JSW Energy Limited (533148) Earnings Call Transcript & Summary
July 19, 2024
Earnings Call Speaker Segments
Operator
operatorGood day, everyone, and welcome to the JSW Energy Q1 FY25 earnings conference call. Just a reminder that every participant line is in listen-only mode, and once the presentation wraps up, you'll have a chance to ask questions. If you need help at any point during the call, please signal an operator by pressing star then zero on your touchtone phone. Kindly be aware that this conference is being recorded. I'll now hand things over to Mr. Abhishek Nigam from Motilal Oswal. Thank you, and the floor is yours, sir.
Abhishek Nigam
analystThanks, Sagar. Good evening, everyone. I’m speaking on behalf of Motilal Oswal Financial Services, and I welcome all of you to the JSW Energy conference call for discussing the Q1 FY 2025 results. Joining us is the company’s leadership team, which includes Mr. Sharad Mahendra, Joint MD and CEO, Mr. Pritesh Vinay, Director of Finance and CFO, and Mr. Vikas Chhabra, Head of Investor Relations and Treasury. So, with no further delay, I’ll hand the call over to Mr. Mahendra for his opening remarks. Over to you, sir.
Sharad Mahendra
executiveYes. Thank you. Good evening, everyone. I appreciate your participation on today's call. This last quarter was outstanding for the power industry and particularly for JSW Energy. Conditions in the sector are changing quickly, bringing fresh possibilities as well as difficulties. As we are aware, given our country's swift expansion, GDP is projected to have risen 8.2% in FY 2024, supported by strong manufacturing and industrial activity. Significantly, India's manufacturing segment expanded 9.9% in FY 2024, underscoring the essential part the power industry plays in enabling greater economic activity. Before we move into our quarterly results, I want to give a summary of where power demand currently stands. Demand for power across the country rose at an impressive 7.5% rate in fiscal 2024, supported by resilient economic activity nationwide. During this quarter, we observed a quickening in demand growth, with a year-on-year rise of a robust 11%, even against last year's higher base. This quarter also saw a record peak demand of 250 GW on 30th of May this year. Consistent with demand growth, the nation's generation went up 11% year-on-year. All India thermal PLFs likewise climbed to 76.4% in the quarter, versus 70% in the same quarter a year earlier.
Sharad Mahendra
executiveWith demand continuing to rise, I think the bigger push is on adding capacity and delivering power that is both sustainable and reliable. When we look at the country's power capacity, total installed capacity has now hit 446 GW. Net capacity addition for this quarter comes to 4.2 GW, after 200 MW of thermal capacity was retired. That compares with net capacity addition of 5.8 GW in Q1 of FY 2024. Renewable energy capacity added during the quarter was 4.4 GW. Solar led this addition at 3.7 GW, while wind capacity added was close to 800 MW in the quarter. India is expected to add 30 GW to 35 GW of RE capacity this year and is targeting roughly 15 GW of thermal capacity additions this year. With the nation aiming for annual RE bids of 50 GW, bidding activity has risen significantly, as seen in the last fiscal. Notably, total installed capacity addition in FY 2024 came to 26 GW, of which 18.5 GW was RE capacity, against the target of 50 GW per annum. This points to a substantial rise in growth opportunities. The Government of India has set a trajectory to increase renewable energy consumption through the RPO obligation.
Sharad Mahendra
executiveStarting from the present 22% level, that figure is scheduled to rise to 30% in FY 2025 and reach 43% by 2030. As for RE's present contribution to the grid, it accounts for 13% of total power generation measured in energy terms. With both of those factors considered, there is a growing requirement for RE generation to be paired with storage. That is being mirrored in what we observe today, with incremental bids now coming for hybrid power as well as FDRE solutions. In contrast to plain vanilla RE generation, FDRE and hybrid projects deliver a comprehensive solution tailored to what a DISCOM or state needs. As a result, we are seeing two developments in the biddings. First, the quantum of auction has grown and now exceeds 50 GW per annum, and second, there is an urgent requirement for these solutions. At JSW Energy, we view this as a huge opportunity for us. Turning now to the merchant markets, we have observed strong demand growth. This stems from hot weather conditions, which caused an unprecedented rise in the country's energy consumption. Even though merchant volumes surged by approximately 17% year-on-year, average merchant tariffs saw a slight year-on-year increase, which points to a strong demand environment. Day ahead market prices in Q1 of the current fiscal stand at INR 5.27, versus INR 5.17 in Q1 of last year.
Sharad Mahendra
executiveCoal prices saw a year-on-year decline, though they strengthened on a sequential basis. Taking a specific index such as API 4, it remains at $108 in Q1 of FY 2025, versus $116 in the last fiscal year, which is a 7% drop. As things stand right now, API 4 coal prices are hovering at roughly $805 per ton. Turning now to how JSW Energy performed during the quarter just ended, we'd like to share that we added 291 MW of capacity in that quarter, all of it wind. Out of this, 45 MW came through closing an acquisition, and the remaining 246 MW was fresh greenfield capacity, representing close to one third of the new wind capacity the country added in Q1 of the current year. Moving to our net generation, output for the quarter rose 18% year-on-year to 7.9 billion units, powered by a 44% jump in renewable energy generation along with a strong thermal showing. It's worth noting that our hydro generation climbed 61% year-on-year, marking the highest Q1 generation in the last 5 years. This is mainly attributable to better hydrology. Nationally, hydro generation was broadly flat in Q1 of FY 2025. That said, the hydro plants in the Sutlej River basin, where our Karcham Wangtoo and Baspa plants sit, have posted an average 38% year-on-year rise in generation.
Sharad Mahendra
executiveWind generation was up 40% year-on-year thanks to capacity additions, plus roughly a 4 percentage point gain in machine availability this quarter. Turning to thermal, net generation rose 4% year-on-year, supported by increased output at our Ratnagiri plant and by contributions from operations at our Utkal Unit One, which did well but ran into some teething issues in the quarter — normal when a unit is first commissioned. That unit has been stable since July, though. On Utkal Unit Two, I'm glad to report that the steam blowing and boiler light up work is done. Synchronization of Unit Two is expected in the quarter we're in now. To give you more detail on projects still under construction, progress is solid on our SECI wind projects, which are scheduled for completion this fiscal year. Wind capacity under construction totals 1.7 GW. On the group captive wind projects, we installed 103 MW in Q1 of the 737 MW of work now underway. At our Kutehr project site, a severe landslide in April 2024 — as everyone knows — washed away all the access roads, which set back project activity.
Sharad Mahendra
executiveWith road infrastructure restored, work has now picked back up, and out of the three units, Unit One's boxing is finished, and all three units should be commissioned within the current year itself. Slide 11 shows you the specifics on the projects still under construction. Over the last six months, we've assembled a strong pipeline of projects totaling 5.7 GW of cumulative capacity. That brings our total locked-in capacity to 15.5 GW. I'm happy to share that PPAs for 2 GW of these projects have already been signed. Beyond that, the required board approvals are in hand, and we're very near to signing PPAs covering 1.3 GW of RE projects, storage included, for captive use by our JSW Group companies. This falls within the 6.2 GW MoU we signed with our group, JSW Group, last year, aimed at capacity additions over the coming few years. Adding this, the total pipeline capacity with PPAs comes to 3.3 GW. Projects for which PPAs are signed should be commissioned in the next 18 to 24 months. Slide 12 lays out the details of the project pipeline. As part of our company's energy products and service offerings, we are building Asia's largest battery energy storage system, at 1 GWh capacity, which is tied up with SECI.
Sharad Mahendra
executiveThe PPA for 250 MW has been signed, and the remaining portion should be — will be — signed very soon. As we communicated earlier, commissioning for this project is scheduled to take place before June 2025. In addition, we are constructing a green hydrogen facility to produce green hydrogen for green steelmaking by our group company. As we said earlier, this is a pilot project for us, with a capacity of 3,800 tons per annum of green hydrogen and 30,000 tons per annum of green oxygen. This is India's largest green hydrogen project currently under construction. Construction has begun at our Vijayanagar site in Karnataka, and we will commission this plant before March 2025. Turning to the company's financial performance, during the quarter we reported an 80% year-on-year rise in profit after tax, at INR 522 crore. This came on the back of strong EBITDA growth of 21% year-on-year. We continue to maintain a healthy balance sheet and receivables. Our net debt to EBITDA, excluding CWIP debt, stands at 2.2. It remains well below our guided range for sustainable normalized net debt to EBITDA of 3.5 to 4. We are making significant progress toward our target of achieving 10 GW capacity by the end of the current financial year, and we are well on track to achieve 20 GW capacity well before 2030.
Sharad Mahendra
executiveGiven the solid base and fundamentals we have, I have every confidence that JSW Energy is positioned well to do very well in the quarters ahead and to seize the huge opportunities that have emerged now that the landscape has changed. Thank you, friends. At this point, I will pass things over to Mr. Pritesh Vinay, who will walk you through more detail on how we performed financially.
Pritesh Vinay
executiveThank you, Sharad. Good evening, everyone, and thanks for being with us on the Q1 results earnings call. Sharad has already gone over, you know, most of the points, but perhaps I'll take just a few minutes. Looking at EBITDA, you know, EBITDA for the quarter came in at roughly INR 1,580 crores. That was 21% higher YOY. If you turn to slide 8 of the presentation, it lays out the EBITDA bridge. But basically, on the thermal side, we picked up an additional INR 90 crores of EBITDA YOY, largely driven by the incremental contribution from unit one of Ind-Barath. On the renewable side, EBITDA rose by more than INR 110 crore YOY, helped by new organic ARE capacities coming on stream, as well as, the, incremental EBITDA generation from hydro thanks to better hydrology. Other income also increased, YOY, on treasury gains and some LPS payments we received during the quarter. On the balance sheet, Sharad has already mentioned, you know, it remains continuously very healthy. If you look at slide number 10 of the presentation, that shows the net debt bridge. So sequentially, quarter-on-quarter, as you can see, net debt has declined by around INR 3,300 crore, and a big part of that, this relates to the extra liquidity from the INR 5,000 crore QIP capital raise we completed in the month of April.
Pritesh Vinay
executiveThus, at the close of the quarter, our cash stood above INR 6,100 crore. The ratios remain sound. On slide 13, the headline leverage metric — net debt to LTM EBITDA — comes in at roughly 3.8x. However, when you strip out the debt tied to capital work in progress to get sustainable normalized net debt to EBITDA, the underlying figure works out to 2.2x, which is quite healthy. Our weighted average cost of debt edged up slightly versus the prior quarter and finished June at 8.75%. Receivables continue to look very healthy, and at June's end, days sales outstanding across total receivables came in at a very healthy 65 days. Moreover, we have witnessed steady gains in every one of our businesses, in every location. With that, perhaps I will pause here, and we can take questions from the floor. Thank you.
Operator
operatorMany thanks. We’ll move on to the Q&A portion now. To ask a question, you can press star and one on your touchtone phone. If you’d like to take yourself out of the queue, press star and two. We ask that participants use handsets when asking a question. Ladies and gentlemen, we’ll pause briefly while the question queue is put together. Our first question comes from Sumit Kishore at Axis Capital. Please go ahead.
Sumit Kishore
analystGood evening. I want to offer my praise for the solid bottom-line results and for the pipeline growth. First question: regarding those pipeline projects totaling 5.65 GW, for the ones without a signed PPA — what's the general expectation there? Roughly when do you anticipate finalizing PPA signing on those projects? And realistically, in FY 2027, how much of that capacity might get commissioned? That's my first question.
Sharad Mahendra
executiveAll right. Look, the bids we've won — as I mentioned — and the PPAs we've signed cover 2 GW, and for the remainder, the agencies that ran those tenders are in contact with the buyers, the various DISCOMs and states, and that ordinarily takes its normal course. We anticipate it happening quite soon; this activity has already picked up speed, and we expect these PPAs to be firmed up and executed shortly. Pinpointing an exact timeline can be difficult, but as we've noted, under normal circumstances the period observed has been anywhere from 30 to 60 days, 70 days. So we anticipate these PPAs being signed before long. Come FY 2027, as you put it — well, as I've stated, whichever PPAs get signed, completion runs 18 to 24 months from the PPA signing date, depending on when the signing happens. On that basis, those timelines will certainly be achieved and the projects will be carried out accordingly. On top of that, whatever captive requirements exist — whether solar or wind — those capacities will also be added within that same 18-to-24-month window.
Sumit Kishore
analystGood. And would that also cover executing a PPA with JSW Steel for the group captive capacity?
Sharad Mahendra
executiveRight, exactly. That’ll come on top of the 2 — the 1.3 GW — and we expect to sign that very soon.
Sumit Kishore
analystMy second question is this: with battery prices changing so quickly, and given what we've observed regarding standalone BESS deployment and discovery, how do you expect load-following FDRE tariffs to settle over the next few quarters? We saw the SECI two FDRE rate, of which JSW won a portion. Yesterday — or the day before yesterday — we saw solar plus single-cycle battery storage. Could you comment on the direction?
Sharad Mahendra
executiveThe precise figure really hinges on what type of requirement it is. Like you mentioned, two days ago, it was a different solution.
Sumit Kishore
analystRight.
Sharad Mahendra
executiveThat involved a combination of solar plus storage — energy storage, battery storage — and handling just one discharge through the evening peak. So it really hinges on the way the project is designed, what the requirement happens to be, and how much energy needs to be met. It depends. So giving a precise tariff for anything — say someone wants 80% power, 80% in energy terms — that calls for a different product design. But yes, as you mentioned, what we've been observing is that it ranges, as was the case day before yesterday, with a single discharge in solar at roughly INR 3.42, or whatever tariff was discovered, which is a reasonable tariff. And I'd like to reiterate here that for us, the tariff serves as our benchmark returns; whenever and wherever we're getting it, and we are meeting our benchmark returns — that is the only situation in which we accept those tariffs and pursue winning the bid, not simply for the sake of winning the bid. So we are very, very certain about what our benchmark returns are, whether we are achieving them or not. So the tariffs, whatever has been discovered, and depending on what kind of product mix is required, in terms of storage and solar, or whether it's FDRE, which is solar, wind, and storage.
Sharad Mahendra
executiveIt really comes down to how the product is designed, rather than offering a single straightforward figure, which you could do with a plain vanilla solar or plain vanilla wind project. In this case, it hinges on what product is actually needed.
Sumit Kishore
analystJust one follow-up on this. Take the SECI FDRE 2 rate of 5.59 or thereabouts that came out in March. If that same bid were held today, have battery prices fallen since then as well? Or has equipment pricing corrected enough that you'd discover a price of, say, some INR 5 for that same tender, you know—
Sharad Mahendra
executiveYes.
Sumit Kishore
analystThree, 4 months from now?
Sharad Mahendra
executiveYeah, that's a really good question. With what we're observing — battery prices moderating as they come down, and cell prices too — I think that same solution, in our view, could be offered somewhere in the range of perhaps INR 4.6 to INR 4.7, or even INR 4.8.
Sumit Kishore
analystYeah.
Pritesh Vinay
executiveSumit, let me add something here as well.
Sumit Kishore
analystYes.
Pritesh Vinay
executiveTrying to forecast something like this is tough, and one very important factor we haven’t addressed so far is how intense the competition is and what underlying returns anyone is actually aiming for, you know? So what does the effective project cost end up being, given the negotiating strength that any given developer might have? And what returns, hurdles, hurdle rates of return, you know, is one solving for? So once you layer all of that together, it gets hard to extrapolate where you think something like this could normalize. Because at different moments in the market, for strategic reasons, different players could be motivated by various things, right? So there could be someone trying to put a tick in the box for multiple strategies, for some other reasons. There could be someone building a pipeline for a potential capital raise. You know, so it becomes challenging in that way to extrapolate, right?
Sumit Kishore
analystYeah. Yeah, yeah. Just one last question. The presentation notes that in under a year from now, both your 1 GWh BESS project and the green hydrogen project will be up and running. Could you share some color on where the battery and the electrolyzer have been ordered from, if anything can be disclosed, so we have a better understanding, and also the project cost?
Sharad Mahendra
executiveAs I mentioned to you, Sumit, when we state that in designing this and whatever else, project cost and similar matters come second for us, the point is we must make sure I earn the return I want, which is mid-teen. In this instance, yes, with equipment prices having moderated, we feel quite confident that perhaps high-teen returns are what we will achieve on these projects. So instead of focusing on what the project cost is, what matters is the return I am getting, and I have absolute confidence that we will obtain returns greater than those we anticipated when we planned these projects.
Sumit Kishore
analystThanks, and I want to wish each of you the very best.
Sharad Mahendra
executiveThanks, Sumit. I really appreciate it.
Operator
operatorThanks. Ladies and gentlemen, so that management can take questions from everyone on the conference, please limit yourselves to two questions per participant. Should you have a follow-up, kindly rejoin the queue. Our next question comes from the line of Mohit Kumar with ICICI Securities. Please go ahead.
Mohit Kumar
analystGood evening, sir, and congratulations on a good set of numbers. My first question is about this clarification. Are you running the Ratnagiri Unit 1 on a case-by-case basis? Is that right?
Sharad Mahendra
executiveYeah. That's correct, Mohit.
Mohit Kumar
analystRight, right. On your second question, we're aware of the PPAs that a handful of state discoms have floated for coal-based plants. Do you see yourselves beginning work on a new power plant, or could you tie up Ind-Barath — look to tie up Ind-Barath under a long-term PPA?
Sharad Mahendra
executiveLook, Mohit, states have clearly begun seeking PPAs once more. As for Ind-Barath, the benefit we enjoy today comes from sitting close to what is nearly a pit-based plant, having adequate coal available there, and our overall fuel cost being extremely competitive and low. We observe that the chance in the merchant market is substantial at present, though it may not last, perhaps I would say, over a long horizon, yet we foresee the coming 1 or 2 years, 3 years, until enough thermal capacity gets, until capacities are added. And as I mentioned during my opening remarks, given how demand growth is running far above what anybody had been expecting, we view this as a solid near-term opportunity for us. At this moment we will keep operating in the merchant market. Yes, the situation and what the government of India has also announced, in order to satisfy rising demand, the fresh thermal capacity additions, which exceed 80 GW, needed by 2032, whenever the chance arises and the state comes forward, we will certainly be pursuing that opportunity going forward as well, for adding more capacity in the thermal segment.
Mohit Kumar
analystIn the near term or medium term, do you think that within the next one year you could begin commissioning or constructing any new power plant?
Sharad Mahendra
executiveNo, that won't happen. Building a new thermal power plant follows its own natural timeline. That delay will certainly be there, but any major investment on our part will only happen if we have the PPAs in hand.
Mohit Kumar
analystGot it. For my final question, sir: regarding the various projects in our portfolio, at which of them are we at 11, and where has the PPA or the LOA not yet been issued?
Sharad Mahendra
executiveMohit, could you take a look at slide 12
Mohit Kumar
analystYeah.
Sharad Mahendra
executiveThat wraps up the part of the presentation that ought to be useful to you.
Mohit Kumar
analystAlright. Thanks. Thanks. Thanks, Mr. Sharad. Appreciate it.
Sharad Mahendra
executiveYeah.
Operator
operatorThanks. Our following question comes from Anuj Upadhyay with Investec Capital, whose line is now open — please go ahead.
Anuj Upadhyay
analystYeah, thanks for the chance to ask, and congratulations on those solid results. My question is—
Operator
operatorSir, your line sounds a little muffled. Maybe—maybe you should switch to headset mode, please, just in case.
Anuj Upadhyay
analystSure. Is it better now?
Operator
operatorThat's an improvement, sir. The floor is yours.
Anuj Upadhyay
analystRight, so my question relates to the underperformance at the Vijayanagar station, and also to the low PLF at Barmer, which out here is still sitting at around 60% to 67%. Could you shed some light on what's behind that?
Sharad Mahendra
executiveSo, Anuj, we've also tried to explain this earlier: if you look at Vijayanagar, out of 860 MW for the station, we have only about 310-odd MW that's tied under PPAs, right? So the remaining capacity is open for sale in the merchant markets, and that's opportunistic trading that has to be done depending on where the dark spreads are, right? And the Vijayanagar plant, since it's inland, the fuel cost compared to Ratnagiri is going to be higher because of inland transportation cost. So from time to time, based on unit economics, we will — the team will go ahead and book trades in the short-term market, and hence you're always going to see variability in the PLF, or variability at the Vijayanagar station, right? As far as the Barmer plant goes, in Q1 we had some planned outages of some of the units, all of which have been completed. So if you look at the CEA data for the current month, for example, it's running at a very high PLF. So the PLF for Q1 is lower due to planned outages.
Anuj Upadhyay
analystOkay. So these were planned outages, right? Does that mean there would be any underrecovery for Q1, which was good for Barmer?
Sharad Mahendra
executiveThe way the recovery or under-recovery works is that it's actually calculated on an annual basis. So yes, for the quarter there will be an under-recovery, but if we hit the deemed PLF numbers over the course of the year, that gets made up toward the back end of the year. Yeah, that's how it works.
Anuj Upadhyay
analystOkay, that's reasonable. And finally, going back to Vijayanagar — I mean, at first our thinking was that this project might run under Section 11, so, but then again, as you said, it largely hinges on the unit economics and the opportunity. So that Section 11 sort of thing—
Pritesh Vinay
executiveYou're correct, Section 11 stayed in place only until around the end of June, as I recall.
Sharad Mahendra
executiveMm-hmm.
Pritesh Vinay
executiveApologies — that's the close of May. May 30th.
Sharad Mahendra
executiveSection 11 applied during March, April, and May.
Pritesh Vinay
executiveYes, but I believe it's no longer on Section 11 at this point.
Anuj Upadhyay
analystAlright, that's a valid point. Appreciate the question and the chance to address it.
Sharad Mahendra
executiveThanks.
Operator
operatorThanks. Our next question comes from Ketan Jain of Avendus Spark, who is on the line. Please go ahead.
Ketan Jain
analystThanks, sir. First question from me is a follow-up on that Section 11 matter. So are you anticipating that the government will extend Section 11 — that it gets extended?
Pritesh Vinay
executiveWell, the key issue is that predicting what the government will do next is extremely hard in the first place—just imagine yourself in their position. The main factors behind such a decision, I think, will be how they see the balance between demand and supply. Demand has grown quite robustly, sure, but we're past the summer peak and the monsoon has arrived, plus there are extra supply sources such as hydro, and the windy season is almost here. So if anyone is projecting a demand-supply gap over the coming couple of months, I would find that surprising. That said, who can say? During the second half of the year, after the monsoon—say, from October through March, which is a high-demand stretch—the government may make that call, depending on the projected load curve and the supply available from different sources at the right moment. Still, my sense is that ordinarily there's no advance notice for these sorts of things.
Ketan Jain
analystGot it, got it. The next thing I'd like to ask is this: at the Ind-Barath and Vijayanagar plants, what kinds of realizations are you seeing, and what kinds of input costs?
Pritesh Vinay
executiveWhat will probably help you understand this is that we won't be disclosing unit cost details on a station-wide basis, but it's also important to help you think about these things, right? So, for example, let's take them one by one. Let's take Ind-Barath. Ind-Barath, we've said, you know, because we don't have a PPA, so there is no SSA. So the only source of coal is through the auction route. Right now, it is either the spot, the auctions or through the Shakti auction schemes, you know, under the Ministry of Power. And there we, you know, from time to time participate, and we've guided in the past that, you know, we have looked at average cost, you know, of between say INR 2.75 to INR 3, you know, on an average, for Ind-Barath. On the imported coal-based stations, we source everything from the seaborne markets, so you'll see how the API coal indices are moving. And then you'll be able to make a good, a good estimate for both Ratnagiri. I also said in a response to an earlier question, that Vijayanagar is inland, you know, so there's an additional inland transportation cost. So there will be a higher spread between Ratnagiri to Vijayanagar.
Ketan Jain
analystGot it. One final question, sir, about merchant capacity. Sir, is there greater demand for merchant capacity during non-solar hours or during solar hours? For instance, what type of PLF does, say, maybe an Ind-Barath run at in a non-solar hour?
Sharad Mahendra
executiveLook, Ind-Barath, Ketan, I want to say this: clearly, from what we're observing, daytime demand is certainly quite strong, but that's because there's so much solar available during the day, thermal power isn't there. In our situation, though, if you look at how we've shifted, we've contracted our capacities on an RTC basis with multiple DISCOMs over the short term—perhaps a 3-month period or a 4-month period. So we're protected from whatever is going on during the daytime at Ind-Barath, and we've contracted our power on an RTC basis for a 3-month period. That's the way we've moved.
Ketan Jain
analystGot it, got it — thanks.
Operator
operatorThanks. Mr. Jain, is there anything else you wanted to ask?
Ketan Jain
analystGot it, sir. Thanks.
Operator
operatorThanks. One quick reminder for everyone on the line: if you'd like to ask a question, hit star and one on your touchtone phone. Our next question comes from Vishal Periwal at Antique Stock Broking. Please go ahead.
Vishal Periwal
analystYes,
Operator
operatorApologies for cutting in, Mr. Periwal, but we can't hear you at all. Could you please switch to handset mode?
Vishal Periwal
analystYes, I apologize. Can you hear me more clearly at this point?
Operator
operatorThat's a better result. Please continue.
Vishal Periwal
analystYes, absolutely. Regarding your question about capacity additions, if you look at slide 12, it provides a bit of detail on that. For the FY 2026 additions, would it be fair to say that the 2.6 GW of PPAs already signed will at minimum get commissioned?
Sharad Mahendra
executiveRight. Like I mentioned, every one of those solar projects has a timeline of roughly, let's say, 18 months. So 18 to 24 months — I believe we'll be adding that within those timelines, yes. But also, as you pointed out, we're confident that this capacity addition will happen over that period.
Vishal Periwal
analystAll right, all right. Then regarding our additions — I mean, going from 25 to 30, like in FY 2030, moving from 10 GW up to 20 GW — do we also have any midterm target for FY 2027 or FY 2028, sir?
Sharad Mahendra
executiveNo, look, Vishal, like I mentioned in my statement as well, we're confident that roughly 18 months ago we stated 10 GW by FY 2025 — that was phase I — and 20 GW by FY 2030. But given how the landscape has shifted and the opportunities that have emerged, plus the volume of pipeline we currently hold, we're confident this 20 GW will be reached sooner — considerably sooner than FY 2030. We're working out what those numbers will be. That effort is ongoing alongside the opportunities, and as I said, our returns, the ones we've benchmarked against, are protected, along with the opportunities that will exist in the bidding space. So FY 2030 will definitely show a different figure, but this 20 GW is going to happen considerably earlier. That much I'll still stand by.
Vishal Periwal
analystYes, sir. Yes, yes. And one final point from me: regarding our CapEx, we mentioned on the prior call that we'd be spending roughly INR 15,000 crore in FY 2025. Do we have any figures we're aiming for in 2026, or is that still undecided?
Sharad Mahendra
executiveRight.
Pritesh Vinay
executiveThat's about it for the moment, Vishal, though since a quarter of the new year is already behind us and, as you know, more and more bids keep lining up for the period still ahead. So for FY 2026, I'd say it's a bit premature. Perhaps near the end of this year would be the right moment to give you guidance for the next year.
Sharad Mahendra
executiveYeah.
Vishal Periwal
analystAbsolutely, sir. Appreciate you addressing that. I’ll follow up at another point. Thank you.
Sharad Mahendra
executiveThanks, Vishal.
Operator
operatorThanks.
Pritesh Vinay
executiveOperator, could we please take the last question?
Operator
operatorAbsolutely. Up next, we have a follow-up question from Ketan Jain of Avendus Spark. The line is yours — please proceed.
Ketan Jain
analystThanks for allowing me to ask a follow-up. Sir, my final question is this: with the wind project still being built, are we dealing with, or do we anticipate dealing with, any issue regarding capacity to evacuate transmission?
Sharad Mahendra
executiveNo — for wind projects currently being built, every bit of transmission capacity is already committed, along with all the projects that are under construction.
Ketan Jain
analystGot it. And on top of that, are you noticing any tightness in the transmission supply chain when it comes to substations or transformers?
Sharad Mahendra
executiveNo, look, definitely, everything is in place. Sure, given the kind of bidding space that now constitutes the bidding, with the quantum rising as we move ahead, this will definitely be one area, but we have already lined things up knowing what my FY 2025, FY 2026, FY 2027 is going to be. We are already handling the whole supply chain — not just the transformers, but also on the execution side or any other aspect when it comes to finishing the project well in time.
Ketan Jain
analystGot it. Thanks, and best of luck to you.
Sharad Mahendra
executiveThanks. I really appreciate it.
Operator
operatorThank you. Since there are no more questions, I'd now like to pass the conference back to management for their closing remarks.
Sharad Mahendra
executiveThanks. I appreciate all of you being on today's call. As I mentioned, I've gone through the majority of the items, but yes, my IR team is available should any additional follow-up questions come up afterward or if any further information is needed. We ask that you please send a note to our IR team. We will certainly get back to you on that. Thanks again very much.
Pritesh Vinay
executiveI appreciate that.
Operator
operatorThanks. That brings us to the end of this conference for JSW Energy. We appreciate everyone for being with us. You can go ahead and disconnect your lines now.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete JSW Energy Limited transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →This call discussed
For developers and AI pipelines
Programmatic access to JSW Energy Limited earnings transcripts and 132,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in JSW Energy Limited or any ticker on your watchlist.
StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.