Sterling Infrastructure, Inc. (STRL) Earnings Call Transcript & Summary

February 26, 2026

NASDAQ US Industrials Construction and Engineering earnings 52 min

Earnings Call Speaker Segments

Noelle Dilts

executive
#1

Hello, everyone, and thanks for being with us this morning as we kick off Sterling Infrastructure’s Fourth Quarter and Full Year 2025 Earnings Conference Call and Webcast. It’s a pleasure to join you today alongside Joseph Cutillo, who serves as Sterling’s Chief Executive Officer, and Nick Grindstaff, Sterling’s Chief Financial Officer, to go over what we’ve achieved. Joe is going to begin by giving a look at the business and how it did during the quarter. After that, Nick will walk through the numbers and our 2026 guidance, and then Joe will come back with further thoughts regarding our markets and what lies ahead. Following that, we’ll take your questions. Just a quick note that slides are available in the Investor Relations area of our site; those slides contain information about our full year 2026 financial guidance. Ahead of handing things to Joe, I’ll go through the safe harbor statement. Today’s conversation might contain forward-looking statements. It’s possible actual outcomes will vary materially from what is said today. For a fuller explanation of risk factors that might impact these projections and assumptions, kindly look at Sterling’s latest 10-K and 10-Q filings. No obligation is taken by the company to revise forward-looking statements because of fresh information, later events, or anything else. Also, please be aware that management could mention EBITDA, adjusted EBITDA, adjusted net income or adjusted earnings per share during this call, all of which are financial measures not recognized under U.S. GAAP. In line with SEC rules and regulations, reconciliations of these non-GAAP financial measures to their closest GAAP counterparts appear in the earnings release we put out yesterday afternoon. When we talk about any results today, including revenue and backlog, we’re citing figures that have been adjusted for prior periods to match the current accounting of our RHB JV, except where stated otherwise. I’ll now hand the call over to our CEO, Joe Cutillo.

Joe Cutillo

executive
#2

Thank you, Noelle. Good morning to all of you, and I appreciate you being on the call for Sterling's earnings discussion covering both the fourth quarter and the complete 2025 fiscal year. To begin, I want to express gratitude to our team for another remarkable year in 2025. We posted robust top-line expansion exceeding 32%, along with growth in adjusted diluted EPS of more than 53%. That marks the fifth year in a row where our adjusted EPS climbed by over 35%. For the full year, gross margins came in at 23%, while adjusted EBITDA margins surpassed 20% for the very first time in company history. These margin levels demonstrate how we keep concentrating on seeking out the opportunities delivering the best returns. On top of that, cash from operations stayed robust, totaling $440 million. We're happy to walk through these results with you today, yet we're even more enthusiastic about what lies ahead. The Sterling Way — our dedication to caring for our people, our environment, our investors and our communities, as we strive to build America's infrastructure — continues to serve as our guiding philosophy while we carry out our strategy and expand the business. Turning to how we performed in the fourth quarter. Revenue rose 69%, powered by a 123% jump in E-Infrastructure Solutions and 24% growth in our Transportation Solutions. Organic growth during the quarter came to 36%. Adjusted earnings per share increased 78%, reaching $3.08, and adjusted EBITDA climbed 70% to $142 million. In addition, cash flow from operations in the quarter was once again quite robust, hitting $186 million. Our backlog situation and clear visibility give us confidence going forward. Signed backlog as of quarter-end amounted to $3 billion, up 78% compared with the close of 2024. Looking at same-store figures, backlog rose by roughly 50%. Once you factor in our unsigned awards totaling $301 million, plus a pipeline of future phase opportunities that has now grown beyond $1 billion, we can see a pool of potential work nearing $4.5 billion for Sterling. Now let me go into our segment performance for the full year and the fourth quarter in greater depth; within E-Infrastructure, full year revenue expanded 59%, which includes 40% organic growth, and adjusted operating income increased 67%. Adjusted operating margins hit close to 25%, representing a gain of over 120 basis points. This resulted from our move toward large mission-critical projects, where our excellent project management and capacity to complete jobs on or ahead of schedule is incredibly valuable to our customers. During the fourth quarter, revenue increased 123%, with 67% organic growth included. The data center market, once again, served as the main growth engine for the quarter. Beyond that, our efforts to expand geographically are truly delivering results. Our Rocky Mountain site development operation, focused exclusively on mission-critical work, expanded by more than 150% versus the same period a year earlier. Adjusted E-Infrastructure operating income rose 91%. Operating margin for the legacy E-Infrastructure site development business was unchanged from prior year levels. Margins keep gaining from our emphasis on large mission-critical projects and solid execution. CEC, which we acquired, is doing extremely well. During the quarter, revenue at CEC rose 21% compared with the fourth quarter of the prior year, and margins came in right where we expected them. The Texas market especially is performing strongly, and we keep seeing enormous opportunities ahead in both electrical and site development. Our multiyear visibility, along with the E-Infrastructure business, continues to be excellent. When we add together our E-Infrastructure signed backlog, unsigned electrical awards and future phased site development opportunities, the total came to over $3 billion. At year end, mission-critical work — data centers, large manufacturing projects and semiconductor — accounted for 84% of E-Infrastructure signed backlog. The future phase work mostly involves mission-critical projects. Now on to Transportation Solutions. For the full year, revenue was up 17% and adjusted operating profit was up 66%, powered by strong market demand and the favorable impact of mix toward higher margin services. In the fourth quarter, revenue rose 24% and adjusted operating profit climbed more than 100%. We closed the quarter with Transportation Solutions backlog of $1.1 billion, an 81% increase year-over-year, thanks to strong award activity and unsigned backlog converting into signed backlog. Turning to Building Solutions, full year revenue fell 6%, and adjusted operating profit fell 23%. During the fourth quarter, segment revenue dropped 9% and adjusted operating margins were 10%. Overall demand for homes has taken a hit as potential buyers grapple with affordability challenges. Despite the headwinds in Building Solutions, the strength of Sterling's diversified portfolio and its strategy of focusing on growth in high-margin end markets let us deliver yet another fantastic year. With that, I'd like to hand things over to Nick, who will give you more detail on some of our financial metrics and the 2026 guidance. Nick?

Nick Grindstaff

executive
#3

Appreciate that, Joe, and good morning to everyone. First thing I want to do is walk you through the backlog numbers on a consolidated basis. When the year closed out, backlog stood at $3 billion. That represents a 78% increase over where we ended 2024, and if CEC is taken out of the picture, the gain is 49%. Turning to combined backlog, we finished at $3.3 billion, which is 81% higher than the previous year-end, or 42% once you back out CEC. Looking at Q4 of 2025, the book-to-burn ratio was 1.64x for backlog, while combined backlog came in at 0.81x. Let me shift now to cash flow. Our operating activities delivered a robust $440 million in cash flow during 2025. As we look ahead to 2026, we expect operating cash flow to remain solid, both in the legacy operations and in the businesses we've recently brought on board. On the investing side, capital expenditures took up $77 million in cash, while acquisitions — CEC included — accounted for $482 million during 2025. As for 2026, we're projecting CapEx somewhere in the $100 million to $110 million range, and that increase reflects spending designed to drive growth and productivity. Over in financing, we saw $162 million flow out, largely because of $74 million spent buying back shares at an average of $168.72 apiece; in the quarter itself, $26 million went toward repurchases at an average price of $310.09 per share. Under the repurchase authorization we already have in place, $374 million remains available. We'll continue to approach buybacks opportunistically. And when it comes to the balance sheet, we're in excellent shape. We closed the quarter with $391 million in cash and $291 million of debt, giving us a cash net of debt balance of $100 million. On top of that, our $150 million revolving credit facility went undrawn during the period. With our strong liquidity, we are well positioned to keep capitalizing on both organic and inorganic growth opportunities in the years ahead. Now I'd like to talk about our guidance. With our current backlog, visibility and strong market tailwinds, we are set up well for another great year ahead; we are initiating the following guidance ranges for 2026. Revenue of $3.05 billion to $3.2 billion; diluted EPS of $11.65 to $12.25. On an adjusted diluted basis, we expect earnings per share between $13.45 and $14.05. EBITDA should land in the range of $587 million to $620 million, while adjusted EBITDA is projected at $626 million to $659 million. If you look at the middle of each of those ranges, every one of these metrics shows robust growth versus last year of at least 25%. At this point, I'll hand the call over to Joe.

Joe Cutillo

executive
#4

Thank you, Nick. When we think about what lies ahead, our confidence stays extremely high regarding the multiyear potential across every market we serve. A robust backlog, upcoming phase possibilities, and discussions held with our main clients about how large future projects will be and how many there will be—all of this feeds into that confidence; within E-Infrastructure, specifically site development, we expect the present momentum in data center need to keep going for as far out as we can see. For a while now, we've been talking about being in talks with our clients concerning the best way to assist them with their substantial multiyear capital spending plans. Because of this, we're being drawn faster into additional regions, such as Texas and the Pacific Northwest. On top of that, the jobs we take on are growing bigger and stretching across extended timelines. When it comes to semiconductor and manufacturing, a sizable collection of mega projects is still out there waiting in the latter half of the decade. Planned semiconductor fabrication plants would fall under this. Our view is that a number of these efforts are nearly ready to move forward and will be granted in 2026; regarding E-Commerce distribution, awards picked up considerably during 2025 when major clients resumed their investment initiatives after the build-out and correction that followed COVID; we think that same drive will carry forward into 2026 as those programs speed up. Taken together, these forces throughout our end markets underpin robust expansion possibilities across a multiyear stretch; we carry really solid momentum in our Electrical business heading into 2026. Client need is extremely robust, especially within the Texas data center sector. We feel a great deal of certainty about our capacity to harness the blend of our site development alongside electrical services to fuel growth and margin gains throughout the platform. Looking at 2026, we anticipate delivering E-Infrastructure revenue growth at 40% or above. That figure encompasses 20% growth or above within the legacy business. Adjusted operating profit margins for the E-infrastructure should land somewhere between 23% and 24%. Over in Transportation Solutions, we've reached the last year of the present federal funding cycle, wrapping up in September of 2026. We've accumulated more than 2 years of backlog and keep witnessing healthy amounts of bid activity. For 2026, we expect ongoing expansion in our primary Rocky Mountain market. The scaling back of our low bid heavy highway operation in Texas is unfolding as intended, bringing about a degree of softening in Transportation Solutions' top line and backlog, which ought to keep pushing margin gains forward as the year goes on. We look for Transportation Solutions revenue growth in the low to mid-single digits during 2026, along with ongoing margin growth. Turning to Building Solutions, we feel the business sits in a strong spot to expand across a multiyear span. Our primary regions—Dallas Fort Worth, Houston, and Phoenix—are each projected to experience population gains, fueling demand for new homes. Beyond that, there's a chance to capture share as we emerge from a down cycle. Looking at the short term, we expect today's soft market conditions to persist. For Building Solutions, we expect revenue to fall somewhere between a high single-digit and low double-digit percentage decrease in 2026, while adjusted operating margins should stay within the low double-digit range. Keep in mind that when it comes to seasonality, the fourth and first quarters are generally slower for us compared with the second and third, and the first quarter is usually the weakest one of the year. When it comes to acquisitions, we remain on the lookout for deals that fit well strategically and would strengthen both what we offer in services and where we operate geographically. Compared with twelve months ago, we're now seeing a greater number of high-quality acquisition candidates in the market. Now on to our guidance for the full year 2026. At the midpoint of our guidance range, that would work out to 25% growth in revenue, 26% growth in adjusted EPS, and 28% growth in adjusted EBITDA; with that said, I'd like to open things up for questions.

Brian Brophy

analyst
#5

I wanted to ask, I suppose, about the transportation awards and the backlog. It looks like that came in much stronger than most people had anticipated. Is there anything worth pointing out? Did any sizable awards stand out?

Joe Cutillo

executive
#6

Yeah. Brian, thanks. There's nothing specific. No single massive project or anything like that. What I think folks often mix up is that although we're nearing the close of a funding cycle, roughly 50% to 60% of the overall funding has been used. So solid bid activity will keep coming our way all the way through that September period, since projects continue to be let, and those will clearly be constructed over some stretch afterward. So we're feeling really good about our position, and we're happy with the bid activity. No big items, really just nice singles, doubles, and occasionally a bit of a triple as things move along. But I'd also like to remind you and everyone else that when a funding cycle wraps up, the world doesn't come to a halt. It isn't a toggle switch. Typically, if the next funding bill isn't in place, they'll extend the funding bill that already exists. Historically, they've generally adjusted that for inflation. Consequently, bids will keep appearing.

Brian Brophy

analyst
#7

Yeah, that helps. So I suppose, just to follow up on that, you mentioned this somewhat in your opening remarks, but I was hoping you might go into a bit more detail. Could you give us an update on how things are coming along with site preparation work as you move into Texas? And how is it going combining that with the joint awards over at CEC?

Joe Cutillo

executive
#8

Yeah. The Texas market has us genuinely enthusiastic, first because of what we're observing from the CEC angle when it comes to electrical and data center growth. Second, though, the site development side is pulling us in extremely fast. My sense is that during the first half of this year, we'll be in a position to discuss some really strong awards happening in Texas. And I'd say we've been — this is my own view — running ahead of schedule and feeling more upbeat regarding how powerful it is to bring these 2 things together, along with the feedback we're getting from customers; so the thesis proving out pleases us greatly; and I expect we'll witness some excellent activity during the first half of this year that leaves everyone pleased.

Brent Thielman

analyst
#9

Nice quarter, everyone. Joe, perhaps building on what Brian asked, could you expand a bit on how the pipeline at CEC has changed since the acquisition? Are the award opportunities becoming much larger? And maybe you could share what you're currently doing or observing that could justify a higher margin threshold for that business going forward?

Joe Cutillo

executive
#10

Yeah; we are — the projects are becoming significantly bigger. Those data centers over in Texas, at our latest leadership meeting we were joking around, our team said, keep in mind when we were thrilled, we landed that initial 100-acre data center. That was only a few years back; and we replied, yeah, we figured it was the largest project and all of that. And they responded, yeah, we've just broken ground on one in Texas and the parking lot alone is 100 acres, right, kind of gives you a sense of scale; these facilities keep growing and growing, and featuring more and more — they're no longer data centers, they're data campuses. I believe folks get mixed up regarding that, and we'll have several buildings situated on them. CEC has achieved excellent momentum and together, the site development CEC are gaining excellent momentum. We're noticing margin gains in a few areas. Naturally, as CEC shifts a greater portion of their mix toward data center, those margins have traditionally been stronger than the smaller industrial commercial type jobs. But also as we're merging the exterior electric with the site development. We've already witnessed notable margin gains from that small dry utility business we acquired in Georgia last year. And precisely the same outcome will occur with CEC over time. So we're in the early stages of moving into those projects. That's why I say, I believe we'll witness some excellent progress during the first half of this year, and we'll begin to see some of that effect as we reach the second half of this year.

Brent Thielman

analyst
#11

Okay, got it. Then perhaps regarding margins from the legacy site development work, like you said, they're kind of level right now and clearly at strong levels. Joe, could you explain why we shouldn't assume they've topped out here?

Joe Cutillo

executive
#12

My apologies, Brent — I didn't catch that correctly. What you're asking about is site margin — margins for site development during the quarter. We don't anticipate those turning negative. That much is certain, particularly since we're seeing bigger and bigger projects come through. On top of that, in the Northeast we're finding certain opportunities involving larger projects, which should push their margins up considerably. One item we'll be discussing increasingly — just like we mentioned in the script, our Rocky Mountain site development business expanded 150% year-over-year. That has us genuinely thrilled. However, something that drags down our margins in that region is that we typically run a somewhat smaller and distinct equipment suite compared with what we deploy on the East Coast. So we'll be putting capital in and doing some alternative capital planning, which we believe can raise their margins quite a bit too, simply by replicating precisely what we do in the Southeast and on the East Coast. Beyond that, from a strategic standpoint, we'll keep exploring additional vertical integration. Vertical integration offers certain leverage and productivity gains. When we enter a new geography, that isn't our starting point; we sort of test the waters, get involved in site development, and carrying that out gives us room to assess some of those players in the vertical integration space, then choose the strongest ones. And over the coming 12 to 18 months, you'll see us folding in some of those across the U.S. Still, I'd like to make one additional point regarding your CEC question, about how quickly they're expanding and all of that. I'd say that if I had another 1,000 electricians in Texas — and I actually have a much larger figure — I believe we could have them working within 30 days or fewer; however, when we acquired CEC, they possessed a modest modular build facility. We're currently in the progress — the process of signing a lease that's triple that size; this will additionally boost their margins, allowing us to begin prebuilding more under factory conditions and then ship those out to the field.

Manish Somaiya

analyst
#13

Nice work on the quarter. I have a few questions. Perhaps we can start with Joe — you mentioned $1 billion of future phase work with high probability. Could you tell us whether that involves customers or programs you already have? Or is it entirely new? And what should we expect regarding the conversion window?

Joe Cutillo

executive
#14

Sure — first off, that $1 billion-plus relates to projects we are actively engaged in right now. So this is genuine work. That's the minimum required to complete those projects. As you may recall, while they keep designing, they put out that work as a package. We completed that next phase of work, and then we carry it out. So it's quite solid; technically we can't label it backlog, but for us, when it comes to capacity planning and everything else, it functions as backlog. It involves existing customers, though we do pick up a new customer occasionally. So we aren't focused only on 1 or 2; however, the vast majority of it sits with the big name hyperscalers that everyone is familiar with, all of whom have publicly shared their budgets, plans and future forecasts, and those are all up considerably. I can tell you that when we look forward over the next 3 to 5 years, and collaborate with them on their planning, we don't see any slowdown. If anything, we keep seeing it speed up.

Manish Somaiya

analyst
#15

Next, I have something to ask Nick. As the E-Infrastructure business grows larger, what's the right way to consider spending on working capital and the conversion of free cash flow?

Nick Grindstaff

executive
#16

Sure. So we're anticipating that our conversion of free cash flow stays solid. To be cautious, we're looking at free cash flow versus EBITDA somewhere around 80%, and that figure is a cautious one. And as we go deeper into E-Infrastructure across the year, we anticipate that will hold.

Manish Somaiya

analyst
#17

All right. Turning it over to Joe again. When we consider how capital gets deployed, Joe, you brought up that clearly there's a buyback running actively — $400 million started in November of last year. You brought up M&A. You said quality assets are starting to appear, which caught my attention since it's been a while since I heard that. Sure, multiples are elevated; but perhaps you could share how you're ranking your priorities. Should we view that as a fourth leg for Sterling? So how are you weighing allocation — capital deployment, M&A, a fourth leg — and what explains this wave of attractive acquisition targets, because that's come up on a few calls now and it's struck me as somewhat unexpected. Please walk us through it.

Joe Cutillo

executive
#18

Yeah, our emphasis isn't really going to land on a fourth leg. What it comes down to is, when we pull back and examine data centers, semiconductors, pharmas that are emerging along with other manufacturing that we're seeing, plus longer-dated projects. At present, over the coming 5 to 7 years, the strongest returns for us will come from how we grow, how we extend solid services and geographic reach inside the infrastructure. That isn't to say we wouldn't — should the correct fourth leg present itself, we would pursue it aggressively; but at present, the chances sitting in front of us and what our core customers keep requesting, in terms of locations that extend to services to deliver over the next 3 to 5 years, truly keeps us centered on pursuing that geographic build-out of site development and additionally added electrical reach along with services and skills, and we'll be examining mechanical as we go too, as a sort of organic next step. So that's where our attention sits. Why do I believe more quality businesses are available on the market. I'd point to 2 things, multiples have definitely risen somewhat for those businesses. But second, I believe many of these owners recognize this enormous opportunity in front of them, and they lack the capital to fund the growth and they sense they're going to let the opportunity slip. And honestly, without partnering with someone large, they'll wind up on the outside looking in and eventually forfeit that work; so they've been in this industry a long time, and this is unlike anything any of us have witnessed in our careers in terms of the — it isn't billions. I believe it will reach the trillions of dollars of infrastructure spending headed our way, whether that's our yellow iron or our electrical skills or some of our other areas that feed into it.

Alex Rygiel

analyst
#19

Regarding manufacturing, high-tech, and fabrication facilities, could you assist us in getting a sense of how large that potential market might be in the years ahead?

Joe Cutillo

executive
#20

Sure, let's begin with semiconductors. I hold the view that we're in the early stages of that sector. Given how long the announced capital expenditure takes before a project is ready to break ground, my expectation is that no significant semiconductor phase will arrive until around 2030. In the interim, though, several projects will land soon. For context, a data center project typically runs about 3 years on average for us. By contrast, an upcoming semiconductor facility will run closer to 7 to 10 years, and rather than hundreds of millions of dollars, the overall scope for those could reach $1 billion. That's quite substantial for our company. On the pharma side, multiple facilities have been announced across the country. Once more, don't be misled — between the announcement and any actual activity, 3 to 5 years will pass. That's simply the cycle: acquiring land, permitting, getting utilities installed. Equipment must be purchased, and often it's specialized equipment with no fast turnaround. Depending on the parts and components involved in the industry, lead times range from 2 to 5 years. So we anticipate all of this arriving. Simultaneously, I'd note that our data center clients aren't easing up across that same period. They're discussing larger builds, additional builds, and collaborating with us to lock in capacity and capabilities. Furthermore, when you observe our geographic expansion occurring over the next 12 to 18 months, it isn't necessarily due to something existing there now. It's because we anticipate future demand, and we're partnering with our customers to be ready. As for the Texas market, it's extremely hot, to put it mildly. What's happening in Texas is incredible; we're pursuing it from the East and from the West. Plus, our CEC business sits right in the middle of Dallas; we feel extremely confident about what Texas will contribute to our company over the next 3 to 5 years.

Louie DiPalma

analyst
#21

Joe, on earlier calls you talked about Sterling moving into West Texas. Could you go further and tell us whether you can expand into Texas to serve additional important markets? I recall you mentioning that you're coming at it from both the East and the West. Have you already secured work on Texas's eastern side and in other markets throughout the state?

Joe Cutillo

executive
#22

Yes. Let me address the East approach, the West approach, and then the market, all right, just so I don't add to any confusion. West Texas is expanding at a very fast pace. And I'd say we are busy winning and working on jobs in West Texas that we will be in a position to announce during the first quarter. What we think of as East is roughly Dallas, Houston, that corridor — not East Texas, which is the piny forest. Not much is happening there at this point. Perhaps that will change; but when I describe coming at it from the East and coming at it from the West, we are leveraging our plateau business to begin reaching what we refer to as East Texas. So in that Dallas market, there's activity up in Oklahoma in the near future that's coming out; and then, believe it or not, what surprises most people is that Houston to West Texas is nearly the same distance as Salt Lake City to West Texas. That's how large the state is. We're coming at the West by using our Rocky Mountain resources and assets. And we'll be pursuing strategic acquisitions obviously, inside Texas or in closer proximity to keep adding assets and resources and capability and capacity. Does that answer it?

Louie DiPalma

analyst
#23

Yes. That was great, Joe. So for 2026, should investors see it as a year when your geographic expansion focus is mainly Texas? Or can you potentially move into other data center and mission-critical geographies in 2026 that sit outside both the Southeast and Texas?

Joe Cutillo

executive
#24

Yes. My view is that during 2026, those areas will account for the biggest portion of data center growth; even so, there is decent activity happening right now up in the Northeast. It's still early. Some projects up there have us excited. We will — regarding the 2 other markets that exist, in one of them, I believe, during 2026, you'll see us begin shifting more assets and resources toward the Pacific Northwest. And once more, several projects up there will likely be released in '27, and those could be very exciting for us. . The market we still haven't worked out how to enter is sort of the Ohio, Indiana market. For us, that's always a possibility. I won't claim we're on the 10-yard line of getting in there or anything like that, but that's another fairly sizable market. Yet when I step back and simply look at the Southeast, a few of the projects up in the Northeast and Texas, you've got the biggest portion of the new stuff coming out, at least with our core customers, and the size of those projects really matches our profile, unlike when you get into mid-Atlantic, where there's a lot of number of data centers, but they're small and just don't necessarily fit our profile.

Louie DiPalma

analyst
#25

And a last question tied to what we've been discussing about your move into new regions. Would it be fair to think that operating margin profitability there will come in below what you earn in the core E-Infrastructure mission-critical segment, so that those of us on the sell-side and in the investor community ought to factor in some drag when modeling expansion into Texas and into the Northwest? Or what's the right way to think about it?

Joe Cutillo

executive
#26

Yes. I'd say it depends — take moving an equipment suite from the Southeast over to Texas: margins come out identical; in our Rocky Mountain region we've posted somewhat lower margins, with pricing the same and the process the same, and that's not a market issue, it's simply that we're still ramping that equipment profile. Keep in mind, we converted highway assets and a few large assets to get them going, and as that build-out continues, those margins will rise. The place we'd notice it — and I believe we will notice it — is on acquisitions: most of them carry somewhat thinner margins than we do, correct? Still, we're confident that once those acquisitions sit inside our footprint, and we bring in our processes, our procedures, our technology and so forth, we can keep lifting those margins until they match ours; and yes, one more thing to remember, Louie — our margins, sorry, our projects, remember, the multiphase ones run anywhere from 3, 5, 7. They always open at a thinner margin, and those margins get better through productivity and what we can accomplish by staging earlier phases to support productivity later on.

Adam Thalhimer

analyst
#27

Solid quarter. Joe, could you elaborate on the CEC modular expansion? I'm wondering what square footage that gets you to? And which parts are done modularly as opposed to on-site?

Joe Cutillo

executive
#28

Sure. The way we look at it simply is that we aren't alone in doing modular work, but whatever we're able to remove from the field through prefab and bring into the field cuts down on how many electricians are required at that site, correct? Yet at the same time it boosts productivity along with cost. So the new facility exceeds 300,000 square feet. What I can share is that we're evaluating whether it makes sense, or does it, to run multiple facilities across the U.S; those could produce these components. So we handle all of it, from the exterior piping and conduit surrounding the duct banks through to the actual cabinets installed in these centers. And we're examining ways to keep growing that capability and expansion. It's quite exciting since it really — once you calculate it, it's substantial in terms of what capacity it unlocks and how it benefits your margins in a positive way.

Adam Thalhimer

analyst
#29

Future of construction.

Joe Cutillo

executive
#30

What's that? .

Adam Thalhimer

analyst
#31

So, regarding what's ahead for construction.

Joe Cutillo

executive
#32

Yeah, I believe we're going to observe, whether it involves our company, our sector, or other sectors, that modular work will keep expanding, since the available workforce keeps shrinking further and further; that's simply the most sensible approach.

Adam Thalhimer

analyst
#33

And finally, I was curious to hear your thinking regarding the residential bid. And given that multiples could be more depressed, does pursuing an acquisition in that space make sense? Or is it better to simply let things unfold?

Joe Cutillo

executive
#34

Yeah; and we don't — I wish I could say there's light on the horizon. My sense is it will be difficult, definitely the first half of 2026. Honestly, there's nothing positive happening right now that would ignite or drive a rebound in the residential segment. And I want to give everyone a heads-up: once a recovery does arrive, those builders will first work through the three to four months of inventory already sitting out there before we'd start to observe fresh construction getting underway — right? To me, that's just reality. Still, you're pretty close to the mark. What I'd add is this: should the right acquisition present itself on the residential side, and multiples have come down. Also, even though their profits have declined, our outlook over the long run is positive. When we reviewed Tealstone's performance after the previous slump, we saw that they gained a substantial portion of the market during the recovery phase, and we believe we will do the same as we emerge from the current situation, particularly in Houston and Arizona. So, should we identify suitable acquisitions, we wouldn't avoid them, provided we secure them at a very steep discount. And 18 months from now, we'll appear quite clever.

Julio Romero

analyst
#35

I'd like to keep talking about how these projects are growing larger. Like you mentioned, Joe, they aren't just data centers now. They've become data center campuses. With these mission-critical efforts expanding in scale and complexity, does the balance between above-ground construction and underground infrastructure shift in any way? And if there is a shift, does that change in mix help margins?

Joe Cutillo

executive
#36

Yeah. We — I can't say we've noticed any meaningful change between above ground and below ground. My sense is that the coming generation of these efforts will include self-power generation; that's going to open up additional development possibilities for them, since when you've got a power plant, you've got everything underground, be it water utilities, you've got the electrical service coming in, all of that. So our view is that both the size and scope of these efforts will increase, not just in physical dimensions, but the volume of things we'll work on will keep expanding. Those efforts truly won't begin until '27 or '28. We might see a single one this year, but that's the biggest portion; yet it also creates chances to examine other goods and services we could bring into those efforts.

Julio Romero

analyst
#37

Understood. If the composition inside mission-critical starts shifting over time toward semiconductors and advanced manufacturing, does anything change?

Joe Cutillo

executive
#38

Yeah. No, the difference isn't huge. Clearly, data centers have duct banks, but what folks fail to appreciate is that every one of these sites contains, quite literally, thousands of miles of buried pipe, wire, and so on — it's a city beneath the ground. So from our standpoint, it doesn't worry us whether the mix tilts further toward chips and less toward data centers, or further toward manufacturing. Looking back, we clearly hold more information on the site development portion, yet margins have come in similar. That's what's great about our model. And with electrical now, plus our ongoing growth in electrical's reach and skills, what we offer can be swapped around. Truly — we — larger projects, clearly, suit us far better, yet whether it's a data center, a chip plant, a big automotive site, or a battery plant, we don't really mind.

Julio Romero

analyst
#39

That's really useful. Now I'd like to know where Sterling stands relative to other specialty contractors when it comes to AI-powered tools, given that adoption of those tools is spreading throughout the industry. Joe, what's your approach to keeping a step ahead of rivals? I'm sure a few of them would claim they're likely leveraging AI to close the reliability gap or perhaps the scale gap with Sterling. How do you view Sterling's position in that setting? And might you leverage these tools to potentially extend your differentiation relative to some of those peers?

Joe Cutillo

executive
#40

Yes. Well, I definitely wouldn't have the visibility to do that. Where our peers stand, I have no idea. What I can share is where we stand. I believe folks would be amazed by what we've accomplished and what we're currently doing with AI and how we connect it not just to estimating and the bid process, but to project execution; last year we ran 3 pilots. To say the teams were thrilled when we initially — when we initially launched them, everyone asked, how does AI apply to our work. Keep in mind, we're flying drones. We're running every sort of analytics on our equipment. We're now linking all of that into project management and accelerating outcomes. Just recently, remember, our capacity constraint in site development is project managers. And from our first AI project alone, we gained somewhere between 15% to 20% of incremental capacity on project managers. At present we have 6 AI projects in progress. So I'll tell you, when folks say, well, is AI genuine and all of that, my response would be that if companies like ours are moving very fast on this and our people, each time they interact with it, identify 4 or 5 additional things we can bring in that will boost the efficiency, the effectiveness, the quality, and equally important, there are some genuinely impressive things we're doing on the safety front with this that will help keep our employees even safer than they are today.

Joe Cutillo

executive
#41

Thanks. I'd like to express my appreciation to all of you for being on today's call. Should you have any questions afterward, please reach out to Noelle Dilts. You can find her contact details in the press release. I'm grateful for that. I'm grateful for what our team accomplished. It was another excellent quarter, and enjoy the rest of your day.

Operator

operator
#42

Everyone, that wraps up today's conference call. We really appreciate you taking part. You can go ahead and hang up now. Have a wonderful day.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete Sterling Infrastructure, Inc. transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

This call discussed

For developers and AI pipelines

Programmatic access to Sterling Infrastructure, Inc. earnings transcripts and 132,000+ others is available through the EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research

OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Sterling Infrastructure, Inc. or any ticker on your watchlist.

StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.