operatorHello, and thanks for staying on the line. You're welcome to the NKT Q2 Report 2022. Right now, everyone is in listen-only mode. Following the speaker's presentation, we'll hold a question and answer session. If you'd like to ask something during that session, press star one and one on your phone. An automated message will then confirm that your hand is raised. Please note that this conference is being recorded today. I'd now like to hand the conference over to today's speaker, Alexander Kara. Please go ahead.
Alexander Kara
executiveThank you. Good morning, everyone, and I appreciate you taking the time to join us for our Q2 results. Joining me in the room is my CFO, Line Andrea Fandrup. Also here is Basil Garabet, the CEO of NKT Photonics. This will be Basil's last meeting for the results. Let me just say a few words. Basil joined NKT in 2015 and grew NKT to the position we're in today. He was clearly instrumental, and welcome, Basil. Today you have the opportunity to ask him some final questions if you have any. Welcome, Basil. Let's move to the key message for Q2 and the highlights. In Q2, we achieved organic growth of 11%, which was driven by good performance in the Solutions application, where service and accessories had low revenue and EBITDA compared with a strong Q2 last year. We had a record high backlog because we were finally able to book the Champlain Hudson Power Express project in the U.S., which brings power from Canada to New York, and the South Auckland second system. On the basis of this backlog and the new project we have been awarded, we have decided to strengthen our manufacturing capabilities in NKT Solutions, and we are expanding our high voltage production capability in Karlskrona.
Alexander Kara
executiveAs you're aware, we've also signed an agreement to divest NKT Photonics, and that represents the last stage in the effort to concentrate NKT entirely on its core operation, the power cable business. Looking at NKT and this divestment: on 24th of June, NKT signed an agreement to sell NKT Photonics to Hamamatsu, a Japanese company. Completion of the transaction depends on regulatory approval, and we anticipate it occurring later in Q1 2023. For NKT Photonics in Q2, revenue grew 18%. EBITDA came in at -EUR 5.8 million, which took a negative hit from EUR 6.1 million in transaction costs tied to the divestment. That produced a net result from discontinued operations of -EUR 9.1 million in Q2 2022. Starting in Q2 2022, NKT Photonics is reported as a discontinued operation and as an asset held for sale. Turning to how things developed in Q2: we saw positive financial performance in the Solutions business line, where we delivered on orders won over recent quarters and years. That was a favorable development. We also increased revenues in application, while EBITDA was negatively affected by rising costs, and we might return to that later.
Alexander Kara
executiveIn Service and accessories, both revenues and EBITDA came in lower, and that's against a very strong comparison from the same quarter last year. During Q2, we incurred some temporary cost increases in the accessories business. Looking at H1 overall, we grew from EUR 640 million to EUR 700 million, which is 9% for the half year, and on EBITDA we went from EUR 73 million to EUR 80 million, which is 11.4%. Turning to the Q2 Solutions results, we've stepped up activities and worked on various projects, each using a different technology. To name just a few: East Anglia THREE is an MI technology project. BorWin, Dogger Bank, Shetland, SuedLink 525 kVDC. We also worked on an AC project, Ostwind and Troll, where Troll is for power from shore. So it's a good mix of projects across different technologies. In April, we commissioned the power cable for Hornsea 2, an offshore wind farm in the U.K., which will deliver clean electricity to 1.3 million households once it's in operation. On the back of all this execution, we have good utilization — in fact, full utilization of the Victoria in Q2, with various installation activities. The high backlog, along with the contract awards for the Solutions extension in Champlain, as we mentioned, are what make the decision to expand production capacity in Karlskrona.
Alexander Kara
executiveAll in all, during Q2 we grew organically by 22%, and EBITDA rose to EUR 30 million from EUR 23 million — a result we consider satisfactory. Turning to the markets, in the second quarter of 2022 we were awarded two large projects. The second of these, SuedOstLink, runs parallel to the first order from 50Hertz and forms part of the energy transmission link from the North Sea down to southern Germany. We also received the Champlain Hudson Express. SuedOstLink came in below EUR 700 million, while Champlain Hudson exceeded EUR 1.4 billion. Looking at the total market for the first half of 2022, it stood at roughly EUR 5 billion, and that figure includes both the SuedOstLink extension and Champlain Hudson Express. Following the close of Q2, NKT announced a turnkey supply deal for the East Anglia THREE offshore wind farm project in the U.K. That one isn't in the backlog yet, and it depends on the customer's final notice to proceed plus a final investment decision. On the whole, a strong Q1, with high voltage project awards of EUR 5 billion. As for our backlog, it has risen from EUR 2.8 billion at the end of Q1 to EUR 4.6 billion at market price, or EUR 4.0 billion based on the tonne of metal price.
Alexander Kara
executiveTo put it in approximate figures, that's a EUR 2.1 million rise in market price and EUR 1.85 million in the per-tonne metal price. Out of the backlog, we anticipate executing roughly 10%, so 10% of EUR 5.4 billion. Over on the right-hand side, you can see the projects we're working on — offshore wind and interconnectors — and we've now added Champlain Hudson and SuedOstLink as well. Turning to application, revenue grew in Q2, with contributions coming from the various geographies where we operate. Within product segments, revenue growth came mostly from high inflation and chiefly from price — that is, price increases — and less from volume. Even with the higher revenues, operational EBITDA has declined, and that decline stems from higher material costs in application on the metal side. We're collaborating with customers to raise prices and working on the contracts to better the situation, and we're also working with our supply chain to secure the future. Across the market overall, we're seeing a slowdown in certain segments, especially the construction-based segment where we deliver cables. All in all, growth — but driven by price increases — with organic growth of 16% and EBITDA of EUR 7.2 million versus EUR 7.6 million.
Alexander Kara
executiveIn Q2, service and accessories fell to EUR 47 million from EUR 65 million, while during last year we had a number of repair jobs. Beyond the decline in repair job revenues, service performed well in the rest of the business. Repair jobs, naturally, matter when it comes to revenue and EBITDA contribution. On the accessories side, higher temporary costs are affecting us, stemming from the footprint transfer of high-margin accessories from Cologne to Alingsås. Overall, I need to say this plainly: EUR 1.8 million of EBITDA in service and accessory is not satisfactory and must be improved. With that, I’ll hand things over to Line, who will walk through the financial details.
Line Fandrup
executiveThank you, Alex. I'll give the complete overview of the income statement here and recap what Alex mentioned as well. NKT keeps up the strong growth trend from 2021, when we achieved 15% growth year-over-year and actually won with 7%, and now for Q2 we're at 11%. For the quarter, this came mainly from Solutions and Applications. NKT recorded a somewhat lower operational EBITDA this quarter. Just to point out the comparison base of exactly how we finished with services and accessories here, where the 2021 service and accessories business line performed very strongly. A minor decline in absolute terms, only to some extent. For the first half, operating EBITDA stands at EUR 80 million, versus the first half of 2021, when we were at EUR 73 million. Regarding the result from discontinued operations, we're presenting Photonics as Alex walked through, with solid growth and a negative EBITDA mainly because of transaction costs. If you look at our FTE numbers against the full-year comparison base from when we ended 2021 through now, you'll see the underlying FTE growth driven by, of course, the expected growth ahead of us and the expansions in Cologne and Karlskrona, but also by some of the footprint changes in our factory layout.
Line Fandrup
executiveNow turning to a highlight on the balance sheet. We observed a significant strengthening of our working capital position, going from EUR 35 million of working capital in Q1 to a very positive availability of EUR -200 million in Q2. That is largely attributable to the Solutions business line, the phasing of milestone payments, and then it relates to the order backlog and the recent awards. This had a positive effect on our capital employed position for the quarter, and our ROCE, also together with the improvement in earnings, stands at 4.1% versus 3.4% at the end of 2021. Naturally, we keep monitoring this key performance metric for the company's return on capital employed. Net interest-bearing debt went down from Q1 to 2.4 in Q2, which left the quarter at 0.2x EBITDA. Yes. Also just a note on the hybrid: you likely saw in our press release that we redeemed the EUR 150 million hybrid on 12th September. NKT does have sufficient funds in place to repay the security, and we are, of course, looking at future financing capacity to ensure we have enough flexibility for the growth ahead, the strong backlog, and even the activities we see, while at the same time securing the right financing structure for the company.
Line Fandrup
executiveNow looking at cash flow for the quarter, it got a lift from how working capital stood, which left us with positive cash flow from operating activities. Investment is still running at roughly the same level as the same period a year ago, reflecting the expansion programs and the Solutions. As you can also see from the key highlights and the report we published, there's a further expansion in Karlskrona of about EUR 90 million for the next phase there. Free cash flow for the quarter comes in at EUR 88 million. Our financial outlook for 2022 stays unchanged, at EUR 1.35 billion-EUR 1.45 billion in revenue and operational EBITDA of EUR 130 million-EUR 155 million. Given where geopolitical and macroeconomic dynamics stand right now, there are some uncertainties tied to the second half. So we're keeping it as is. To repeat the key messages from Q2: organic growth of 11%, mainly driven by Solutions and applications, while sales and accessories, as expected, declined from the very favorable 2021. Order intake in Q2 was very strong — a record — with a correspondingly very high order backlog, which gives us good visibility into the future. We'll expand high-voltage production in Karlskrona further, and in this quarter we also announced the divestment of NKT Photonics to a good future home, where they'll maximize the company's potential.
Line Fandrup
executiveWith that, I'll turn things over for questions and answers. Operator, we're ready to take questions from the audience.
Operator
operatorThanks. Just a quick reminder that to ask a question, you'll need to press star one and one on your phone and then wait for your name to be announced. So again, if you'd like to ask a question, please press star one and one on your telephone. We're now going to take our first question. Please stand by. Today's first question comes from the line of Massimiliano Severi from Credit Suisse. Please go ahead. Your line is open.
Massimiliano Severi
analystYeah, hi, this is Massimiliano at Credit Suisse. Thanks for taking my question. My first one is about the Karlskrona expansion — could you perhaps say a bit about how the EUR 90 million of CapEx will be phased, and what that means for NKT Solutions' space capacity in 2024 and beyond?
Alexander Kara
executiveYes, I appreciate the question. Regarding that EUR 90 million, most of it will be spent during 2023, with a smaller portion this year. Once the capacity expansion is finished, the effect will come to roughly EUR 2 net million starting in 2024 and continuing after that.
Massimiliano Severi
analystThanks. For my follow-up, could you perhaps discuss the guidance? Would it be reasonable to say that, assuming supply chains don't deteriorate beyond where they stand right now, you ought to land at the upper end of the guidance? Or is the softer construction outlook expected to be a significant drag, possibly pushing results well below that top end of the guidance?
Alexander Kara
executiveLet me share a few thoughts on the supply chain. The supply chain—what we're looking at here—mainly affects the application business and the construction portion of the cables, the ones that deliver goods to the construction business. Here's what we've observed. Let me add a bit more detail on this. What we've observed is that we exited Russia for material procurement, aluminum, and also pulled out of all sales activities in Russia. We've had to move to new suppliers in the market. We've also noticed in the market that certain metal suppliers, aluminum especially, have experienced enormous price increases, cost increases on energy and gas, and some have even reduced or halted production of their output. We need to find a new supplier, and that means looking outside of Northern Europe or even Europe. This has resulted in higher costs, particularly for aluminum, because of transportation, but also because of aluminum premiums. This is an effect we're trying to correct through negotiations over price increases and discussions with our customer. Also, for price increases, you must be able to change price based on your contracts and on the terms and conditions that are defined. We're working on price increases with the customers.
Alexander Kara
executiveWe also examine the supply chain and how we can keep it secure moving forward. In Q2 we saw this cost rise sharply, and a price increase was not enough to offset it. This won't be finished in Q3. It will carry into Q4, and we'll work on correcting these actions. That's one aspect within Solutions. Another thing we're seeing in Solutions is a slowdown in certain market segments, tied to the construction side of the cable. Here we have two effects: the slowdown and the rise in aluminum, particularly within Solutions. So that's the situation for Solutions. On the other side, there's Service. As I mentioned, Q2 was unsatisfactory for us in Service and Accessories. Part of it is higher accessory costs, but it also depends on the Q3 or Q4 results, or the second half, phrased that way, on whether you have any repair or repairs. We think we've hit the bottom in accessories from the footprint change and believe it should rise. Here too, as I said, the contribution from repair jobs matters. We also face some uncertainty in the service business.
Alexander Kara
executiveNow, regarding the Solutions side, as you're aware, project phasing shifts from one quarter to the next. There can also be changes. Given this application, service, and Solutions, we arrived at overall uncertainty in the market. We reached the conclusion not to upgrade our guidance.
Massimiliano Severi
analystThanks, that was very thorough. My final question concerns paying back the hybrid and the Photonics divestment. You've now announced DKK 90 million of CapEx in cash krona, yet you still have over DKK 100 million remaining from the Photonics disposal. What I'd like to ask is whether you can comment on what you see as the strategic priorities, and perhaps also on the hybrid — do you expect it to be fully refinanced, or only partly, with some of it used to reduce leverage? Thank you.
Line Fandrup
executiveOh, thanks for that question, Maximilian. I hope I caught everything you asked, but on the hybrid and how we're thinking about it, we see a really strong, let's say, future for NKT when it comes to the backlog. We've now called the hybrid, but we also see a scenario in which issuing a new hybrid would be the right way to finance NKT's growth going forward, making sure we have a capital structure that fits best for the years ahead. That's being discussed in the meeting right now, and I think we view a new hybrid as a route that is definitely something to consider.
Massimiliano Severi
analystAppreciate it.
Operator
operatorThanks, and we'll move along to the following question now. Just a moment, please. The next one is from Daniela Costa at Goldman Sachs. Go right ahead — your line is open.
Daniela Costa
analystHello, good morning everyone, and thanks for taking my question. There are two things I'd like to ask about. First, Rikke, given these new CapEx investments, perhaps you could comment a bit on the cadence of free cash flow you anticipate over the years ahead. Will it be negative, I suppose? Do you expect it to come in negative during 2022 and 2023, and then reap the benefits afterward? Or might you begin reaping some benefits slightly earlier? And tied to this new investment, why did you choose Karlskrona rather than, say, making some investment in the U.S.? That's the first part. For the second part, I wanted to ask about the margins on the backlog. I believe your peers have said recently that margins in the high voltage segment — I think Nexans said they could range between 17%-24%, leaning more toward the submarine side. They've noted that terrestrial was somewhat lower. Could you comment a bit, given Champlain and Germany, their terrestrial contracts — are those more toward the lower end? Do you view this kind of very high teens as a long-term possibility for NKT? If you could offer us some commentary there, thank you.
Line Fandrup
executiveAppreciate that, Daniela. I'll take your first question and then pass things along to Alex and a few of the others. On the new CapEx in Karlskrona, as you're aware, we don't provide guidance on cash flow. Clearly, once integration is complete, this ought to be a strong contributor going forward for NKT, and that also means it will contribute cash. What we're certainly examining — and you follow this as closely as we do — is a market that's booming, even with what you might call limited capacity when it comes to executing every project, since customers keep coming to us, and at certain moments we're simply unable to accept additional orders. Broadly speaking, NKT's capacity is something we keep evaluating on an ongoing basis. So we'll see a future in which this new investment naturally adds to cash generation, and also one in which we'll keep weighing what steps to take next so that NKT keeps growing. Over to you, Alex.
Alexander Kara
executiveThe question was about the rationale for putting money into Karlskrona and growing there rather than in the U.S. As you'll notice, EUR 90 million — that CapEx isn't for a whole factory. Through that EUR 90 million, we're largely making use of what already exists, civil buildings that are already constructed, especially the port that we've just completed. Here we get the greatest returns on the investments. Practically speaking, as I said earlier, with that EUR 90 million, we're able to boost revenues starting in 2024 and going forward by roughly EUR 200 million. Within, say, a bit over a year. Relative to the revenues, the CapEx is fairly low, and it's quick. That's the reason behind the Karlskrona decision. And naturally, we also have delivery commitments from the complex that we hold in hand. Now, on the question about margins, the 17%-24%, if you look at our Solutions business, we have an onshore operation and an offshore operation. Where we said, we shifted the lower end of the high voltage onshore business to 25 — that's meant to enhance profitability. Then we continue working on further improvements in the factories. As we carry out the projects with better margins, which we're seeing arrive thanks to the improved supply-demand balance, we also anticipate growth rising along with the margin over time.
Alexander Kara
executiveYeah, that's right. I think that hopefully addresses your question.
Daniela Costa
analystMy apologies — may I jump in briefly with a follow-up on the responses to both of those questions? You brought up the EUR 200 million of incremental sales on Solutions. Could you remind us, since some incremental sales were already coming from the earlier factory expansion you announced, I think in mid or late 2020? At full capacity — in the past, I believe you used to guide to close to EUR 1 billion. Once every factory expansion is complete, what level should we now regard as full capacity?
Alexander Kara
executiveRight. So back in 2021, we made the decision to add capacity. Solutions was running at roughly EUR 700 million to EUR 750 million. We launched the initial investment, which we announced at EUR 150 million. On item 49, we mentioned a step up to EUR 1.1 billion starting in 2023. So EUR 1.1 billion from 2023, and then from 2024 — we said now that we have that EUR 90 million investment — that takes us to EUR 1.3 billion a year in revenue.
Daniela Costa
analystYes. Naturally, price plays a significant role in this mechanism as well. That point is already included in what Alex mentioned.
Alexander Kara
executiveRight. Pricing plays a major role. Naturally, the real question is what share ends up turnkey versus supply only. These are approximate figures.
Daniela Costa
analystYeah, sorry, just to make sure I've got this right on your second answer, since I'm not certain I fully followed. Would you say terrestrial carries a thinner margin than submarine? And do you go along with the ranges? I believe Nexans has said something like terrestrial sitting in the low teens, while submarine is more in the high teens to 20%. I'm not after a specific figure from you, just wondering whether those broad ranges ring true when we consider the mix?
Alexander Kara
executiveI mean, when we’re talking about terrestrial land cable — AC onshore land cable — traditionally it carries a smaller margin compared with a sea cable. And here, demand is rising going forward for 400 kV AC in Germany. That could have a favorable effect as well. Broadly speaking, AC onshore is lower. When it comes to DC 525 Kv, you’ve seen that we announced the SuedOstLink extension. On that, I’d say margins aren’t necessarily lower than what you’d get on a sea cable.
Daniela Costa
analystGot it. Thanks so much.
Operator
operatorThank you. We'll move on to the next question now. Please hold. Our following question is from Akash Gupta at JPMorgan. Go ahead. Your line is open.
Akash Gupta
analystYes. Morning, everyone, and thank you for joining. My opening question also follows up on project margins. I see that in Q2 you had a fully utilized vessel, but I'd like to hear about how capacity utilization currently stands across the entire solutions business, covering every aspect of manufacturing and installation. Could margins improve going forward from full saturation in a way that perhaps didn't apply in Q2? Put simply, I'm trying to get a sense of how much better future solutions margins can become through price mix, and whether utilization might also be a factor compared with last quarter?
Alexander Kara
executiveThat's a substantial and multifaceted question, Akash. Well, clearly, utilization has an effect on the outcome, and so does the mix across the factories. Utilization is going up, our backlog is high, and therefore we still see potential, for instance in 33 kV AC, for 2022 to 2023 and beyond. On installation, naturally with greater volume, both in Karlskrona and in extrusion, plus more turnkey projects, we also get better utilization of the Victoria, which is a help to us. Utilization was good during the first half, and we're seeing somewhat less in the second half. All in all, the higher revenues from turnkey consequently and logically affect how well utilized our vessel is.
Akash Gupta
analystAppreciate it.
Alexander Kara
executiveI think that we do.
Akash Gupta
analystYeah.
Alexander Kara
executiveSure, Akash — go ahead.
Akash Gupta
analystI had another question about applications margins. I think you did a good job explaining that there are certain contracts and that you saw some cost increases. What I'd like to understand better is the timing of when you'll be permitted to revisit or raise pricing—for instance, when those contracts come up for renewal. Perhaps you could share more about when accessory margins are expected to improve going forward.
Alexander Kara
executiveAs you can imagine, unlike our Solutions business, we have hundreds of contracts, and their terms and conditions differ. That's not something we can fix quickly. We raised prices substantially in Q2. Practically all of the revenue increase came from price, while volume was flattish or up slightly. We can raise prices, but there are limits too, and those limits come from the contracts and the terms and conditions we have with the customer. We're working on that, and at the same time we see room to improve on the procurement side, bringing materials to more normalized levels, which of course would then help us. Also, we're now working on the footprint movement as well. Those aren't yet, let's say, activated. That's still ongoing. Overall, we're working on it, but it will drag into Q3, and we're not sure when we're through, to be honest.
Akash Gupta
analystThanks. One last quick item from me: water levels on the Rhine have been back in the news over recent weeks. Would it be fair to describe that as a possible headwind for the second half as well, and is it already baked into the guidance? Or are you in a stronger position now than a few years ago, when lower water levels raised your transportation costs?
Alexander Kara
executiveNo, the Rhine River won't have any effect on us in Q2, since we don't have any cable loads coming out of Cologne. Ostwind 2 has been delivered. There will be no impact whatsoever. Unfortunately, the impact is only on nature and the fishes.
Line Fandrup
executiveYeah, and just to add to what Alex said regarding Q3, but—
Alexander Kara
executiveMy apologies — that should be Q3 and Q4.
Line Fandrup
executiveOur position is stronger now, since we have — how should I put it — a barge that really deals with shallow water more effectively than what we had back in 2018.
Alexander Kara
executiveRight, that's accurate. Yeah. Glad you brought that up. There's a barge we've got that's built for shallow water on the Rhine, so it can handle that river. Like I said, we don't have any load outs during this year's second half.
Akash Gupta
analystTo put it plainly, that isn't a guidance risk for this year.
Alexander Kara
executiveNo. That's zero risk.
Akash Gupta
analystMuch appreciated.
Operator
operatorThanks. Just a reminder — to ask a question, press star one and one on your phone's keypad. That's star one and one to ask a question. We're ready for our next question now. Please hold. Our next question is from Claes Westerlind at Nordea. Go ahead, your line is open.
Analyst
analystThanks, and I hope you’re able to hear me.
Alexander Kara
executiveYes. Did you have a question for me?
Analyst
analystYes, I actually do. First, I want to express my appreciation for the years at NKT and the many quarterly presentations, Basil. I hope you're very happy with the company's new owner. Not least, now you know whether you were the prettiest person in the bar. Absolutely. Yes. Yeah. We definitely were the prettiest girl in the bar. Good to hear. Yes. Very good. Okay. Turning to the cable activities. Alex, perhaps you could offer some commentary on the pipeline, both for the nearer term, so 2022, and also the pipeline for next year. That would be my key question.
Alexander Kara
executiveThe pipeline — you're referring to Solutions, I assume, right?
Analyst
analystExactly. Exactly.
Alexander Kara
executiveLike I mentioned earlier, in the first half of the year it was EUR 5 billion. After that came the U.K. CFD round, and there we managed to secure a contract with them for East Anglia THREE. Naturally, the rest — roughly 1.5 to 5.5 gigawatts — still has to be awarded. As you're aware, certain contracts may involve pre-agreement, and some customers might play the market. We obviously see some opportunities here in the U.K. CFD, and a number of other projects are coming up soon. The figure of EUR 7 to 8 billion on average across 2022, 2023 and 2024 holds for every segment — interconnectors, offshore wind, power from shore. There's no shortage of opportunities. That's healthy for the industry. It means supply and demand have shifted, and we're now in a position to be far more selective. The more projects there are in the market, the more we're able to handle them, you know. I'd say that's enough for the entire industry.
Analyst
analystWhich projects would you turn down, and is that only a matter of timing and price? Or does being more selective mean something else — what does that actually mean?
Alexander Kara
executiveRight, timing matters, obviously — you have to have production capacity on hand. If not, that works only when the customer agrees to shift their schedule. It also hinges on the other cable companies, the competitors, and whether they're able to deliver. Timing and capacity availability are prerequisites, unless the customer can move things around. Then comes price. There are enough projects out there that we can say, all right, this price looks attractive. Naturally it also depends on what the contract conditions are, and, yes, those are the two key criteria.
Analyst
analystRight, that’s clear. One last thing about a hybrid, Line — you said there’s a situation in which you might issue a new hybrid. What situation is that?
Line Fandrup
executiveI think what we're really weighing up here is where the market stands, right? We referred to that hybrid as being in place when it was also moving up to a coupon above 10%. There's obviously, let's say, a threshold of discomfort when it comes to funding NKT's future through a hybrid. Our view is that the hybrid, assuming favorable market conditions, might serve as a solid means of financing the growth that lies ahead for us as well.
Analyst
analystSo that would mean, if you were going to build a greenfield — a brand-new factory. Is that what you're referring to?
Line Fandrup
executiveActually, no — it's a bit wider in scope than that. It isn't a trigger tied to us waiting for FID. What it really involves is ensuring the financing and the appropriate capital structure are in place for NKT from the point when the hybrid eventually gets called on September 1. By then, our aim is to have either a hybrid or another form of financing set up, so that we can keep carrying forward the strong momentum we currently have.
Analyst
analystOh, sorry — I just want to make sure I've got this right. So does that mean that, absent a new hybrid, your balance sheet isn't strong enough to land some of these large orders?
Line Fandrup
executiveNo, that's not what it means when you look at the whole picture in a linear way. What it means is that we foresee a future in which NKT has plenty of opportunities to grow and to keep the momentum going, and we want to secure that. If and when we come out with a new hybrid, that's what it's for — securing that. It isn't meant for a trigger event, and it isn't meant to stand alone as a way to secure things. We have a stronger balance sheet.
Analyst
analystAll right, thank you.
Operator
operatorThanks. There’s time for one more question. Please hold. Massimiliano Severi of Credit Suisse has a question. The line is yours — go ahead.
Massimiliano Severi
analystHi, thanks for the follow-up. This is quite a broad question. When I think about what it costs to transport a cable, first of all, could you give us a sense of what portion of a project's total cost would go toward shipping a cable from Europe to the U.S.? And the follow-up would be: if you don't open a factory in the U.S., do you think that in the future you'll still be competitive enough to transport a cable from Karlskrona to the U.S., even after your competitors have opened their U.S. factories? Or would that basically mean you'd focus on Europe rather than on the U.S.?
Alexander Kara
executiveOkay. So when you look at transportation, what you really have to examine is what a vessel costs, or its day rate, and then you factor in how many days are required to get from Karlskrona over to the U.S. You also have to think about this — even if you don't own a factory, just take our competitor as an example. Say their vessel is sitting in Europe right now and they've got a job in the U.S.; they'd still have to sail an empty vessel across to the U.S., load the vessel up, load the cable there in the U.S., and then bring it to the transporter. It's unlikely that a competitor would, at any given moment, maybe have a permanent vessel sitting on standby in the U.S., since they've also got projects not just in the U.S. — but that's of course a bit of an assumption. You'd need to work out the vessel's cost, or its price at the day rate, times some number of days, and then you'd have to set that against the overall size of the project. Obviously a small project connecting two islands — I don't know, let's just say EUR 10 million or so — wouldn't make sense.
Alexander Kara
executiveThat makes sense. Still, when a project runs into the several hundred millions, maybe transportation expenses can get folded into the total package. Naturally, you also have to consider the downside. If your factory sits in the U.S., you must make sure you've got the load as well. Each option comes with pluses and minuses. Even so, we believe we're able to deliver projects in the U.S.
Massimiliano Severi
analystThat’s great. Thanks very much.
Operator
operatorThanks. Right now, we don’t have any more questions. I’ll turn the call back over to you.
Alexander Kara
executiveAll right. Thanks a lot for taking the time to hear about our results, and I wish each of you a good day — we'll speak again soon. Bye-bye.
Operator
operatorThanks. That brings us to the end of today's conference call. We appreciate everyone joining us. You can go ahead and disconnect now. Speakers, please remain on the line.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete NKT A/S transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →This call discussed
For developers and AI pipelines
Programmatic access to NKT A/S earnings transcripts and 132,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in NKT A/S or any ticker on your watchlist.
StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.