Noelle Dilts
executiveThanks, everyone, and good morning as we kick off this webcast and conference call covering Sterling Infrastructure's second-quarter 2024 earnings. It's a pleasure to be with you, and joining me to go over what we achieved are Joe Cutillo, our Chief Executive Officer, and Chief Financial Officer Sharon Villaverde. Joe is going to start things off by walking through the business and how it did during the quarter. After that, Sharon will take you through the financials and our guidance, and then Joe will come back to share his view of the market and the outlook for the entire year. Following that, we'll take your questions. Just a quick note that slides are available in the investor relations area of our site, and those slides lay out the specifics of our revised financial guidance. Before I hand things to Joe, let me go through the safe harbor statement. Today's conversation might contain forward-looking statements, and what actually happens could end up materially different from what gets said today. For a fuller picture of the risk factors that might impact these projections and assumptions, please look at Sterling's latest 10-K and 10-Q filings. No obligation is taken on by the company to revise forward-looking statements because of new information, later events, or anything else. Also keep in mind that management might mention EBITDA, adjusted EBITDA, adjusted net income, or adjusted earnings per share during this call, and none of those are financial measures recognized under U.S. GAAP. As SEC rules and regulations require, you can find reconciliations of these non-GAAP financial measures to the closest comparable GAAP measures in the earnings release we put out yesterday afternoon. I'll now hand the call over to our CEO, Joe Cutillo.
Joe Cutillo
executiveThanks, Noelle. Morning, everyone, and I appreciate you being on the call for Sterling's Q2 2024 earnings. What we posted in the second quarter shows how dedicated we are to producing robust earnings growth and cash flow for those who hold our stock. During this quarter, we achieved earnings per share of $1.67, which is a 31% rise compared to the same period a year ago, marking a fresh record for a second quarter. Because we kept emphasizing margin improvement, gross profit margins climbed past 19%; operating income rose 20% while revenue increased 12%, as we keep moving our mix toward services with higher margins. We're experiencing powerful tailwinds in the markets we serve, and bidding activity is still quite robust. Backlog when the quarter closed came to $2.1 billion, which is 21% higher than a year earlier and 2% above where it stood at the start of the year. Combined Backlog, which gives a broader picture of our awards, reached $2.45 billion, up 2.2% versus the previous year. For this quarter, our Book-to-Burn Ratio for Combined Backlog exceeded one, and we still enjoy excellent visibility into the pipeline of opportunities that lies ahead. Our forecast is actually stronger than what our backlog figures show. As our work moves toward big, multi-phase projects in transportation as well as E-Infrastructure, we gain better visibility into upcoming phases of work. Even though winning those future phases isn't guaranteed, historically we've had a strong likelihood of doing so. This pipeline of high-probability work now amounts to more than $500 million. We posted yet another excellent quarter for generating cash, with operating cash flow hitting $121 million. Our balance sheet looks very healthy, and our net cash position now stands at $211 million. We're actively looking for acquisitions that would fit well with our solid platform and speed up growth. The Sterling Way represents our pledge to look after our people, our environment, our investors, and our communities as we construct America's infrastructure. That continues to be our guiding principle while we expand and diversify the business. I want to thank each of our employees personally for helping us turn in another outstanding quarter. Now I'd like to talk about our results for the second quarter of 2024. In E-Infrastructure, our biggest and most profitable segment, operating profit increased 20% as operating margins widened by more than 480 basis points, hitting 21.4%; this impressive margin growth shows our ongoing emphasis on large mission-critical projects and superb execution. Since the small commercial and warehouse markets have weakened and turned less appealing from a margin standpoint, we've chosen to redirect our efforts and resources toward the large project markets, which include data centers and manufacturing. Although this pivot is affecting top-line growth, we think it's the optimal and most efficient way to use our resources as we work to maximize returns. Total E-Infrastructure revenue fell 7% in the second quarter, which mirrors this rotation. Our data center revenue, which now accounts for more than 40% of our E-Infrastructure backlog, expanded by over 100% during the quarter. Small commercial and warehouse work dropped by more than $30 million compared with the second quarter of 2023. When it comes to the manufacturing market, we had a tough revenue comparison on our hands because a big project kicked off in early 2023. Projects like this usually see activity weighted toward the front end, then it settles down for the rest of the project's duration. This project's work will keep going into early 2026, though at revenue levels somewhat below the peak quarters of Q2 and Q3 of 2023. E-Infrastructure awards came in at $148 million for the quarter, which pushed backlog to $868 million — roughly even with the same period a year ago, and up 7% versus the start of the year. Once again, the data center market drove awards more than anything else, since customers are hurrying to construct the capacity that technology advancements, AI included, demand; we keep drawing on resources throughout our business segments to grow E-Infrastructure in the Rocky Mountain region, where three sizable data center projects now sit. We're still seeing gains in the Northeast, and after the quarter closed we secured some further data center awards in the Mid-Atlantic. With our work increasingly tilting toward large projects, our pipeline of high-probability future work has grown, giving us solid visibility into 2025 and 2026. Now on to Transportation Solutions. Revenues rose 54%, all of it organic, while operating profit climbed 57%. Margins widened 11 basis points year over year, hitting 6.6%. Our markets are the best in our company's history, and the margin opportunities look very appealing. We closed the quarter with Transportation Solutions combined backlog at $1.5 billion, up 5% from the second quarter of 2023. Second quarter awards for Transportation Solutions reached $88 million, with unsigned awards of $309 million. Still, the situation is better than backlog and unsigned awards suggest. In the quarter, we won the initial design for several large Progressive Design-Build highway projects. That design work and backlog account for just a small portion of what these projects are expected to be worth in total. As with E-Infrastructure, this brings very high probability work into the pipeline that the awards in our backlog don't capture. Shifting to building solutions. Total segment revenue fell 2% in the quarter, even as operating income rose 2%. Quarterly results differed across our markets and geographies. Revenue at our residential concrete slab business dropped 7%. Heavy rainfall in Texas largely caused this decline; on top of that, builders struggled with the availability of developed land. Builders took up much of the available capacity during a very strong first quarter and are now trying to catch up. PPG keeps performing very well, posting pro forma organic growth of 8% along with strong margins. Our commercial business was down $14 million from the prior year period, which matches what we expected. Our segment's operating margins are getting a boost from the ongoing shift in mix toward residential slabs and plumbing, and they came in at 12.7%, up 57 basis points; having said that, I'll hand things over to Sharon so she can walk you through the quarter in greater detail along with our guidance for the full year. Sharon?
Sharon Villaverde
executiveThank you, Joe, and good morning to everyone. I want to walk you through a few specifics from our financial results, starting with the backlog figures. At the close of our second quarter, backlog came in at $2.1 billion, which represents a 20.9% gain versus the same period a year earlier. Backlog gross margin stood at 16%, marking a 50 basis point gain relative to last year's second quarter. This uplift was driven by a greater volume of E-Infrastructure backlog along with growth in both the size of transportation backlog and its margin. Unsigned awards for the quarter came to $347.2 million. We ended the quarter with combined backlogs of $2.4 billion, which is a 2.2% rise over the second quarter of last year and a modest sequential gain versus the first quarter of 2024, reaching a new all-time high. For the second quarter of 2024, book-to-burn ratios came in at 0.49x for backlog and 1.05x for combined backlog. The timing of awards tends to be uneven in our line of business, so it's best assessed across several quarters. On a year-to-date basis, book-to-burn ratios were 1.04x for backlog and 1.09x for combined backlog. Now moving to our second quarter income statement. Revenue reached $582.8 million, up 11.6% from the prior year quarter. Organic revenue growth came in at 8.4%. Consolidated gross profit for the current quarter was $112.7 million, which is 22.2% higher than the 2023 period. Gross margin rose to 19.3%, a 160 basis point gain versus the second quarter of 2023. This margin improvement mainly reflects gains in E-Infrastructure and transportation. General and administrative expense represented 4.8% of revenue during the quarter. G&A expenses rose by $3.8 million in the quarter, reaching $27.9 million. That increase is attributable to the PPG acquisition, general inflation, and growth. Operating income for the second quarter was $72.7 million, a 20.7% gain over the prior year quarter. Our operating margin improved 94 basis points, reaching 12.5%. Our effective income tax rate for the second quarter was 24.8%. We still anticipate that our full-year effective income tax rate will be roughly 25%. The net effect of all these items produced a record second quarter, with net income of $51.9 million, or $1.67 per diluted share — improvements of 31.4% and 31.5%, respectively, versus the second quarter of 2023. Second quarter EBITDA came to $87 million, an 18.3% gain over the prior year quarter. EBITDA margin improved to 14.9%, up from 14.1% in the prior year quarter. Cash flow from operating activities during the first half of 2024 was a strong $170.6 million, compared with $181.1 million in the prior year period. Cash flow used in investing activities during the first half of 2024 included $44.4 million of net CapEx. Given the significant growth in our transportation segment, we are increasing our expected net CapEx for the year to $60 million-$65 million. Financing activities produced a $56.8 million cash outflow, mostly from repurchasing $30.1 million of shares at an average of $100.70 apiece. We closed the quarter in a very strong liquidity spot: $540 million in cash alongside $328.9 million of debt, leaving $211.1 million in cash net of debt. On top of that, our $75 million revolver went untouched across the period. Given a strong first half and meaningful opportunities across every operating segment, we're lifting our guidance for the year. The updated ranges look like this: revenue between $2.15 billion and $2.225 billion, gross profit margin between 18.5% and 19%, net income between $175 million and $180 million, diluted EPS between $5.60 and $5.75, and EBITDA between $300 million and $310 million. With the breadth and strength of our business portfolio, our solid liquidity, and our comfortable one-time EBITDA leverage, we're set up well to seize further chances to create substantial shareholder value in 2024 and beyond. I'll now hand the call back to Joe.
Joe Cutillo
executiveThanks, Sharon. We look ahead and see many years of potential tied to rebuilding this country's infrastructure. Sterling plays an essential part in constructing the data infrastructure that makes modern life possible — the manufacturing production returning to the U.S., the roads, bridges and airports that link us together, and the houses we occupy. Within E-Infrastructure solutions, we expect data centers to stay strong, since today's capacity is just a small portion of what artificial intelligence and other new technologies will require. When it comes to manufacturing, we expect that across the rest of 2024 and into 2025, onshoring-related projects of mid to large size will proceed at a fairly steady rate. Looking toward 2026 and 2027, an enormous set of mega projects is coming. Planned chip plants would be part of that. These projects' scale and length are astonishing and will consume a substantial share of industry capacity. Because developing them is so complex, we think some time will pass before awards begin to flow. We expect e-commerce and small warehouse markets to stay weak in 2024, though preliminary activity in those markets for 2025 gives us encouragement. These dynamics underpin strong profitability growth potential across a multiyear stretch for E-Infrastructure; for 2024, we expect operating profit growth approaching 20%. In Transportation Solutions, we have now reached the halfway point of the present federal funding cycle, have accumulated more than 2 years of backlog, and keep seeing very robust bid activity. We think the market environment now allows us to maintain elevated growth compared with historical levels, provided margins hold at current levels or go higher. We have strong confidence that our transportation business will produce robust growth and margin expansion in 2024 and 2025. In building solutions, the business is well positioned for growth over a multiyear period... Our key geographies of Dallas, Houston, and Phoenix should keep seeing population growth, which drives demand for new homes. Beyond that, there is considerable runway for share gain in our Houston and Phoenix markets. Near term, builders confront challenges tied to affordability and land availability that could dampen activity. The largest variable in our growth outlook is interest rates. Any cuts down the road could speed up new home demand. We anticipate modest top-line growth in building solutions in 2024, with operating profit growth of over 20%; on the M&A front, we're working hard to find the right deals to grow the company and enhance our service offering. The E-Infrastructure market remains our top priority for M&A. We will stay patient and disciplined in our inorganic growth strategy. When it comes to share repurchases, we will keep taking an opportunistic approach. Because of our strong first half performance and backlog position, we are raising full year guidance. The midpoint of our new guidance would represent 11% revenue growth, 28% diluted EPS growth, and 18% EBITDA growth. Having said that, I'd now like to open things up so you can ask questions.
Brent Thielman
analystHey, thank you. Morning. Nice quarter. Joe, I get the change you're making in E-Infrastructure, clearly pushing, you know, really strong margins here. I suppose what I'm asking is, when do those projects and commercial, sort of, warehouse work start to become worth going after once more, even if they're, you know, possibly dilutive to the margins you're delivering right now?
Joe Cutillo
executiveYeah, so the change is, what I'd describe as, you know, kind of a short-term change, since margins in those commercial and warehouse projects have come down. When they return, so it's several factors, Brent. Clearly fewer projects are coming out; those projects lean heavily on interest rates. So we saw that beginning to slow from both an activity and a pricing perspective in the second quarter of last year, and it's simply carried on through today. Once those margins return to near or historical levels, combined with the better margins we've got in the other segments, we'll begin chasing those again. I'll tell you, we're heartened just by the talk about interest rates coming down and by some of the economic headlines; it definitely appears far more likely and perhaps better than, or larger cuts than, we expected. We've begun seeing, just within the last 30 days, projects we've known were sitting out there returning and having discussions about pricing and timing and that kind of thing. So we believe, realistically, around the first quarter of next year, we'll begin seeing those projects return; we won't move from 0 to 1 00 where we were instantly, but we're heartened by what we're seeing, and that's roughly what we expect.
Brent Thielman
analystAll right, that's good to hear. Thanks for that, Joe. One more question — regarding this pipeline of $500 million tied to those multi-phase projects. Joe, when you consider that figure over a longer horizon, can we think about how soon it turns into an actual signed contract? I'm just kind of curious, based on what you've seen, how that lines up with the backlog you report over time?
Joe Cutillo
executiveYeah, so here's the positive side and also the part that creates some confusion. From a strategic standpoint, we've been shifting in this direction gradually. In our E-Infrastructure business, the contracts are set up — as you're aware, Brent — with several phases. We recognize the full project might run into several hundred million dollars, though what gets released initially could be somewhere between $30 million and $50 million. Take a data center project as an illustration — it's pretty typical for that opening portion to land near $30 million, and from there it can expand to well beyond $100 million as the project moves along. The reason this works well for us, so it's clear to everyone, is that we put in a bid and finish one phase, then once the following phase is issued, we bid on that one and finish it too. If inflation jumps or material availability shifts, or market conditions change, we're committed for only a very brief window, and with E-Infrastructure we can adjust. On transportation, those Progressive Design-Build efforts are a bit murkier at the start. A design stage on a project worth several hundred million dollars could run $1 million to $2 million, and that's the figure we'd include. After design wraps up, we set the price for phase one; say the project totals $200 million — then $30 million or $40 million, possibly $50 million, arrives in that first phase. We carry that out, and a further $50 million comes in. As a result, pinning down a precise duration is difficult. The result is that our backlog stays steadier. We draw it all the way down, then add another $50 million, use that up, and add $50 million again. Because of that, it never appears as some huge gain. Had we injected $200 million on the first day, everyone would be thrilled by the jump in backlog. We're aware that $200 million exists, yet it only appears as $1.5 million, or it might appear that way. Beyond explaining the reason we lifted guidance, when we discuss the favorable conditions and the areas of strength we observe across the markets, we clearly possess greater insight into upcoming work than at any point before. Looking back a year and a half, that figure would likely have been closer to $100 million rather than $500 million. While I can't cite the precise amount, the increase has been substantial, and my expectation is that it will keep climbing across the coming 6 to 12 months.
Brent Thielman
analystAll right, that's excellent. Perhaps only the final item, Joe. I realize transportation can, by its very nature, be a bookings business that arrives unevenly. So, when you consider the schedules across the areas you mostly serve for the remainder of the year, do some solid chances exist to add to backlog during the second half?
Joe Cutillo
executiveYes, let me share this with you: during the past 30 days, I've given approval for us to pursue more work than we did across the entire first six months before that. That's roughly six months' worth for transportation. Plenty of projects, really strong projects, are coming to market. We feel quite optimistic not just about where backlog stands right now, but about where it's headed. And one thing, I think, gets overlooked when we discuss growth and expanding things — transportation is a textbook case, and infrastructure will show the same pattern. As we've consistently said, we kept transportation's growth restrained at roughly 3%-5% until reaching a margin hurdle; once we reached that hurdle, we expanded by more than 50% during this quarter; we can activate those growth rates incredibly fast. I believe people vastly underrate how swiftly we're able to expand the business. When margins are favorable, we will expand the business aggressively. Transportation is in that position. We'll keep expanding it and seize the market fully. Infrastructure will reach that point once more, likely early next year in our view, and we will speed that up tremendously when the moment arrives.
Noelle Dilts
executiveBrent,
Brent Thielman
analystThat's great. I'll follow up with you later. My apologies — please continue, Noelle.
Noelle Dilts
executiveRegarding transportation's backlog, if you examine either the official backlog or the one that's been signed, the awards appear weaker this quarter. Keep in mind, though, that during the first quarter we shifted quite a bit of work out of unsigned backlog and into signed backlog, and now we're in the process of rebuilding that pipeline. That's why combined backlog is actually the superior measure to consider for this quarter — it does a better job of capturing the underlying demand in that business.
Brent Thielman
analystThat's helpful. Thanks, Noelle.
Joe Cutillo
executiveThanks, Brent.
Adam Thalhimer
analystHey, good morning, guys. Great quarter.
Joe Cutillo
executiveThanks, Adam.
Adam Thalhimer
analystJoe, do you see any recovery possible in the Northeast next year?
Joe Cutillo
executiveYeah, I think, you know, looking at it... If you recall, our Northeast operation runs at a thinner margin than what we have in the Southeast. That's due to several factors — they handle a wider scope of work on those jobs, like sound walls, curb and gutter, and they lean toward more of the smaller projects, the kind we call $15 million type projects, and many of those really hinge on interest rates; the Northeast was the first and fastest to slow down last year. But just like in the Southeast, there are projects out there, we're seeing them, and so we believe they'll start coming out once interest rates begin to drop. But the other move we made with the Northeast that's about to really start paying dividends is that we've pushed them further down into the Mid-Atlantic. If you remember, for several years we've been asked to go into the Mid-Atlantic. We haven't had the capacity for projects of that size. Now that we've freed up some capacity, we've expanded down into the Mid-Atlantic. We've won a couple of very nice jobs after the quarter ended that are data centers, and one's gonna be a manufacturing one. It's gonna offset that small business, and that small business will come back next year.
Adam Thalhimer
analystAll right. Could you also speak to the data centers you're observing at present? Do they come in bigger than those from 12, 18, or 24 months back?
Joe Cutillo
executiveYes, that pattern is still holding. You need to keep the markets in mind. In the past, if you considered Virginia — and Dallas was another example — those were extremely robust data center markets, but each was just one building with a small footprint; those markets are continuing to add buildings, right? So when we build a data center in Virginia, it isn't a job worth several hundred million dollars; it's closer to a $40 million job or a $20 million job, based on which one it is. Beyond that, the forces pushing this are power and water, and those are what drive these data centers farther out into rural areas. Once they reach rural areas, they discover they're able to purchase bigger parcels of land and can put up data campuses. So rather than one data center, what we typically work on has between 3 and 5 data centers on it. I'll tell you, there are some truly wild ideas out there for some very large mega projects that would be 5x-10x larger than any data center we've built, and we're watching those closely; those probably won't come to pass for another year or so, but the size and scope keep growing. Yes. And for us, we, we couldn't ask for anything better.
Adam Thalhimer
analystThat matches my thinking. All right, so moving on to transportation, I'm hoping to get a better feel for how much revenue you believe transportation can ultimately generate, and where do you see margins ending up over time?
Joe Cutillo
executiveRight, our transportation capacity isn't infinite. What I'd say is this: we've still got available capacity, there's still space for growth, and we continue to push our bid pricing higher; and luckily, up to now, we keep coming out on top. So my view remains that we're looking at 100 to 200 basis points of margin expansion across roughly the next 12 to 24 months. And if the margins justify it, we'll find a way to bring on more capacity. That part is simple for us. What we don't want is to bring on capacity when the margins don't justify it, correct? So we'll sort it out. In any of our segments, we've never walked away from work that carried really strong margins, so.
Adam Thalhimer
analystAll right, and for my final question, could you bring us up to speed regarding how you're deploying capital? For instance, is anything catching your eye when it comes to mergers and acquisitions?
Joe Cutillo
executiveYeah, we've taken a look at that. If it were known how many opportunities we've reviewed, you'd probably be stunned. We review quite a few. Plenty of companies are up for sale. That's the positive part. Buyers aren't as plentiful as they used to be, which is also positive; however, truly excellent companies are scarce at the moment. We're searching diligently. We feel good about completing something within this year. Having more than one would be great, but our pipeline is full enough that I believe a deal will land before year-end. It feels like we're forever pushing these to year-end, which, for me, is the worst possible moment to close. Still, we ought to get one done this year.
Adam Thalhimer
analystOkay, great report. Thank you.
Joe Cutillo
executiveThanks.
Julio Romero
analystMorning, everyone — Joe, Sharon, and Noelle. Appreciate you fielding our questions.
Joe Cutillo
executiveMuch appreciated, Julio.
Julio Romero
analystThe margins look great, honestly. It's genuinely encouraging to watch infrastructure margins exceed 20% during the quarter. Could you walk us through what drove that this quarter, and perhaps address whether that margin level in E-Infrastructure can hold up moving forward?
Joe Cutillo
executiveYes. The primary factor is the mix shift, correct? A bigger share of our revenue now originates from those mega centers, be it data centers, manufacturing, or comparable facilities. Once again, the end type is irrelevant to us — the bigger the project, the greater the efficiencies we achieve, and typically, we pull stronger margins from those jobs. So nothing in those markets looks like it's moving in reverse. In fact, we believe capacity will get tighter across those markets over the coming 2 years, which means we ought to hold that margin and possibly even gain a bit more. When the mix shift swings back toward those smaller industrial projects and commercial projects, margins there are lower, correct? So you simply run the numbers on the blended result. Our hope, then, is that we keep growing the large projects at a pace where, as the small ones arrive, the overall margin stays intact, correct? The increase might be smaller, but we shouldn't experience a meaningful drop.
Julio Romero
analystUnderstood, that helps. Next, you said data centers account for roughly 40% of segment backlog right now. What would you estimate for how much of 2024 segment sales and E-Infrastructure will ultimately come from data center sales? And as that set of mega projects goes out to bid in 2026 and 2027, how do you expect that share of data center-related revenue to move?
Joe Cutillo
executiveYes, so we're above 40% at this point, and my view is that it will keep increasing. Given what we're seeing happen, we're genuinely puzzled, because we continue to hear claims that data centers are decelerating or similar. I can tell you we have more data center activity ahead of us than we ever could have envisioned. There's simply no way I could have forecast this volume. More participants are entering from a builder standpoint to take this on. It keeps expanding, and nothing in the capital planning we're looking at suggests a slowdown. In fact, we're seeing the really large players beginning to talk with core contractors about what they can do to lock up multiyear capacity with them, since they worry everyone will run short of capacity, and that concern is justified. If they don't take that step, they'll face problems; so we're enthusiastic about where this is headed. So data centers will remain a percentage of our backlog, and I think we'll probably... I haven't crunched the numbers, but, you know, backlog converts into revenue, so it should be fairly close, I'd imagine. Do you guys have any figures on that?
Sharon Villaverde
executiveFor 2024, roughly speaking, the split is going to look like around 2/3 in large projects and 1/3 in smaller ones.
Joe Cutillo
executiveAll right.
Julio Romero
analystAll right, that's useful.
Joe Cutillo
executiveThen, more medium.
Julio Romero
analystGot it. It was good to see your company carry out a $30 million buyback during the quarter. Could you speak to how we ought to view your use of cash for repurchases, particularly given the recent decline across the wider market?
Joe Cutillo
executiveHonestly, I lack the figures, yet I'd wager we made a purchase yesterday, and we'll keep purchasing at the same pace as we have previously. There's a schedule in place — a ladder might be the correct word for it. We have set price levels, and when those levels are hit, automatic buying of shares is programmed in; we don't handle — that process is fully delegated. It simply occurs and gets executed; our view remains that the stock is severely underpriced, and the optimal move available to us at present, prior to securing an acquisition, is to repurchase additional shares.
Julio Romero
analystThat's genuinely useful. I'll share it with the team. Many thanks.
Joe Cutillo
executiveThank you, Eva. I'd like to express appreciation to everyone who took part in today's call. Should you have further questions, or if you'd want to arrange a call... Pardon me, a call with her — the contact details can be found in the press release. Wishing all of you a wonderful day, and we're grateful for your participation. Thank you.
Operator
operatorThat concludes today's conference call. Thank you for your participation. You may now disconnect.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Sterling Infrastructure, Inc. transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →This call discussed
For developers and AI pipelines
Programmatic access to Sterling Infrastructure, Inc. earnings transcripts and 132,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Sterling Infrastructure, Inc. or any ticker on your watchlist.
StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.