: we are currently securing the regulatory approvals, EC and FC, and we expect both to be in place by the close of this financial year. Equipment ordering is underway, and we anticipate moving into construction early in the next financial year. As I said as well, to prevent situations of this kind later, we are already working on that total. Along with these two projects, there are five additional ones, making seven projects overall. We have already begun these preparatory steps in order to obtain the various regulatory approvals, carry out land acquisition, and place equipment orders. Once we secure the bids and then complete the financial closure, those projects can enter the construction stage ASAP.
Sumit Kishore
analystGot it — very clear. So if you begin building that initial 300 MW, 2.4 GWh next year, completing it would require another 24 months, correct?
Prashant Jain
executiveNo, that's going to take 36 months.
Sumit Kishore
analystThree years.
Prashant Jain
executiveWe're looking at 36 months to 48 months. It varies by project — for one we think 36 months, while another might run 40 months to 45 months — but we'll provide guidance on that in due course.
Sumit Kishore
analystAlright. Thanks a lot, and I wish each of you the very best.
Prashant Jain
executiveThanks.
Sumit Kishore
analystThanks, everyone. Goodbye.
Operator
operatorThanks.
Pritesh Vinay
executiveModerator, could we have the final question now, please?
Operator
operatorYes, the final question comes from Rajesh Majumdar at Batlivala & Karani Securities. Go ahead, please.
Rajesh Majumdar
analystI had a couple of things I wanted to ask. First, is the company on the lookout for additional coal assets that lack PPAs under NCLT, or any other assets of that kind that might be available — are we considering those? That was my first question.
Prashant Jain
executiveRajesh, we keep evaluating different opportunities, and whenever we come across a good one, we will definitely try to, you know, lock it in. For the record, you can take it that anything and everything available in the power sector, we are interested in it.
Rajesh Majumdar
analystAre there still opportunities like that out there? That's actually what I was asking.
Prashant Jain
executiveThat is a difficult one to answer, yet, you know, plenty of opportunities exist out there, though they aren't obtainable at a fair price. Some opportunities can be had for a fair price. When the price is unreasonable, many things can be obtained.
Rajesh Majumdar
analystAlright. Sir, my second question concerned the 6 GW addition at JSW Steel. Actually, I was on the JSW Steel call a short while ago as well. The company stated clearly that CapEx funding for this will be shared in some manner. Could you shed some light on how that is going to work regarding the funding from JSW Energy and how it will operate?
Prashant Jain
executiveUnder the act, there is a captive power policy, and under it these projects have to sit inside an SPV. The power procurer must hold 26% equity in that SPV, with JSW Energy taking the remainder. Debt will flow into the SPV based on that PPA, to supply the power. That is the way it will work, and that is the same group capital structure used across all our existing power projects, thermal or renewable.
Pritesh Vinay
executiveYes, Rajesh, that's precisely the same approach we're applying to the 958 MW currently in our pipeline of projects that are under execution. It follows a comparable model under the captive scheme.
Rajesh Majumdar
analystRight. When you provide the CapEx guidance, this is clearly part of what’s included there, correct?
Prashant Jain
executiveYes, yes. It will be similar, but we’ve already provided guidance for a long-term CapEx plan, which falls under Strategy 2.0, and so guidance will be based on that plan.
Rajesh Majumdar
analystGreat, that’s useful—thanks a lot. I believe we don’t have any further questions. Thank you very much, sir, for the chance, and if you’d like to offer a few closing comments, you’re welcome to wrap up the call.
Prashant Jain
executiveNo, thanks a lot, everyone, and happy Navaratri and happy Dussehra to each of you and your families. Thank you.
Operator
operatorThank you. That brings this conference to a close on behalf of Batlivala and Karani Securities. We appreciate everyone joining us. You can disconnect your lines now.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete JSW Energy Limited transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →This call discussed
For developers and AI pipelines
Programmatic access to JSW Energy Limited earnings transcripts and 132,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in JSW Energy Limited or any ticker on your watchlist.
StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.