Good morning, everyone, and welcome to the Sterling Infrastructure Third Quarter 2026 Earnings Conference Call and Webcast. It's a pleasure to be with you today to go over our results alongside Joe Cutillo, Sterling's Chief Executive Officer; Nick Grindstaff, Sterling's Chief Financial Officer; and Dan Govin, Sterling's Chief Operating Officer. As a reminder, slides that accompany this call can be found in the Investor Relations section of our website, and they contain additional details about our full year 2026 financial guidance. Today's discussion may contain forward-looking statements. Actual results could differ materially from what is stated today. For a more complete description of the risk factors that could affect these projections and assumptions, please refer to Sterling's most recent 10-K and 10-Q filings. The company undertakes no obligation to update forward-looking statements as a result of new information, future events or otherwise. Management may reference certain historical, forward-looking and non-GAAP financial measures, and reconciliations of these non-GAAP financial measures to the most directly comparable GAAP financial measures are included in our earnings release and posted in the Investor Relations section of our website. Additional information regarding our forward-looking statements and non-GAAP financial measures is available in the press release. Throughout today's discussion, unless otherwise noted, all third quarter 2026 comparisons are to the third quarter of 2025. I'll now hand the call over to our CEO, Joe Cutillo.

Joseph Cutillo

executive
#2

Appreciate that, Noah, and morning to all. Sterling delivered one more remarkable quarter, as adjusted diluted EPS jumped 118% to $7.58. Revenue was up 127%, while adjusted EBITDA grew by more than twofold. On top of that, our forward visibility continues to widen. Total scope work — spanning signed backlog, unsigned awards, plus the upcoming phases currently being designed across our existing projects — now totals close to $8 billion, an increase of about 90% versus a year ago. Those numbers reflect how strong our market is, the excellent work our teams are doing, and the ongoing payoff of our strategy. It was a standout quarter, yet even more important is the insight these results give us into the opportunity that lies ahead. Over the course of 2026, it has grown increasingly evident to us that we are only at the beginning of a substantial, multiyear wave of investment in large-scale, mission-critical infrastructure throughout the United States. Data centers continue to be a strong engine of growth, yet the opportunity extends well beyond them. Fannie semiconductors, advanced manufacturing, energy infrastructure, and the wider build-out underpinning the next generation of U.S. industrial growth. The magnitude of this opportunity is prompting us to think even more ambitiously about how we position sure for long-term growth. Our focus is on developing the capacity services, geographic footprint, and customer relationships needed to capture a greater share of this investment. It's worth noting that the $8 billion in scope work doesn't reflect all the development potential at the campuses we're already working on today. A lot of these projects cover hundreds or even thousands of acres, and they're being built out in multiple phases across several years. These are real opportunities—supported by land, permits, and power commitments—and they sit on top of what's already in scope; altogether, they give us more than 5 years of additional work. Sterling is in the strongest position it has ever occupied. We can see future growth clearly, we enjoy close ties with the people we serve, and we possess the money and operational capacity to seize the opportunities in front of us. Everyone here looks forward to what lies ahead for Sterling, and we feel sure we can rely on robust, profitable expansion well into the future. At this point I'll pass things to Dan, who will walk us through the segment results in greater depth. Dan?

Daniel Govin

executive
#3

Thanks, Joe. I'll begin with Infrastructure Solutions. There, demand that had previously been absent came through strongly, project activity picked up speed, and our execution was outstanding — all of which delivered another great quarter. Revenue climbed 212% compared with the same period last year, powered by ongoing momentum in data center and semiconductor campus projects. Within the infrastructure segment, our site development operations more than doubled revenue organically, and each of our geographies posted solid growth. Demand from customers in the Southeast remains strong, and projects continue to expand in acreage, phase count and complexity; that pattern aligns exactly with what we do best, allowing us to bring our wide-ranging self-performed capabilities and our execution model, which has proven itself, to bear. In the Northeast, our large semiconductor campus keeps advancing very well, and we are still ahead of schedule. The large-scale work we're doing is bolstering our standing and our name in the semiconductor sector. In the Rocky Mountain region, momentum keeps building—activity on big projects that were awarded recently has picked up pace, and that produced yet another quarter of outstanding growth. Our crews are performing well and are effectively shifting transportation resources around to capture the growing mission-critical opportunities. More and more, key customers are asking us to help carry out their capital plans in Texas, and that is generating considerable need for what we offer in site development. Based on the opportunities before us now, we anticipate Texas will be a significant source of growth across the coming years. Moving on now to CEC. In the quarter, the Electrical business brought in $426 million of revenue — more than four times what it posted on a pro forma basis for the entire third quarter of 2025 — and that expansion was fueled by quicker progress on major hyperscaler and large colocation projects. CEC is expanding rapidly and once again performing at a high level. Growth so far this year has run well ahead of what we originally anticipated, and we now think full-year revenue may surpass $1 billion. That momentum carries beyond 2026, since CEC keeps accumulating high-quality, longer-duration backlog with established customers, which sets the business up for further growth in 2027. Robust demand and solid execution at both CEC and site development are producing substantial profit growth for the segment. For the quarter, adjusted operating income in Infrastructure Solutions rose 171%, and adjusted operating margins came in at 23%. Those margins were lower than a year ago, which reflects the much larger revenue contribution from CEC — it accounted for one-third of segment revenue this quarter, compared with 10% in the same period last year. Inside the segment, site development operating margins held at the strong levels seen in the first half of 2026, even though a number of our big mission-critical projects are only in the early construction stages. As these multi-phase campuses progress into later construction phases over the months and years ahead, margins usually expand. Operating margins were up both year over year and sequentially, and the margin improvement we're seeing in the core business is encouraging. We've talked before about how we're shutting down certain non-core business lines that came to light during due diligence — something we anticipate wrapping up by the end of 2027. Our estimate is that those non-core operations will weigh on full year 2026 CEC margins by about 160 basis points, which obscures a roughly comparable gain in the core business. At the time we bought CEC, we pledged to achieve 300 to 500 basis points of run rate margin improvement at CEC over 18 to 24 months. Given the progress in the core business and our planned departure from non-core work, we're confident we can fulfill that pledge. Looking ahead, the possibilities in e-infrastructure continue to expand. All told, our scope work is now valued at approximately $7 billion, representing growth over the prior year. The bulk of these prospects relate to mission-critical work, giving us considerable visibility into ongoing growth. Turning to Transportation Solutions: revenue declined 3%, reflecting the shift of resources away from transportation toward higher-margin infrastructure work; that transition continues to speed up as e-infrastructure activity grows in the Rocky Mountain and Texas regions. This was the second quarter in a row that our Rocky Mount operation generated more revenue from e-infrastructure than from transportation. Despite the revenue decline, adjusted operating income for Transportation Solutions increased by 22%, with adjusted operating margins reaching 19.7%. This reflects the rigor we bring to project selection. The Transportation Solutions backlog ended the quarter at $964 million, a 31% year-over-year increase, largely due to converting unsigned backlog into signed. Total combined backlog for the segment fell 22%, again reflecting the shift in resource allocation. At Building Solutions, segment revenue declined 5% amid slower homebuilder activity, and adjusted operating margin stood at 8%. We anticipate residential market conditions will remain under pressure through the rest of 2026 and into 2027. We are steering the company prudently through today’s conditions while setting it up to win additional market share when things turn better. Looking at the bigger picture, this quarter shows plainly how Sterling’s strategy is playing out. We are gaining from unusually strong demand in the markets that give us the best returns, growing more choosy about where we put our resources, and laying groundwork for growth across multiple years; on that note, I will pass things to Nick, who can walk through some of our financial metrics and the 2026 guidance. Nick?

Nick Grindstaff

executive
#4

Thanks, Dan, and good morning. I'll start by covering our cash flow and balance sheet. During the first 9 months of 2026, operating activities generated $427 million in cash flow, which is up 68% versus the same period last year. One item worth flagging is the rise in accounts receivable at quarter end. Those receivables came in higher because Eaton infrastructure activity grew substantially, and collections timing also played a part. That said, early in October we already collected a major portion of those outstanding funds, which positions us well for strong operating cash flow in the fourth quarter. Investing activities produced a $276 million outflow, and that figure includes $115 million in capital expenditures. We now expect full year CapEx of roughly $140 million. Financing activities generated a $325 million outflow year-to-date. On July 2, we completed the extension and expansion of our revolving credit facilities to $1.5 billion and pushed out the maturity by 2031; we drew on this facility along with cash on hand to retire our existing term loan. The larger facility further bolsters our financial flexibility and adds capacity to support organic growth as well as M&A. Financing activities also reflected $107 million of share repurchases. At quarter end, $267 million was still available under our existing repurchase authorization; we'll keep taking an opportunistic and disciplined approach to buybacks as part of our broader capital allocation strategy. Now for the balance sheet. We finished the quarter with $217 million in cash and $95 million of debt, giving us a cash net of debt balance of $122 million. Together with our expanded revolving credit facility and strong cash generation, the balance sheet gives us considerable capacity to keep investing in the business and to pursue acquisitions. Onto guidance. Our results through the first 9 months and better visibility into the fourth quarter give us more confidence in our full year outlook; we are raising our 2026 guidance ranges as follows: revenue of $4.63 billion to $4.73 billion, diluted EPS of $19.16 to $19.42, adjusted diluted EPS of $21.70 to $21.96, EBITDA of $905 million to $916 million, adjusted EBITDA of $970 million to $981 million. With that, I'll hand the call back to Joe.

Joseph Cutillo

executive
#5

Thanks, Nick. The trends we've pointed to across the last several quarters haven't just carried on — they've picked up speed. Projects are getting bigger or more technically complex, and they're lasting longer. Our execution keeps building trust and loyalty with our customers, and that is opening doors for Sterling to move into new markets, shoulder more responsibility and play a bigger part in our customers' long-term capital plan. The opportunity in front of us is bigger than ever. More and more, the question isn't whether the opportunity exists, but how fast we can add capacity to capture it; we're putting money into our people, equipment and our capabilities while keeping the execution discipline and focus on returns that have driven our success. As we look toward the rest of 2026, we're confident that we'll deliver another record year. The midpoints of our revised guidance ranges would represent 88% revenue growth year-over-year, 101% adjusted EPS growth and 94% adjusted EBITDA growth. Our guidance still assumes a more pronounced weather impact in the fourth quarter than we saw in 2025. Stepping back, our multiyear growth strategy is built around 2 complementary drivers: strong organic growth and disciplined strategic acquisitions. We're targeting annual organic profitability growth of 20% to 30% over the next several years, with M&A offering an additional chance to speed that growth up. Together, these drivers support an aspiration to grow earnings by approximately 50% per year. We believe 2027 is shaping up to be another year that meets or exceeds this organic framework; on the acquisition front, we remain very active and encouraged by the quality of opportunities in the market. We'll keep pursuing acquisitions that expand our capacity and geographic presence and enhance the value we can bring to our customers. Our strong balance sheet, significant cash generation and disciplined approach to capital allocation give us the flexibility to fund organic growth and pursue strategic acquisitions supporting our multiyear growth ambition; we're confident in Sterling's ability to deliver sustained, profitable growth and long-term value to our shareholders. With that, I'd like to turn it over for questions.

Manish Somaiya

analyst
#6

Joe, looking at the full-year margin guidance, it points to roughly 19% in the fourth quarter, and obviously that's lower than the 21.6% you posted in 3Q. So I was hoping you could help us bridge that gap. I know you mentioned the CEC setting of noncore businesses is going to have an impact on margins? And then, staying on this subject, more specifically, would the fourth quarter be the trough for margins? And how should we think about 2027 as we head into it with a strong backlog and, as you noted, 20% to 30% organic growth.

Joseph Cutillo

executive
#7

Yes. I appreciate that, Manish. Yes. Looking at Q4, a few things are in play. First, there's the usual seasonal pattern we shift into every year. As we've mentioned, we're taking a somewhat cautious view on weather for the quarter, relative to — just as a reminder for everyone, 2025 gave us roughly the mildest, most forgiving winter we've experienced. It didn't materialize here. We essentially didn't plow anything, and we made it through the entire winter. We don't anticipate a repeat. If it does repeat, that's great — plenty of upside, and we'd all be pleased. Therefore, seasonality alone is causing some margin erosion, and on top of that we have CEC's expansion—let me pause and address that for a moment, since everyone seems to view it negatively, which genuinely puzzles me. A few people have called this a mix problem, though that's not how I'd frame it. Our electrical business is a very different operation from site civil work—it takes significantly less capital, and we scaled it far more quickly than we ever thought possible, which is a fantastic result. That business has grown to more than twice its size. Yeah, everybody treats it as a negative because it pulls total margins down. To double the business, we've invested essentially nothing to 0 capital. We've had far greater success bringing on electricians than we ever expected, and that's a great sign. We have the next phases and next levels of projects coming from our customers. So we've done well at executing and delivering, and yet we're getting beaten up for it. To me, that just doesn't add up. So we're expanding that operation, and our site civil segment has grown really well. But as we scale it much faster, the key point is that its margins are thinner. That's simply how it will stay, because a large portion of what they do is tied to materials, and the profit you can make on materials isn't the same as what comes from performing the work. Then there's another bright spot: we've come a long way. At the start, we stated that margins in that segment would climb 300 to 500 basis points over 18 to 24 months. I can tell you we've traveled a considerable distance down that road; we're ahead of schedule, and that's if you exclude the legacy business, which we know remains with us through the end of '27, and hopefully we can take some steps to exit it a bit sooner. If you set that aside, we are on track, and we have realized more than 150 basis points of improvement in CEC, correct? So that is — I simply want to take this chance to discuss that a little, because I believe people are genuinely mixing up the good news that has come out of position. And because of that, they are penalizing us for really no reason at all. On the second question, could you repeat it, Manish?

Manish Somaiya

analyst
#8

Let me — Yes. Joe, my follow-up was on the margin trajectory. Is 4Q likely to mark the low point for margins? And how should we think about the margin path as we move toward 2027? And since I have the mic, could you also touch on backlog — how much of that unsigned backlog you hold, which is fairly substantial, might convert into signed backlog? What sort of pace should we expect for that?

Joseph Cutillo

executive
#9

Yeah, so I'll start with the trough. Seasonality in our margins is definitely something we have, and it's going to continue. Now, as we grow the business and move into other regions, could that soften it somewhat or move it around? Sure. But seasonality will still be there, so we won't see a flat margin across all 4 quarters. I'd add that our expectations for site civil growth in 2027 are fairly high. At the same time, we think electrical has a shot at sustaining some of those growth rates. If that happens, then again, the blended margin is simply the blended margin. I can't forecast it, since I don't know what revenue will be. Theoretically—and I stress theoretically, since in practice site margins will continue improving and electrical margins will do the same—whatever those revenues end up being is what will set the final margin. Still, we're quite optimistic about the margin trajectory in every part of our infrastructure segment. As for backlog, I wish we could somehow move away from it completely, because for us that number really means nothing. We need to consider what sits in backlog—projects we're currently executing—along with something we refer to as unsigned awarded contracts, largely in transportation and a few in electrical. These represent work already granted to us, where we're still working out final pricing or finalizing terms and contracts. So they'll add to backlog and could come in during the quarter if design work is needed, and they may take a couple of quarters, but we've already won those jobs. We're in the final negotiations. So those things do occur; we’re already discussing the following phase or phases in design—that’s roughly how we’re describing it, apologies for the wording—but that effort really sits with the site civil group. It’s work for which we’re either designing or pricing for customers, and we know it follows directly after the phases now underway. Yet there’s another element everyone is overlooking. For anyone who joined the tour and is also on this call, we have literally thousands of acres that are permitted, powered, and ready to go. Once the current phases wrap up, they’ll handle the design and construction of the following phases, and that work spans more than 5 years for us. As for backlog, it makes up only a limited share of what’s already in front of us. When we talk about adding capacity, I’m sure somebody could wonder why backlog isn’t growing as fast as the capacity-building needs would imply. The explanation is future land along with the long duration of those projects, which we know are required to generate that capacity for taking on the new projects that are coming. I hope that makes it clear.

Brent Thielman

analyst
#10

Joe, could I ask a quick follow-up on what you just said about infrastructure, and maybe take on a few of the other concerns folks have out there? I mean, you've got all these campuses where phases run for years, and presumably those have power. Looking at everything else out there — I guess just in terms of new campuses that might be in your pipeline to work on — do those also have their power connections figured out? Just trying to address that worry.

Joseph Cutillo

executive
#11

Yes. Yes. I don't know of any campus we've ever started that didn't already have power on it. So all of these are permitted, all powered, already good to go. Looking at the projects in the pipeline, they're clearly handling the permitting and power work; once that gets released, they typically hand it over to us and we begin. The additional land we're referring to is included in that package. And in many instances, when they've managed to secure more power for the project, they're acquiring extra land nearby. So quite a few of these jobs keep growing beyond what they were when we first began the project. That's very common.

Brent Thielman

analyst
#12

All right. So maybe turning to CEC — clearly, there's been enormous growth here — Joe, this year, with some of the constraints that exist out there, could you help us think through how you generate more from this business, whether that means capacity investments, and so forth? And ultimately, I think what I'm driving at is: what's a realistic growth assumption, in your view, for a business like this, considering that 20 to 30 you put out there, given the demand and the supply-side constraints?

Joseph Cutillo

executive
#13

Let me share a couple of points with you, Brent. We've felt very good about CEC's capability to bring on electricians; based on the latest figure I saw, we brought on about 80 per week in the state of Texas alone. We believe we can keep succeeding at that through 2027. I'll say this: we have some fairly aggressive growth opportunities at CEC in '27. Beyond that, we're seeking small to midsize — and a large one would be terrific — acquisitions where we can take the labor force, what they're currently working on, perhaps small commercial projects or small industrial projects, and redirect those labor forces to our ambition-critical customers, adding capacity there. On top of that, we mentioned we tripled the size, and we're building out our IMS facility, which includes prefabbed modules. Whenever we can prefab for molecules, that removes a significant share of the work needed on the project, which in turn creates capacity for us. So those are the areas we're really concentrating on, and we're pleased with the progress. I believe CEC will post great growth numbers in '27 <<inaudible>>.

Brent Thielman

analyst
#14

Alright, one final quick question about site development. I believe you said earlier that you perhaps didn't witness that margin step-up in the 3Q versus prior quarters, simply because of how projects were timed and early-stage projects. Could you discuss some of the other factors, such as the new geographies you're ramping up — are those margin drivers getting close to what you'd call core legacy margins? Please walk us through that.

Joseph Cutillo

executive
#15

Yeah, so on the new geographies, we're definitely not close to what I'd describe as the margins of our most established geographies, but we believe we're seeing good improvement in <<inaudible>>. Another thing to bear in mind — we discussed the Micra project in the high turn of the quarter, and Brent, I'm not sure whether we've covered this specifically with you, but a unique aspect of that particular project is the first roughly $600 million, at 4 million cubic yards of rock, that we had to purchase and put down. So that's a big material purchase, and margins on the material side come in lower. As a result, the margins on that job aren't at the levels of our traditional job. Then, as we move into future phases, it becomes a more traditional job for us. So that definitely came in lower on a blended margin basis; however, we're quite pleased with how all the margins have progressed, because even with that, even with the new geographies, we managed to hold site civil margins flat quarter-over-quarter. So that tells us we're making considerable progress across many areas. Given that Micron bid, we would have expected margins to have declined for the quarter.

Noah Levitz

analyst
#16

To start, during the prior quarter's call you noted a bit of weakness in Q3 bookings, followed by what sounded like a recovery in Q4 and the beginning of 2027. Apologies if I overlooked this, but can you share some specifics about those possible bookings? Are you still anticipating they'll come through in this quarter or early next year? And given that various peers sit at different stages and sizes, do you feel confident those possible expected bookings will be just as large? Or is your confidence simply that they'll land within that window?

Joseph Cutillo

executive
#17

What I can say is this, and it's another reason we're not fans of backlog. Hypothetically, I could sign a $1 billion project and only record $10 million of it into backlog — the remaining $900-something million would be invisible to you, right? What I can say is this: every project we've discussed as coming out in the fourth quarter and the first quarter remains in place. They are still on the way; timing will vary. Timing always makes me nervous, because a one-week slip can push something out of one quarter and into the next. Even so, those projects continue to advance. They are larger than the projects we've seen before and will run longer than past projects did; we're very optimistic that they will be contributors in 2027. What's their pace of getting started across the board? Pretty much the usual situation, correct? They're handling permits and dealing with all of that, and once everything is finished, they'll pull the trigger and get us moving as quickly as they can. So the outlook there hasn't changed at all. No change regarding project type or size, and we're continuing to move forward. Thus we feel quite good about the opportunities ahead of us and the effect that will have on '27.

Noah Levitz

analyst
#18

Great, that's very helpful. I mean, could you walk us through the geographic expansion in more detail — in particular, how is your Texas penetration progressing in light of the ERCOT audit? And then please separate out West Texas exposure, with your Rocky Mountains business and, I guess, Stoneridge having exposure there, from your East Texas exposure with Plateau; and also, have you begun expanding into the Pacific Northwest already, or is that more of a 2027 event? You mentioned customers pulling you into that geography as well as other geographies. So an update specifically on Texas, and then the Pacific has less than other ancillary geographies?

Joseph Cutillo

executive
#19

Yeah. Well, in the next 5 years Texas is going to be the biggest data center state; so the size of the projects coming out is enormous. They're in what I'll call the early phases of a lot of these projects, and that's what we see potentially coming up in the fourth quarter and the first quarter of next year, some of those both in West Texas and what we felt in East Texas, which is really North Central Texas; in — we've made great progress on the ones we're on. The CEC business has got the second phases. Site development work is ongoing. On those, we hold the complete package set, and clients keep approving us to take on additional scope. Texas looks very promising to us. The real difficulty at the moment is expanding capacity quickly enough to seize all the demand coming our way. Put simply, the opportunities before us exceed what we can currently handle, and we're working out ways to add capacity so we can absorb that. In the upper Northwest, or Pacific Northwest, business is up, and we're actively working there. Among the initial projects we're handling is a Micron chip facility located up there. We were brought into that Micron plant as a result of our New York projects. We view that as just the start. The data centers we've been discussing haven't emerged yet. Our expectation is that it'll be late '27 or '28 before that activity begins to appear. However, the positive side is that we're positioned through Stoneridge, through our business, and through the work we're performing up in Idaho, and we'll be prepared for it once it arrives.

Noah Levitz

analyst
#20

Great. And then one last quick question. Your guidance points to CapEx of $140 million for 2026, which suggests a $20 million sequential step down, especially since we're having plenty of conversations today about capacity. And previously, you've mentioned that some of the heavy machinery providers are experiencing some supply tightness. Is that partly why CapEx is coming down sequentially? Or how are you viewing growth CapEx and your ability to build capacity to meet all of this tremendous demand.

Joseph Cutillo

executive
#21

Yes. I'll let Nick give you some color on it, but it's just timing. It's — I wouldn't look at it as stepping down, I think, as we go to next year, we will be more CapEx to help with our growth rates. But Nick, do you want to give some details?

Nick Grindstaff

executive
#22

Right, so there are other levers we can pull when it comes to recurring equipment. There's a leasing program we offer, and of course rentals as well. But the point is that not everything lands in the CapEx figure. So we'll use our leasing program to make up the difference in CapEx.

Kurt Yinger

analyst
#23

Great. Just briefly on CEC. I believe through roughly the year to date, that adds up to slightly over $800 million in revenue. I know there's that $1 billion number floating around out there. So I suppose my question is whether there's any reason to believe the Q3 burn might be something that couldn't happen again? Or is that maybe just a bit of conservatism as you think about the end of the year?

Joseph Cutillo

executive
#24

Yes. We — like we said, there's no reason we can't do Q3 and other quarters. We've factored in some conservatism on weather. Another factor that often slips people's minds is the fourth quarter, when we have two major holidays, Thanksgiving and Christmas. Our teams work throughout the entire year without taking time off, so we aim to schedule their vacations around those holidays since that makes things much simpler for us to handle. So a portion of the seasonality really comes down to managing labor and resources. To be honest, it's far simpler for us to announce that we'll close operations for these two weeks, or trim staffing during these two weeks and cut crews during these two weeks, so that everyone can take their vacation and we can hit the ground running the following year. So there's nothing unusual about Q3. The CEC segment keeps posting really robust bookings and growth. They secured the next buildings for multiple Texas projects, and that revenue is now starting to come through.

Kurt Yinger

analyst
#25

Got it. Okay, and then secondly, just on the broader competitive landscape on the site development side. You've mentioned wanting to plant the flag on those longer-duration projects and making sure you're matched up with the right customers. I guess, is there any trade-off you have to accept on margin to get that added visibility? And to make sure you're paired with those right customers? Or do service, speed, execution, all of those things still come through in the margin profile of the work you're bidding, or new work, so to speak?

Joseph Cutillo

executive
#26

A few things to bear in mind. First off, our first phase is always the lowest margin phase. And as these projects move forward, and we get deeper into phases, our margins rise over time, okay? And much of that, everyone assumes it's pricing, but it's really about productivity and the things we can do along the way in earlier phases that either help us or remove expense we'd have to incur in future phases. That's the reason. The other part is that if we plant a flag in Texas, where we're not 100% vertically integrated, those initial margins will be lower than in the Southeast, where we are vertically integrated and we perform everything. That said, we've said strategically that once you reach critical mass, and we're getting there very quickly, we will start vertical integration in Texas or in new geographies that we are in and keep ramping up that margin profile; so you get a double ramp. You've got the actual progression of the phases over that 5-year period or 7 years, whatever that project takes. And then you've got an incremental ramp, which comes about as we keep vertically integrating the other ancillary services and stuff needed on that project, you get another pickup. So if you look at it, this is the best way for us to have not only long-term growth, but also long-term margin expansion opportunities, because the margins will rise on those projects over time.

Kurt Yinger

analyst
#27

Got it. Maybe one quick follow-up on that. You've talked about a fair number of these new geographies in Texas — for example, when you think about the timeline for vertically integrating some of those new areas, would you frame that as roughly 2027, or more likely further out for when that happens?

Joseph Cutillo

executive
#28

Sadly, it's not a toggle switch. It's more of a duration pace, so to speak. It took us — well, I'd say we still haven't finished the Southeast <<inaudible>>; we keep looking at other services we could offer, and there are parts of the project. If I had to give a rough average ballpark, it's really more like a runway of 24 to 36 months. Just so you understand what we have to do: there isn't <<inaudible>> match such that, when we acquire a company, we could keep them occupied 100% of the time on projects. If we don't, we end up with underutilization and negative productivity, and that will actually put a drag on margin. So what we prefer to do — and it takes a bit more time, but it's a far more successful model — is to partner with subcontractors in test track. Those that we consider top-tier, we continue expanding until they reach a point where they can no longer handle our pace — at which stage acquiring them makes logical sense, correct? It benefits both sides, and our track record is strong: not just in completing those purchases, but in doubling or tripling their size within 12 to 18 months by adding more revenue and volume. So the results have been very good. Therefore, once we've built sufficient critical mass — whether in blasting, <<inaudible>> standardization, or if I can create 10 additional banks — we'll begin exploring ways to vertically integrate that. Alternatively, there are situations where we might attempt to build a small business ourselves in support of that.

Brian Brophy

analyst
#29

Clinton Helmer here, sitting in for Brian Brophy. Stoneridge clearly did quite a bit better than expected. CMC already went over some of the drivers. Is this basically a one-time thing thanks to that big project you brought up earlier? Or what sort of trajectory should we have in mind as you keep executing on tuck-ins from the site development side? What kinds of things are you seeing there? Any color would be appreciated.

Nick Grindstaff

executive
#30

Sorry, what was the question about Stoneridge that you mentioned?

Analyst

analyst
#31

Yeah, and sort of in terms of how it did better than expected — clearly the Micron plant is part of that. I'm sort of trying to get a sense of what trajectory we should have in mind as you keep executing on these tuck-ins? Any color on that would be appreciated.

Joseph Cutillo

executive
#32

Yeah, yeah; so the Micron job really has nothing to do with the Stoneridge. The Micron job is tied to — the reason we landed it, how we landed it, is the performance we've shown on the Deer job. And if you guys recall, we delivered the September package in July and we delivered the January, February back in September. We're a number of months ahead on that project. Not only was migrates <<inaudible>>, the GCs there are really impressed by how much further along we were. They asked us to go look at the job happening in Idaho, and we've begun doing some work on it. We're actually using our RLW business for that one. They were handling another data center up in that region, in that area. So we simply shifted a level over there. What was the next question?

Analyst

analyst
#33

No, that was about all. Thanks for clearing that up. That helps a lot.

Joseph Cutillo

executive
#34

Yeah, I'd say the key point there is precisely what we've done in data centers we're now doing in semiconductors, as the semiconductor tidal wave arrives around 2030. So for us, this much work today and satellite conductors is a big bonus, but really more of a credit to our teams for the value they deliver to customers, and we're confident we'll be the go-to company on the major semiconductor jobs to make.

Sangita Jain

analyst
#35

Joe, I'd like to ask you something wider about the market as you see it today, specifically the resistance around <<inaudible>> day in productivity — and is the way you approach risk on terms and conditions for those large bookings changing at all?

Joseph Cutillo

executive
#36

Yeah. A few things: there's an enormous amount of noise right now, and I'm eager to possibly get past permitting and everything else; and in fairness to our customers, they have these projects, they have a sending there, they're set, they're moving; but what they're trying to figure out is whether something is going to shift, right? Honestly, I can't say, and neither can they. Take Texas as a good illustration of what's happening with permitting right now—there's a lot of talk about it, and about having to redo the whole review. One issue that came up involves TC2, the agency that issues every water permit in Texas, which relies on an automated system for permits. So what happened? Data centers kept filing permit applications through that automated system, and permits were being approved. Then some group intervened and said, "Hold on, that's not what the governor called for—these permits need a manual review." And PCQ responded, "well, we don't actually have a procedure for reviewing them by hand." The customer asked, "I got permits. Are they valid or not valid?" Right now they're going back and forth debating whether those permits hold up, so there's a bit of limbo. Will those projects proceed? Absolutely. Will they proceed? Is there confusion in the system right now around things like that? Absolutely, there is. My sense is that a lot of this disappears after the election, and it will become very clear. But nobody is backing off projects that we can see; we're not seeing anyone change strategies or anything else. But let's just say we're all wrong. Worst case scenario, something like that happens. So here's the outcome you should expect: those 1,000 acres I still have in the pipeline — the ones with power and permitting in place — well, until they sort out the other pieces, they're never going to find a way to either get that built out quicker or acquire additional land nearby. So as we sit here and look at it, with more than five years of work within reach on the projects we're pursuing, you might ask, could there be some noise? Probably. But do we hear anything suggesting the work is slowing down or shrinking? Absolutely not. So we'll work through it, and everything will turn out fine.

Sangita Jain

analyst
#37

Then, if I could ask just one question about all the margin discussion we've had so far. You mentioned tighter margins and the puts and takes. Several jobs are at early stages, and those stages usually dilute margins somewhat. You're also expanding into new geographies. So could you tell us how you're thinking about which comes first — whether the existing jobs moving to advanced stages will show more margin, or whether geographic expansion takes over, and we keep seeing margins around a flattish range for a while.

Joseph Cutillo

executive
#38

Well, I need to do a fairly deep analysis on that. What I'd tell you is that in the quarter, you would have expected our margins to go down, and they did, which shows that the combination of margin advancements and the new geographic expansions is improving very nicely. We're in the early phases of a lot of projects. I would have thought that would have brought it down, and the Micron project, which is a unique one — we know that shifts into a different set of phases as we get into 2027, probably around the second quarter. We know we'll keep making advancements. So I don't see our site margins going backwards. The question is how fast do they go forward, right? And as those kick in, they are all positive tailwinds to negative tailwinds is <<inaudible>>.

Adam Thalhimer

analyst
#39

Joe, you mentioned growing earnings by more than 50% through acquisitions. Was that meant as a multiyear figure, or specifically for 2027?

Joseph Cutillo

executive
#40

Well, Adam, across the last 6 years, our bottom line has grown 48%. Going backwards isn't something I like to do. And based on what we're seeing come out of the marketplace, I believe there's a multiyear opportunity here to keep growing. Yes. Everyone talks about data centers, and we feel very bullish about what we're seeing over the next 3 to 5 years as those data centers get built out; and we feel like we're positioning ourselves extremely well for the semiconductor wave that starts arriving around 2030. So you put those together plus all the — nobody is talking about the one-off manufacturing plants here and there. I think we've got the <<inaudible>> plant. An Audi plant was just announced; 4 or 5 others were just announced. We don't have those, but we'll see where they land and if we do, we're passing on the pharma sites right now simply because we lack the capacity to pursue them. So there's plenty of opportunity for us to do that. The biggest wildcard is the acquisition. I feel very good about the organic side. Acquisitions are always a lot <<inaudible>> talk. Can we find the right ones at the right place at the right price? I feel very good about the market today. We've seen some high-quality businesses out there, both in site and electrical, and we're excited about 2027. So it's not '27. This is what we think we can do over multi-year.

Adam Thalhimer

analyst
#41

All right, good color. And then how much were margins hurt in Q3 because of diesel or other inflation?

Joseph Cutillo

executive
#42

Yeah, it's actually fascinating. Nobody bothered to mention diesel. Nobody heard us bring up inflation. And the truth is, what we love about how our contracts are structured and how these things get phased is that it really blunts a large portion of that risk. If we wanted a $1 billion project — a 7-year $1 billion project — and we placed all of it in backlog, we'd be grinding away on every single one of these calls about diesel prices, about concrete prices, about something else. So <<inaudible>> negative, the outside growth doesn't believe we have $1 billion, but we know we do. It's a positive because the contract structure really blunts the risk on that stuff. So I'll tell you we've had 0 impact defaults. But we aren't going to discuss it because our job is to overcome it and the impact is so small we're moving forward.

Julio Romero

analyst
#43

There are plenty of solid questions on capacity today. Looking ahead just 4 to 5 years, how should we think about the speed of capacity, and what sort of visibility do you have into that speed? Joe, you mentioned that you've done really well with hiring and adding people while managing attrition. You mentioned that CEC is a strong returns business, needing relatively less fleet and more about adding headcount. So clearly, with the demand outlook very strong over multiple years, it sounds increasingly like the pace of capacity additions matters more and more to the growth runway in, say, '28, '29 and the coming decade. So could you just address the pace and the visibility you have?

Joseph Cutillo

executive
#44

Yes. Yes. Really that's a good question. It's the question nobody has asked, and I'm glad, because it's somewhat of a delusional question — we've grown it a lot; we said that over the next several years, we can grow 20% to 30% organically and feel comfortable with that. We've grown far more than that organically across the last couple of years. Now we can only sustain that sort of pace for so long. We feel good about the 20% to 30% organic pace over the next several years. Certainly, internally, we're going to try to do a heck of a lot more than that. But you really start getting stretched on some of the internal resources and capabilities. To beat that pace, it's really going to require us to do more on the acquisition front and really add more capacity, whether that's in new geographies or within geographies where we already operate — for us to even come close to keeping up with the pace of stuff coming out of Texas, we're going to have to make those acquisitions. Now, as we discussed during the site tour a couple of weeks ago at — there are things we can do with acquisitions that aren't even in Texas that can help us with capacity in Texas. And what I mean by that is we have 2 types of crews. We have traveling crews, and we have local groups. And for us, if travel improved, it doesn't matter whether they're in Virginia or Texas or Ohio or wherever you want to pick, okay? They travel and they do work; so one of the things we're looking at is if we have a concentration of either traveling crews on a mega project, and it's going to be there for a long period of time, or multiple traveling crews in a geography, it makes sense for us to make an acquisition within that geography, which we can then lever to do the work of the traveling crew and grow that business quite substantially, very quickly. That opens up the capacity in that travel group, so I’m able to make an acquisition there, expand that business very fast, likely doubling it in 3 years, and that releases travel in pro, which now gives me $500-plus million of capacity that I can place into a new <<inaudible>>. So those are a few of the things we’re considering in order to raise the <<inaudible>> of growth above that 20% to 30% overall.

Analyst

analyst
#45

That's quite useful. Now, have you noticed anything shifting in the way customers finance or commit to upcoming phases, or in how they negotiate payment terms, and could you speak more generally about how customer financial quality shapes your customer selection process?

Joseph Cutillo

executive
#46

Yes. No, nothing at all has shown up. Still, the bulk of our customer base, the top-tier players and those one tier below, are all in very solid financial shape. I realize everyone gets nervous when Beta or Amazon or someone secures financing. My view is that means more money heading our way for building additional things, correct? That's the best possible development whenever I see it happen; so nothing of that kind has appeared. The receivables step-up this quarter is really about timing and kicking off the first phase of many of these projects. And as you'd expect, once you start a project and get moving, even with a 30-day billing cycle, it takes a minimum of 60 days from finishing the build and installation before that first payment arrives; so unless you begin those right at the quarter's start, you won't see it. And our first couple of weeks in October were pretty strong. So it's just a matter of waiting out what we've seen before.

Joseph Cutillo

executive
#47

Great, thank you Bob. Once more, I appreciate everyone being on the call today. Should any follow-up questions come up, please reach out to Noelle Dilts. You'll find her contact details in the press release. I hope everyone has a wonderful day; we'll be speaking with you later this afternoon. Thanks.

Operator

operator
#48

That wraps up today's conference call, everyone. We appreciate you joining us, and please go ahead and disconnect your lines. Have a great day.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete Sterling Infrastructure, Inc. transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

This call discussed

For developers and AI pipelines

Programmatic access to Sterling Infrastructure, Inc. earnings transcripts and 132,000+ others is available through the EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research

OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Sterling Infrastructure, Inc. or any ticker on your watchlist.

StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.