Noelle Dilts
executiveHello, everyone, and thanks for joining Sterling Infrastructure's conference call and webcast for the third quarter of 2025. It's a pleasure to be with you as we go over our results alongside Joe Cutillo, our Chief Executive Officer, and Nick Grindstaff, our Chief Financial Officer. Joe is going to kick things off by walking through the company and how we performed during the quarter. After that, Nick will cover our financial results and guidance, and then Joe will share a market outlook and a full-year outlook; following that, we'll take your questions. Just a quick reminder that slides are available in the Investor Relations area of our site. Those slides contain information about our financial guidance for the full year of 2025. Before I hand things over to Joe, let me read the Safe Harbor statement. Today's discussion might contain forward-looking statements. Actual results may differ materially from what is said today. For a fuller picture of the risk factors that could impact these projections and assumptions, please see Sterling's most recent 10-K and 10-Q filings. The company undertakes no obligation to update forward-looking statements because of new information, future events, or otherwise. Also, please be aware that management might reference EBITDA, adjusted EBITDA, adjusted net income, or adjusted earnings per share on this call, all of which are financial measures not recognized under U.S. GAAP. As SEC rules and regulations require, these non-GAAP financial measures are reconciled to their most comparable GAAP financial measures in the earnings release we issued yesterday afternoon. All results discussed today, including revenue and backlog, refer to figures that adjust prior period results to conform to the current accounting for RHB JV unless otherwise noted. In addition, all comparisons are to the prior year quarter unless otherwise noted. I'll now turn the call over to our CEO, Joe Cutillo.
Joe Cutillo
executiveThank you, Noelle. Good morning to all of you, and we appreciate you being on the call today. Sterling turned in yet another exceptional quarter, with solid top-line expansion, wider margins, a bigger backlog, and very healthy cash generation; it's a pleasure to walk you through those results now, though what excites us even more is what lies ahead. Starting with what we posted for the third quarter, revenue climbed 32%, driven by a 58% jump in our e-infrastructure solutions segment, which included 42% organic growth. On top of that, our transportation segment posted 10% growth during the quarter. Adjusted earnings per share rose 58%, reaching $3.48. And adjusted EBITDA came in at $156 million. That's up 47%. Gross profit margins widened 280 basis points versus the prior year, hitting 24.7%. On top of that, cash flow from operations during the quarter was once again very robust, at $84 million. The strength of our backlog and the clear visibility it gives us underpin our confidence going forward. Backlog stood at $2.6 billion when the quarter closed. That's a 64% increase year-over-year. If you set aside what the recently acquired CEC contributed, backlog was still up a solid 34% year-over-year. Within e-infrastructure solutions, backlog reached $1.8 billion, a 97% rise overall. And 45% once CEC's contributions are excluded. When you factor in our unsigned awards as well as the pipeline of future phase opportunities, the pool of work we can see spans more than $4 billion. For Sterling. The Sterling Way — our commitment to looking after our people. Our environment, our investors, and our communities as we go about building America's infrastructure — continues to be the principle that guides us as we carry out our strategy and expand the business. Now I'd like to go deeper into how each segment performed. In e-infrastructure, third quarter revenue was up 58% compared with the prior year and more than 34% on a sequential basis. Without CEC, revenue rose over 42% year-over-year and 21% sequentially. The data center market once again served as the leading growth engine this quarter, with revenue from that market up more than 125%. Compared with a year earlier. Adjusted segment operating income was up 57%. Or 48% when CEC is excluded. For the legacy e-infrastructure site development business, adjusted operating margins came to 28.4%. That's an increase of more than 140 basis points over prior year levels and 10 basis points on a sequential basis; the improvement came from our ongoing move toward large mission-critical projects, data centers among them, where our strong project management and our record of completing jobs on or as scheduled are hugely valuable to the customers we serve. We're glad to have finalized the CEC acquisition in the quarter. We foresee enormous opportunities ahead to make the most of our broader service portfolio, and early feedback from our customers has been positive. CEC added $41.4 million of revenue in September. And adjusted operating margins that matched what we had anticipated. Visibility in the e-infrastructure business remains very good. With the CEC acquisition completed recently. Adding together our e-infrastructure signed backlog. Unsigned electrical awards, and future phase site development opportunities comes to roughly $3 billion. Turning to transportation solutions, revenue for the third quarter increased by 10%, while adjusted operating profit rose 40%, fueled by robust market demand along with gains from a mix shift toward services carrying higher margins; we closed out the quarter with a transportation solutions backlog totaling $733 million, up 23% compared with the prior year. On a sequential basis, backlog for the segment was about even, as awards matched burn. Just a reminder, the wind down of our Texas low-bid heavy highway operation is having some effect on backlog during this year, though it will eventually help segment margins. Moving to building solutions, during the third quarter, revenue for the segment fell 1%, and adjusted operating income dropped 10%. Adjusted operating margins for the quarter came in at 12%. Demand for homes overall has taken a hit as prospective buyers grapple with affordability issues. Revenue from our legacy residential business was down 17%, due to weakness across the housing market generally. Despite these headwinds in building solutions, the strength of Sterling's diversified portfolio and a strategy centered on growth in high-margin end markets allowed us to post yet another record quarter; with that, I'd like to hand things over to Nick for more detail on some of our financial metrics and full-year guidance. Nick?
Nick Grindstaff
executiveThank you, Joe, and hello everyone. I want to start by walking through our consolidated backlog figures, each of which has been adjusted so that RHB is removed from the comparable prior-year period. Backlog for the third quarter came to $2.58 billion, representing growth of 64% over the second quarter of last year. CEC added $475 million to that backlog. If you set CEC aside, backlog rose 33.8% versus the prior year. We finished the quarter with combined backlog of $3.44 billion, an 88% gain. Setting CEC aside again, combined backlog was up 43.5% compared with a year earlier. For the third quarter of 2025, book-to-burn ratios, with CEC excluded, stood at 1.23 x for backlog and 1.76 x for combined backlog. On a year-to-date basis, those ratios, again excluding CEC, were 1.31 x for backlog and 1.58 x for combined backlog. Turning now to cash flow, operating activities delivered a solid $253.9 million across the first nine months of 2025, versus $322.8 million during the same stretch last year. Investing activities consumed cash during the first nine months of 2025, including $46.9 million of net CapEx along with $484.2 million tied to acquisitions, CEC among them. Financing activities produced a year-to-date outflow of $80.7 million, largely because of $48.5 million in share repurchases completed at an average price of $135.96 per share. We still have $80.9 million available under our existing repurchase authorization. From a balance sheet standpoint, we are in great shape. At quarter end, our liquidity was very strong: $306.4 million in cash alongside $294.6 million of debt, leaving us with a cash net of debt balance of $11.8 million. Our $150 million revolving credit facility went undrawn throughout the period. I'd now like to walk through guidance. With such powerful tailwinds supporting our business, Sterling is set up for yet another record year in 2025, so we are raising our guidance ranges to $2.375 billion to $2.39 billion in revenue, which works out to a gain of more than 5% at the midpoint compared with our earlier guidance range. Diluted EPS is guided to $8.73 to $8.87. Adjusted diluted EPS is guided to $10.35 to $10.52. That equals a 9% rise at the midpoint versus our earlier guidance range. EBITDA is guided to $448 million to $453 million. Adjusted EBITDA is guided to $486 million to $491 million, a 6% improvement at the midpoint over our earlier guidance range. Financially speaking, we are positioned extremely well to keep pursuing both organic and inorganic growth opportunities in the years to come. With that, I'll hand the call back to Joe.
Joe Cutillo
executiveThank you, Nick. When we think about what lies ahead, our optimism regarding the multi-year potential across every one of our markets stays very high. The confidence we have comes from a robust backlog, upcoming phase possibilities, and conversations we're having with clients. To begin with, in e-infrastructure site development, we expect the present vigorous appetite for data centers to persist well into the future. Multi-year capital deployment strategies are being talked about by those we serve, and we're concentrating on how to team up with the appropriate partners to back those strategies; our customers are drawing us into fresh regions, such as Texas, where site development work is now being carried out by us. Turning to the manufacturing sector, activity levels through 2025 appear to be moving at a reasonably consistent rate. Looking ahead to 2026 and 2027, an extremely large collection of mega projects sits on the horizon; this would encompass semiconductor fabrication facilities that are planned. The e-commerce sector has gained considerable strength during 2025. A substantial backlog has been established by us, and we think momentum ought to carry on into 2026. Taken together, these forces underpin robust expansion possibilities across a span of multiple years. Shifting to CEC. Entering 2026, our momentum is quite favorable. Demand from customers is extremely robust, especially within the data center segment, and several sizable projects have been secured by the organization in the last few months. Opportunities for margin expansion continue to appear over the coming couple of years. We hold a great deal of confidence in our capacity to capitalize on combining site development with electrical services as the new year begins; for 2025, e-infrastructure revenue growth of 30% or more on an organic basis, and nearing 50%, is what we expect to deliver. With CEC included. For the complete year, adjusted operating profit margins for e-infrastructure ought to come in around 25%, CEC included, versus 23.7% during 2024. Within transportation solutions, the last year of the present federal funding cycle, wrapping up in September 2026, is drawing near; more than two years of backlog has been accumulated by us, and healthy amounts of bid activity keep showing up. For 2025, ongoing expansion in our core Rocky Mountain and Arizona markets is what we anticipate. Our low-bid heavy highway business in Texas is being downsized in line with the plan, which brings about some softening in transportation solutions top line and backlog, yet ought to produce significant margin gains as the year unfolds. On an adjusted basis during 2025, transportation solutions revenue growth in the low teens is what we expect. Adjusted operating profit margins in the 13.5%-14% range are what we forecast, against 9.6% during 2024; within building solutions, our belief persists that this business is positioned well for growth across a multi-year span. Continued population gains are expected in our key geographies of Dallas, Fort Worth, Houston, and Phoenix, which will fuel demand for new homes. On top of that, a notable chance to gain share exists in Houston and Phoenix; over the short term, we anticipate soft market conditions persisting, pushed by affordability difficulties. For full-year building solutions revenue, a mid- to high single-digit decline is what we forecast. We expect adjusted operating margins to land in the low double digits, versus 14.8% in 2024. Just to reiterate, when you look at seasonality, our fourth quarter and first quarter are usually softer than the second and third quarter, and the first quarter is normally the weakest one we see all year. When it comes to acquisitions, we keep searching for small to mid-size deals that fit our strategy well and would strengthen both what we offer as services and where we operate geographically. Now, turning to our full-year guidance: the midpoint of the raised 2025 guidance range would work out to 27% revenue growth year-over-year, as adjusted for RHB. That's 47% adjusted EPS growth. And 42% adjusted EBITDA growth. With that, I'd like to open things up for questions.
Brent Thielman
analystHi there, and thanks. Morning to you. Congratulations on an outstanding quarter.
Joe Cutillo
executiveThanks, Brent.
Brent Thielman
analystJoe, sure, perhaps I'll start with just the opening question. It seems like — I mean, it appears that both the signed and unsigned business at CEC has expanded quite a bit since that June deal was announced. So once more, we'd simply be curious about what's driving that momentum and the award activity over there. And what's our thinking on — it sounds like there are some sizable data center projects — but what's our thinking on how those convert across the next 12+ months or so?
Joe Cutillo
executiveYes. So during the quarter they posted really solid and robust bookings and wins. It's largely tied to the data center side as that keeps advancing, plus a handful of other sizable projects that sit somewhat beyond the data center area. Here's my take. Their bookings quarter was excellent; that has us excited. But what truly has us excited is how our end customers and end markets are receiving this combination. And we're in the early days of discussing a number of 2026 projects and how we tackle those as one joint package rather than as separate individual packages. So that has us quite excited. Like we mentioned on the call, we've begun doing site development in Texas; we believe that will expand very aggressively as we head into 2026. And I'll say this — the teams are collaborating tirelessly to bring one another into that market, into these upcoming large future phase jobs. So, honestly, I couldn't be happier with where things stand. Right from the start, the team spent two weeks working side by side on things. I was enthusiastic about the deal beforehand. After those two weeks together, looking at the opportunities they identified across the site development and electrical teams, I walked away even more enthusiastic.
Brent Thielman
analystJoe, it sounded like you have an upbeat view when it comes to chances for margin expansion there. Is there anything particular you're noticing in the award activity that gives you confidence on that front? What's behind that margin expansion?
Joe Cutillo
executiveYes, so it's a mix of factors. For starters, looking purely at site development, these projects keep growing larger and larger; and when our customers describe the next tier of projects headed our way, again, they're only getting bigger, and that's great news for us; when you put the electrical side together with site development, we've demonstrated substantial productivity improvements thanks to the small dry utility business tuck-in we completed at the start of January. Their margins have risen 40%. Simply from pairing that with site development; we believe there are definitely chances to scale that up further with CEC; and on top of that, since CEC keeps pushing deeper and deeper into the data center space, those margins boost their average margins; so if we're able to strengthen their portfolio and backlog in that space, their margins will keep climbing too. So we're feeling quite confident about ongoing margin improvement throughout the segment.
Brent Thielman
analystAll right. For my final one, I want to stay on that same topic — the e-infrastructure segment and what's currently in backlog, specifically regarding the legacy side of site development. Joe, would you be able to address how project sizes have changed, including within mission-critical, across the past 12+ months? I realize mission-critical now represents a larger piece for you, but in what ways is that being redefined by the projects you're adding to backlog at present?
Joe Cutillo
executiveI'm not sure we're actually redefining it. The sole additional piece for e-infrastructure is clearly the CEC acquisition fees. Yet the base business increased — was that 34%, I believe, in backlog? So for us, mission-critical once more means data centers, manufacturing, and e-commerce distribution — those are basically what I'd call its three core elements. Did I leave anything out? 45%. 45%. Right. So we're up 45% in that area. So nothing has been redefined by us. It's just the scale of these data center projects, and once the chip plants come out, those are quite sizable too. They'll keep helping us on the margin front. Something we really don't discuss in the script that I believe matters and that everyone should understand is that we say we're in Texas. I'll tell you there are additional geographic footprints we're aggressively looking to expand into. Not because large projects exist there right now, but because we're confident large projects will be there, based on what our customers have told us over the next two to three years. So we're working to get in early, establish our footprint, and be positioned for those to come up.
Noelle Dilts
executiveBrent, it's Noelle here. What I'd say is that at this point, more than 80% of what we have in backlog qualifies as mission-critical work. Think about things like data centers, manufacturing, and so on. So that share keeps climbing. And as Joe mentioned, even inside that mission-critical category, the jobs themselves are becoming bigger and more intricate, including underground infrastructure, which works in our favor. So the intensity of the work we're performing keeps growing.
Joe Cutillo
executiveRight, and building on that point, something occurs to me. Not only do we discuss data centers expanding in scale, but every mission-critical project is growing larger. When we look at e-commerce distribution making a comeback, our backlog growth there is up 150%, I believe. Those projects run roughly two to two and a half times what they used to be. Beyond the footprints expanding, as Noelle pointed out, the infrastructure tied to an e-commerce distribution center increasingly resembles what you'd find in a data center. What I mean is that with all the EVs Amazon is using, plus all the underground utilities that must now be routed to those charging stations and so forth, it looks like a mini duct bank. So the complexity, the size, and the scope keep growing — which suits us perfectly. And with the electrical component now included, you can easily picture how we bring those two together and fold that into the offering.
Brent Thielman
analystAll right, that's great. I appreciate all the specifics from everyone. I'll hand it over.
Joe Cutillo
executiveThank you, Brent.
Julio Romero
analystThanks. Hey, good morning, Joe, Nick, and Noelle. I'd like to focus on that $4 billion+ figure you brought up — the combined backlog along with the forward pipeline of future phase work. Give us some help understanding which end markets or customers make up the mix behind the growth in that forward pipeline. Then, second, how do you estimate the timing for when that forward pipeline starts turning into orders?
Joe Cutillo
executiveI believe you need to separate it into its components. As for the backlog, we are either in the process of converting it or will do so before long into work. On the unsigned side, those represent projects where we either hold letters of intent or have secured the physical job. We're either working through contract terms or some final design effort is underway. Those will probably kick off in 2026. When exactly in 2026 varies based on the specific project. Certain ones might begin in the first quarter, the second quarter, the third quarter. I can tell you that many of the large design-build highway projects will kick off in the second and third quarter of next year, more or less within that process; and then regarding that future phase work, here's how to think about it: as we use up the current backlog — the work we're doing right now — that subsequently moves into current backlog. So it extends across what I'd describe as a 2026, 2027, and on into 2028 timeframe, during which it will land.
Julio Romero
analystUnderstood. That’s quite useful. Then, please continue. My apologies.
Joe Cutillo
executiveNo, I apologize. I merely wanted to confirm I’d covered all the points you were asking about.
Noelle Dilts
executiveI would say in terms of the composition.
Joe Cutillo
executiveOkay, so, if you look at that, out of the $4 billion, $3 billion sits in e-infrastructure. And within that, data center makes up the biggest share — likely 75% or 80% of that portion.
Julio Romero
analystUnderstood. That's really useful. Now perhaps we could shift to transportation solutions, where margin strength was quite remarkable this third quarter. Could you walk us through what's driving that? My understanding is that the effect of the low bid phase isn't really showing up yet, unless I've got that wrong; and then please discuss the margin profile of what sits in your transportation backlog and unsigned awards.
Joe Cutillo
executiveYes. I believe the progress the Transportation Group has achieved is vastly underappreciated. Our margins are best-in-class, and they keep improving. Once again, it comes down to what I'd describe as choosing the right projects and staying focused, as we increasingly take on design-build or alternative delivery work, while aviation and rail keep making that portfolio more diverse. Margins are going to keep rising. A significant portion of that hasn't appeared yet, although we've gotten a small amount from winding down the Texas low-bid operation; that effect will show up more in 2026 as we eliminate, or I should say reduce, that backlog. But it will persist through roughly the first — most of it will be used up during the first half of 2026.
Julio Romero
analystAlright, I'll hand that over. Many thanks.
Adam Thalhimer
analystMorning, everyone. Fantastic quarter.
Joe Cutillo
executiveHey there, Adam. I appreciate it.
Adam Thalhimer
analystJoe, there's something I'd like to bring up with you — you mentioned 2026 and 2027 having a sizable collection of mega projects. Clearly, the number of those you can put bids in for, or your bandwidth for bidding, has limits. So what's your thinking on deciding which ones get priority, and how do you set prices for that work?
Joe Cutillo
executiveYes, I appreciate that question, Adam. Our capacity is significantly greater. We've been getting ready for this; for a couple of years now, we've been holding discussions with our customers about several of these projects. So internally, we've been taking steps to prepare. As we've mentioned, project management tends to be our largest constraint on capacity, along with the program we've established to cultivate future project managers; we've been running it for, I believe, 4 or 5 years, and it's genuinely beginning to deliver results by adding more capacity. Still, when everything is said and done, nobody should be caught off guard if we decline one of these mega projects, because should the pricing be wrong, the margins be wrong, or the contract complexity not work for us, we're fine walking away given the visibility we have in data centers and the other mission-critical work in the pipeline; but I'll tell you, we are evaluating those, and we'll keep adding capacity as necessary to handle them. Just remember, with a year of runway to add capacity, we can add quite a bit. Should someone show up tomorrow saying, "I've got three $500 million jobs," and they need to start in 60 days, that might be difficult for us. That would pose a challenge. Yet our customers have been excellent. The hyperscalers and even these large chip plants have been excellent at looking ahead and anticipating what's coming. Another positive aspect of the chip plants is that they've taken much longer than I think the builders expected for them to get moving with all the upfront work that's been required; so we've been watching these approach for two years now. So we'll be ready.
Adam Thalhimer
analystAlso, that got me thinking. You mentioned starting site preparation in Texas. My assumption is you're handling that on your own, and I wanted to know whether, or in what way, you're using the assets tied to the Texas highway project that is now slowing to a close.
Joe Cutillo
executiveYeah. That's also a solid thing to ask. So, on a site development project or maybe two, you might spot those. With CEC, the smaller pieces of equipment we've got in that fleet are quite able to handle certain utility and underground tasks; putting those assets together means we're now in a position to begin duct bank work in Texas. So my sense is that within the coming 6 to 12 months, should you visit one of our locations, you could come across some equipment carrying a TSC logo.
Adam Thalhimer
analystAlright, and then as a final point, you mentioned that you keep evaluating smaller and mid-sized transactions. Did that remark apply only to the residential segment, or does it cover the entire company?
Joe Cutillo
executiveNope, that's not it. Yeah. Nearly all of the transactions on our radar sit within e-infrastructure or close to it; that isn't to say we'd refuse to examine opportunities and act opportunistically in building solutions. Still, I'd say to you at this moment that roughly 95% of all that we're reviewing or the people we're speaking with concerns added value — whether that's capabilities, stretching into new geographies, or simply straight assets tied to e-infrastructure or thereabouts.
Adam Thalhimer
analystOkay. Thanks, guys.
Nick Grindstaff
executiveThank you.
Noah Levitz
analystThank you. Joe, Nick, and Noelle, good morning, and I appreciate you answering my questions. First, regarding transportation, has the government shutdown affected transportation funding in any way? Also, you've spoken before about a possible follow-on bill to the IIJA. Could you provide any update on whether you still believe it's progressing? Should it be larger? Is there anything else you can share? Thank you.
Joe Cutillo
executiveYeah. So to begin with, the government shutdown has had zero impact. The money for these jobs was already allocated. It's already out there. So there's no effect whatsoever on that; that doesn't mean some grant projects or grant programs someone has out there couldn't be delayed. Fortunately, I'm not aware of anything of ours connected to that. Not one word of concern has come from our business units. So that's not a problem. As for the next bill, the current one expires at the end of September of 2026. I'll say that. I was with the D.C. team. That was probably four or five weeks ago at this point. Things have been moving along quite well. I always add the caveat; this is D.C., and this is the government. We can see how things function or dysfunction. But they're probably six months ahead of where they've historically been. And I'm hopeful something will get done in a timely manner. Still, remember that the reason we aren't losing any sleep over this is we'll enter September with approximately two years of backlog. Also, if there isn't a resolution or a new bill passed, which is probably the better way to put it. An extension will be put in place. Typically, or historically, those extensions have been the existing kind of spend rates plus an inflation adjustment. So we don't halt. We keep going at that pace. What generally does occur in that year when there's a gap, or that six months or whatever period is needed to bridge to the new bill, is that states tend to pursue more smaller projects rather than the big multi-year projects, since they're uncertain how much funding they'll have over a multi-year period. But the truth is the world doesn't shut down. Our projects don't stop. The bid activity projects shift somewhat; but what we're seeing, what people fail to understand, is that spending will keep occurring under this current bill. There are still approximately two years of spending remaining on the current bill that they must get out before the end. So as of today, we expect to go in with two years of backlog. We could go in with more backlog than that depending on which projects get squeezed into this last, let's call it 18 months or less. Now, I suppose it's nearly a year until the next one.
Noah Levitz
analystGreat. That helps. Then here's my final question. You mentioned data center growth exceeded 125%, which is outstanding, and it follows the prior quarter, when it was over doubled. Could you unpack that a little further? Is that expansion from projects already underway? Is it fresh projects starting up? Or is it the present phases — the ones where the work happened during the quarter — turning out to be larger phases?
Joe Cutillo
executiveYeah. Yeah. It's all of those together. I think if you ask our crews in the field, something they take the most pride in this quarter isn't how strong the quarter was and the results they managed to produce, but they found it truly impressive to increase total backlog given the burn rates they carry, yet part of that comes from new projects, and here's how to think about it: without winning new projects, if we had only moved future phase into backlog, our total would have gone down, correct, so we didn't merely move future phase into backlog, we also secured enough new projects to make up for that burn rate and expand that total backlog.
Noah Levitz
analystExcellent. I really appreciate it; that's everything on my end.
Alex Rygiel
analystHello. Fantastic quarter, and I appreciate you fielding my questions. There have been plenty of helpful responses already during this call, but I have several things to ask. Historically, do you typically run into any permitting problems that might hold up the beginning of projects?
Joe Cutillo
executiveOkay, so here's what I can share with you: getting permits approved right now definitely takes more time than it did before COVID. And honestly, even before COVID, I'd have said the whole thing was awful and dragged on forever, all right? Approvals absolutely move more slowly these days. But typically, on the site development portion, the hold-up we encounter isn't between signing contracts and breaking ground. It's more about the wait to actually sign those contracts, so we have visibility into upcoming work. We're confident we'll secure those projects, though it might not happen during the current month. Perhaps it slips to the following month, or it could land outside this quarter and fall into the one after. Looking back, we've never really experienced a situation where equipment sits ready, our team is set or already on location, and then we get stalled. So luckily for us, the point where this occurs in our workflow is usually prior to kicking off. That said, I can share that based on past data, something that once required six weeks to permit now demands three months. In some markets, possibly five. So that early-stage component is pushing things back. That's also part of why certain mega projects take forever to actually begin. Take these chip plants—we're aware they exist; we're aware they're on the way. Yet they're still working through plenty of permitting, securing utilities, and utilities need permits plus other things, correct? So it sort of snowballs; it's absolutely a major bottleneck. I'll say this, and I've said it to everyone: if the U.S. wants to speed up onshoring, reshoring, chip plants, whatever kind of build it is, provided they could resolve the regulatory and permitting hurdles, that would accelerate these projects along with spending and funding at an exponential rate.
Alex Rygiel
analystDouble. And then within building solutions, are you seeing any signs of green shoots?
Joe Cutillo
executiveMy apologies. Could you repeat that?
Alex Rygiel
analystWhen it comes to building solutions, is there anything you're noticing that suggests 2026 might begin turning upward once more?
Joe Cutillo
executiveHonestly, our view is that nothing will likely occur before the second half of 2026. Rates are still drifting lower, it's true. There are many programs that builders currently have running; what we've observed is a leveling off, all right? Conditions aren't deteriorating. That's the positive part; even so, nothing we've seen suggests an increase is coming our way in the near term.
Alex Rygiel
analystI really appreciate it.
Joe Cutillo
executiveThanks. I want to thank all of you once more for being on today's call. Should you have any additional questions you'd like to follow up on, or if setting up a call is something you'd like to do, please reach out to Noelle Dilts, or the contact details are included in our earnings release. I hope everyone's day is a great one, and thanks for spending your time with us. Thank you.
Operator
operatorEveryone, that brings today's conference call to an end. We appreciate you joining us, and we request that you please hang up your lines.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Sterling Infrastructure, Inc. transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →This call discussed
For developers and AI pipelines
Programmatic access to Sterling Infrastructure, Inc. earnings transcripts and 132,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Sterling Infrastructure, Inc. or any ticker on your watchlist.
StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.