executiveGood afternoon, everyone, and thanks for being with us on this call covering ACS Group's first quarter 2026 results. I'm Javier Crespo, Head of Investor Relations. Our CEO, Juan Santamaría, will lead today's call, and he's joined by our Corporate General Manager, Ángel García Altozano, our Chief Financial Officer, Emilio Grande, and the remaining members of the management team. After our CEO's presentation, as is customary, we'll open the lines for a Q&A session and we look forward to taking your questions. Juan, over to you now.
Juan Santamaría Cases
executiveThank you, Javier. Good afternoon, everyone, and thanks for joining us today. In the first quarter of 2026, the group kept delivering strong operational and financial results, with solid growth in sales, backlog, and net profit, supported by an outstanding level of cash flow performance. The quarter also brought further progress in our growth strategy, reinforcing ACS's position as a global engineering-led provider of end-to-end infrastructure solutions, with leading positions across rapidly expanding growth verticals, including AI, digital and tech, energy, critical minerals, and defense. The key results highlights are as follows: Operational net profit reached €239 million, up 25%, in line with the top end of the guidance range set for 2026, while net profit nominal stood at €232 million, up 30% FX-adjusted. Sales and EBITDA also showed solid growth, up 12.5% and approximately 16% FX-adjusted respectively, and supported by Turner's continued strong performance and the positive evolution of our strategic growth markets. Cash generation remained outstanding, with a last-12-months net operating cash flow of €2.3 billion, driving a €1.4 billion improvement in net debt year on year. New orders reached €17.5 billion, representing a 1.3 times last-12-months book-to-bill, a 20% increase FX-adjusted, while backlog approached €100 billion, up 13.5% and providing around two years of visibility.
Juan Santamaría Cases
executiveData centers are still a major growth engine for us, and backlog there has hit €19.4 billion — that's more than double what it was a year ago. On the shareholder remuneration side, I'd also point to the 20% bump in our 2025 dividend per share, which now stands at €2.40, as approved at the recent AGM. Going forward, ACS keeps up strong momentum, supported by our record backlog and wide exposure to markets where appetite for advanced infrastructure keeps speeding up. That diversified profile, together with rigorous risk management and a disciplined approach to capital allocation, strengthens the group's resilience and gives us a solid platform for creating long-term value. We reaffirm our guidance for operational net profit in 2026 of roughly €1,030 million to €1,070 million, which means growth of 20% to 25%. Now let's dig into the group's consolidated performance for the period. Sales climbed 12.5% FX-adjusted to €12.3 billion, powered by a strong showing in North America and continued expansion in strategic markets, especially digital infrastructure, which came in at €3.2 billion. EBITDA rose by nearly 16% FX-adjusted to €772 million, with margin expansion in every segment and at the overall group level. Profit before tax came to €410 million, up around 24% FX-adjusted. We posted strong operational net profit growth of 25% year on year, hitting €239 million, which is in line with the top end of our full-year guidance.
Juan Santamaría Cases
executiveOur backlog stands at nearly €100 billion, up 16% on a comparable basis — that's after adjusting for FX and the sale of 50% of UGL Transport — and it comes on the back of a last-12-months book-to-bill that keeps climbing, now at 1.3 times. All in all, this is a very strong start to the year, with growth across the main operating metrics and profitability continuing to improve. Turning now to what each business line contributed, the quarter's strong performance was driven by Turner and Engineering and Construction, both of which kept showing significant operational momentum. Turner delivered an outstanding performance, with attributable operational net profit rising 60% FX-adjusted to €143 million. That was driven by accelerated momentum in digital infrastructure and a continued uplift in margins. Engineering and Construction also recorded a strong contribution, with attributable operational net profit up 38% FX-adjusted to €67 million, reflecting a higher contribution from Flatiron-Dragados and a solid performance at HOCHTIEF Europe. CIMIC contributed €46 million, remaining broadly stable on a comparable basis. Slide 5 highlights the group's outstanding and sustained level of cash conversion. Net operating cash flow was €2.3 billion on a last-12-months basis. Pre-factoring, it amounted to €2.1 billion, which represents an increase of €471 million year on year.
Juan Santamaría Cases
executiveThat performance was underpinned by robust EBITDA generation — last-12-months EBITDA rose 16.7% — and by strong working capital performance. Within the quarter, working capital posted its usual seasonal outflow, yet with a substantial year-on-year improvement. Taken as a whole, cash flow performance keeps showing the quality of our profit growth and the strength of the group's operating model. Turning to the financial position, the group closed March 2026 with net debt of €1.5 billion, a strong €1.4 billion improvement year on year. That came mainly from the outstanding net operating cash flow generated over the last 12 months, which, together with financial divestments, supported continued investments in data centers and other strategic opportunities. Financial investments over the last 12 months include €508 million in data center projects, €200 million related to the Abertis capital contribution in the context of the A63 acquisition, €371 million in other infrastructure equity investments, and €204 million in M&A and others. On the other side, financial divestments included €428 million for the creation of the joint data center platform with GIP, €228 million from the sale of 50% of UGL Transport to Sojitz, and €300 million from the final settlement of the ACS Industrial transaction with VINCI.
Juan Santamaría Cases
executiveDuring the first quarter of 2026, our investments totaled €232 million, with €152 million of that going into data centers, and divestment proceeds brought in €536 million, which left us with a net cash inflow of €304 million. On top of that, €441 million went toward shareholder remuneration across the last 12 months. Turning to Slide 7, as of March 2026 our order backlog sits at an all-time high of nearly €100 billion. Driving that increase was a very strong order intake of €17.5 billion, which rose 20.3% FX-adjusted and produced a better book-to-bill ratio of 1.3 times on a last-12-months basis. This very positive performance shows the group continues to succeed in winning high-quality projects throughout our strategic growth markets, especially in AI, digital, and tech, where backlog has more than doubled year on year and now makes up around 21% of the group's total backlog. Other strategic growth sectors also remained strong, including defense, biopharma, health and education, energy, and critical minerals. Our backlog is in line with the group's strategic priorities, which strengthens the visibility and quality of future growth. In the slides that follow, we call out a selection of recent significant new orders that illustrate the progress we are making in scaling our capabilities across our key strategic growth verticals, while further reinforcing the quality, diversification, and resilience of our backlog.
Juan Santamaría Cases
executiveThey also show that we can reliably turn robust market demand into high-value opportunities, drawing on our engineering know-how, worldwide reach, and end-to-end delivery approach. I'll begin with AI, digital, and technology, where we keep extending our leading position. The global data center market continues to grow very strongly, fueled by surging demand for cloud services, AI workloads, and high-performance computing. As a global end-to-end solutions provider, the group possesses the resources and capabilities to meet this demand by drawing on its scale, long-standing ties with hyperscalers, worldwide sourcing know-how, and growing use of modularization and off-site manufacturing. In the period, Meta chose us as one of the key contractors for a $10 billion, 1 GW data center campus in Indiana, United States — a 4 million square foot state-of-the-art facility that supports AI and digital infrastructure workloads. We also won a data center contract in Malaysia for a 58 MW facility from a repeat client, which further reinforces our presence in Asia. In Europe, we were awarded construction of a 160 MW data center in the Netherlands, to be built in four phases. In the United States, we are also taking part, together with partners, in a $15 billion, 902 MW data center complex in Wisconsin, which forms part of the wider Stargate program.
Juan Santamaría Cases
executiveAlso, work has already begun at our data center in Alcalá, Madrid, which we are developing within our data center platform. On the whole, we keep broadening our footprint throughout the entire AI stack — data centers, semiconductors, and cloud infrastructure — and we have solid medium-term visibility backed by our order books and a growing pipeline. Energy infrastructure represents another important strategic growth vector for the group. Growing investment in energy security and the shift toward low-carbon systems is driving sustained demand for advanced energy infrastructure. ACS holds a strategic position across the entire energy value chain, from generation and storage through transmission and advanced technologies, backed by strong end-to-end capabilities and global engineering expertise. We hit a key milestone at the start of 2026, when we were chosen as part of Amentum's global delivery team for the Rolls-Royce SMR nuclear program, in which we will assume the strategic role in infrastructure management for deploying small modular reactors across the UK and the European Union. What is more, in the final quarter of 2025, we landed a major €685 million, 15-year framework contract at the Sellafield nuclear site in the UK. These awards strengthen our positioning across nuclear, storage, transmission, and renewables, building on our long-standing nuclear track record and supporting our strategy to expand across the nuclear value chain.
Juan Santamaría Cases
executiveMoving on to transport and sustainable infrastructure — for many decades now, this group has ranked among worldwide leaders in transport infrastructure and sustainable mobility, and the outlook is still highly favorable, backed by infrastructure stimulus programs and the necessity of modernizing essential networks. In Europe, we landed the following stage of Prague Metro Line D, a €1.2 billion project, along with Sweden's East Link high-speed rail project, a €900 million contract carried out under a collaborative model. In the United States, we keep growing our footprint through efforts like the Battery Park resiliency project in New York, a $1.7 billion climate resilience project. In Australia, we won the Perth Airport new runway project as part of a major joint venture. Within biopharma, health, and education, we maintain leading positions, underpinned by our technical capabilities, strong client relationships, and local presence. In the UK, we were awarded a €200 million PPP project for the University of Southampton. In the United States, we landed a $500 million Baptist Health hospital expansion in Florida. In Germany, we won the Max Rubner-Institut PPP project in Kiel, and we continue delivering hospital projects in Flensburg. Let me now move to critical minerals and natural resources.
Juan Santamaría Cases
executiveWe’re seizing on demand that keeps accelerating—driven by the energy transition, digital infrastructure, and defense—and through Sedgman and Thiess we’ve established a worldwide position in minerals processing and mining services. One core element of our strategy is our partnership with Vulcan Energy on the Lionheart lithium project in Germany, where we’ve acquired a 15% cornerstone equity stake and locked in an end-to-end role. We also landed an A$700 million agreement tied to the Eva Copper project in Australia, plus contracts in India that will help support building out zinc processing infrastructure. Now shifting to defense: infrastructure spending in that sector is projected to rise substantially across the globe, and ACS is strongly positioned, drawing on robust engineering capabilities and a demonstrated record of execution. In the period, we won a major contract for the German Armed Forces University campus in Hamburg—a landmark project that brings together our defense and social infrastructure expertise. In the United States, we were chosen for a global construction services program for the US Air Force. We were also awarded the modernization of the Čáslav military airport in the Czech Republic. Let’s now review performance by segment, beginning with Turner, which keeps delivering outstanding momentum and remains the primary engine of the group’s growth.
Juan Santamaría Cases
executiveSales rose over 25% on an FX-adjusted basis, hitting €6.5 billion, with data centers as a key driver and solid growth across pharma, semiconductors, aviation, and public buildings lending support. EBITDA climbed 53.5% FX-adjusted, and the EBITDA margin widened 72 basis points to 3.9%, which reflects Turner's end-to-end strategy, its emphasis on advanced tech projects, and higher value-added services. Operational profit before tax came in at €246 million, an increase of 56% FX-adjusted and well above the upper bound of the 2026 guidance growth range. Operational attributable net profit grew more than 60% FX-adjusted, to €143 million. Turner is also still showing very strong commercial momentum: new orders rose more than 48% FX-adjusted to €10.3 billion, pushing the order backlog to a fresh record of €42.3 billion, up nearly 34% FX-adjusted, and AI, digital, and tech now account for roughly 41% of Turner's total backlog. Now let me move to CIMIC, where performance remains solid and portfolio rebalancing is progressing further. Sales came to €2.4 billion, with a shift toward strategic growth markets — data centers in particular — offsetting the winding down of large transport infrastructure projects. EBITDA was broadly stable on a comparable basis, with margins up. Operational profit before tax hit €116 million, a 4.8% increase on a comparable basis, helped by margin improvements.
Juan Santamaría Cases
executiveOperational net profit attributable to the company rose 3% on a comparable basis, hitting €46 million. Our order backlog came in at €23 billion, a 7.9% increase versus a year earlier, while new orders totaled close to €3 billion, giving a book-to-bill ratio of 1.1 times measured over the last 12 months. Moving to the Engineering and Construction segment on Slide 17, sales grew 9.5% FX-adjusted to €2.6 billion, helped along by sustainable mobility and defense projects. EBITDA rose by nearly 24% FX-adjusted, and the EBITDA margin gained 75 basis points to reach 6.6%, powered by a strong contribution from Flatiron-Dragados and HOCHTIEF Engineering and Construction. Attributable operational net profit posted robust growth of 38% FX-adjusted, backed by a solid €3.5 billion in order intake, which produced a strong last-12-months book-to-bill ratio of 1.2 times. Backlog rose 5.3% FX-adjusted to €31.3 billion. Moving on to the Infrastructure segment on Slide 18, this segment posted an attributable net profit of €37 million for the quarter, up 3.3% year on year. Abertis EBITDA grew above 9%, lifted by positive traffic and tariff performance, while the contribution was offset by non-operational factors, including higher PPA depreciation. ACS Digital & Energy is now reported separately for the first time, including the equity accounting of the data center joint venture.
Juan Santamaría Cases
executiveDuring that time, it added €8 million to attributable net profit. Moving to the next slide, we examine Abertis in greater depth — the company turned in a solid operating performance during the first quarter of 2026. Revenue grew 6.4%, reaching €1.5 billion, and EBITDA climbed 9.1% to €1.1 billion. The EBITDA margin came in above 71%, an increase of more than 173 basis points. Overall traffic was up 1.4%, with especially strong gains in Spain, where traffic rose 6.4%; in the United States, up 4.8%; and in Chile, up 2.4%. Abertis likewise kept reaffirming its strategy of perpetual growth. In the period, it bought the remaining 48.8% stake in Abertis, the A63 toll road in France. More recently, Abertis announced a tariff renegotiation and a 19-year extension of the FARAC concession in Mexico. That comes on top of the 21-year extension and tariff adjustment at Fluminense in Brazil, along with earlier organic initiatives, such as the extension of Intervias in Brazil, Metropistas in Puerto Rico, Autopista Central in Chile, and Sanef in France. On Slide 20, we lay out several considerations regarding this important extension. Under the agreement, the concession will grow by 19.5 years, running until 2067, on an asset that produced roughly €550 million of EBITDA in 2025 and is closely tied to the US economy.
Juan Santamaría Cases
executiveTariff escalations are part of it too, tied entirely to CPI across the concession's duration, plus a €1.2 billion CapEx program spread over four years that will be entirely self-funded via local cash flows and debt. Through this deal, Abertis's average portfolio life goes from 12 to 15 years, and the RCO toll road network's EBITDA backlog gets a 78% lift as well. Slide 21 lays out, as usual, the key figures broken down by country for Abertis's portfolio. To wrap up our look at the first quarter 2026 results, allow me to point out the group's key achievements. We posted a solid operating performance, with operational net profit hitting €239 million, a rise of 25% year on year, matching the top end of the guidance range set for 2026. Once again the group showed outstanding cash performance, as last-12-months net operating cash flow came to €2.3 billion, an increase of €640 million year on year. Order backlog hit a fresh record of €99.8 billion, 16.1% higher FX-adjusted on a comparable basis. Worth flagging as well is the momentum in data center awards, where backlog stands at €19.4 billion, roughly 118% higher FX-adjusted year on year, with new orders more than doubling. Fueled by this data center build-out momentum, Turner remains a major engine of the group's performance, delivering operational PBT growth of 56% FX-adjusted and a Q1 EBITDA margin of 3.9%.
Juan Santamaría Cases
executiveTurning to Infrastructure, Abertis keeps strengthening its perpetual operator model. In Mexico, FARAC received a 19.5-year extension, which includes tariff increases. That marks a very important milestone and pushes Abertis's average portfolio life up from 12 to 15 years. Shareholder remuneration also stays a priority for us, as shown at our recent AGM, where a 20% DPS increase was approved, taking it to €2.40 per share. Going forward, we remain confident in our ability to keep executing our strategy, building on a very strong start to the year and clear momentum across our key growth platforms. We reiterate our operational net profit growth guidance of 20% to 25%, backed by the expansion of our end-to-end capabilities and our growing exposure to high-growth, higher-value markets. With a record backlog, a 1.3 times book-to-bill, and strong visibility, we are well-positioned to keep delivering strong and sustainable growth. Thank you once again for joining us today. We now look forward to your questions.
Operator
operatorEveryone, we're beginning the question-and-answer portion at this point. Should you like to pose a question, kindly hit star five on your phone's keypad. Thanks. Our first questioner is Graham Hunt. You may proceed.
Graham Hunt
analystGood afternoon, gentlemen, and many thanks for those questions. I have just two, both about cash flow, if that's all right. The first: clearly, this year has begun exceptionally strongly where cash generation is concerned, yet you have been turning in operational cash above expectations for quite a while now — arguably above even your own. I am simply trying to grasp, to dig a bit into, what lies behind that. Is it purely working capital arriving in greater volume thanks to the growth you are seeing, or is there also effort going on behind the scenes that is helping to genuinely deliver that operational cash flow ahead of where you perhaps had expected it? Then, following on from that, I suppose the question is: what will you do with that cash? If my memory serves, at your CMD last year you had a slide showing a pleasing balance between generation of operational cash flow and your infrastructure investments, but you are running, I think, well ahead of that operational cash flow element. As we consider where it goes, is there room to put it into more Greenfield, or ought we to read the rather substantial dividend increase you have announced as a signal of where that surplus cash might be headed?
Graham Hunt
analystThanks.
Juan Santamaría Cases
executiveThanks a lot, Graham. I'll begin with cash flow. Right — we generated very strong cash at the start of the year. Three factors are behind that, I'd say. First comes growth. Over the past 4 years we've grown very strongly, and we expect that growth to keep going. We have really good visibility into how that backlog and those new orders will perform over the coming years. Second, the projects, the contracts, the quality of the awards are strong as well. One of our big ambitions was making sure we could execute our projects with no surprises and secure contracts that provide value, with a very good balance and a risk-based approach to projects — and that lets us deliver without surprises, which also drives cash flow. Then there's probably some recovery of positions too. The key point is that what has pushed cash flows up to now will most likely keep pushing cash flows going forward. In that sense, we see no change. On firepower, we're talking about €1.6 billion with working capital at zero.
Juan Santamaría Cases
executiveAt the moment, what we consistently refer to is roughly €900 million of net operating cash flow annually after dividends are paid, since the 1.6 figure would take the payments into account. Strip out the dividends and you arrive at €900 million. As I recall, we multiplied that by five back then to reach €4.5 billion, and after that we added on the divestments — potential divestments, correct? That, I believe, is how we approached valuation in our CMD. Naturally, looking back — and I think we covered all of this during our earlier investor presentation — you could observe how we have handled those cash inflows and divestments relative to new investments. Going forward, the same approach will be applied. We think we will keep reaching €800 million each year, possibly more, so that will keep supplying us with substantial cash flow. We believe there are still potential non-core assets available, yet as things stand, our business plan does not require divesting them in order to hit our objectives. The potential acquisitions under consideration — be it data centers, be it Greenfield infrastructure, Abertis, etc. — fit inside the plan.
Juan Santamaría Cases
executiveWe’ll keep striking and maintaining that healthy balance between injecting operational cash flow and making investments. On the dividend side, our value proposition is always to preserve a really solid mix of shareholder remuneration and share price appreciation, correct? Naturally, all of that is underpinned by a resilient business that generates cash. The dividend was announced at €2.40 per share, and that figure includes both the February entry and the July complementary. Our policy will keep balancing that appealing shareholder remuneration against the rating — the investment grade rating — and our investment plans. We always put those three together. As I mentioned earlier, the robust cash generation is going to let us keep having all the cash we require for our continuous growth, right? We aren’t giving up, nor are we weakening that position, correct? We are accepting the €2.40 per share because we believe that despite that, our strong cash flows will allow the full growth potential we are seeking.
Graham Hunt
analystGot it, thanks Juan. Appreciate it.
Operator
operatorDario Maglione, we'll take your question next — go right ahead.
Dario Maglione
analystHello, and thank you for the presentation. Congratulations on such a strong set of results. I'd like to zero in a little on Turner, and in particular on the data center business inside Turner. Could you give us some more detail on order intake for data centers at Turner in Q1? Both what you booked during Q1 and also regarding the backlog of projects that have been awarded but aren't yet in the backlog. Then perhaps a question about the group guidance for 2026. After this very good Q1, especially on an FX-adjusted basis, that guidance does look increasingly conservative, particularly for Turner. Any thoughts on that? Maybe one last question, if I may, on the joint venture to build data centers. Is there any update on signing leases? Thanks. Thanks, Juan. Hey,
Juan Santamaría Cases
executiveThanks, Dario. I'll begin with Turner, and then get more specific about Q1. Looking back at last year, Turner closed out with a $16 billion backlog for the full year 2025. As of Q1 '26, though, Turner's data center backlog has hit $19.6 billion — and yes, we're talking in US dollars — so that's been really strong growth. What matters even more is that an additional $15.5 billion isn't in backlog yet — right, it's not in the backlog yet. That tells you Turner will keep expanding at an extremely, extremely, extremely rapid clip. Revenue came in at $10 billion last year for 2025, and overall we now expect to land somewhere around $18 to $19 billion this year. It's moving even faster than we had expected. We figured we'd get to 25 by 2030. My belief is that by the time this year ends, we'll be at roughly $17 to $19 billion — right? Data centers are moving very quickly. To be more specific on Q4, new data center orders came to roughly €5.7 billion, an increase of about 114.9%. Guidance was the next question. On guidance — well, first off, the numbers speak for themselves, right? Turner operational PBT rose 56% in USD during Q1, against guidance of 25% to 30%.
Juan Santamaría Cases
executiveNew orders came in above 48%. Turner was awarded projects worth roughly €23 billion, and over $15.5 billion of that was in data centers alone. On top of that, we're seeing efficiency gains keep building from Source Blue and greater modularization from XPL, which is essentially lifting margins, and margins will keep improving through the rest of the year. Yes, that's moving in the right direction. The one caveat I'd raise on Turner — and the reason we haven't raised guidance yet — is that margins climbed a great deal across 2025. Q1 was somewhat slow last year; it was up against the prior year, but over the course of the year it rose much more. Before we issue legal guidance, we want a clearer picture of where we might land by year-end, right? As soon as that's clear, we'll provide an update on Turner. Now let's turn to the ACS Group, right? Much the same story with ACS Group, right? Every business is delivering strongly, within or above guidance. Yes, it has been conservative. The only factor that kept us from upgrading guidance this time is geopolitical uncertainty and FX movement, right?
Juan Santamaría Cases
executiveAs soon as we get clarity on what's happening with the current geopolitical uncertainty—Iran in particular—and with how FX moves, we'll provide an update, right? The issue isn't really that we're avoiding raising guidance; it's that we have to be certain before we issue any new guidance that's legally binding. The last item concerns the GIP. Things there are progressing very, very favorably. On one hand, all 100% of the sites are now hooked up to the grid. 80% have a clear route to power—we hold all the permits—and we're wrapping up the final connections and infrastructure. We anticipate the first lease before the close of the first half of 2026. That matters a great deal, since we already have framework agreements in place with various prospective clients, and getting the first one over the line will unlock further positive news on the commercialization front. We remain on track to commercialize the 250 MW IT that we expect to bring to market this year, so that's proceeding as planned. Beyond that, and on top of the GIP platform, we keep advancing an additional 1.5 GW of projects outside the GIP platform for which we currently have the path to power, the permitting, and the connection—so that's quite encouraging too, and it has been developed out of the platform.
Juan Santamaría Cases
executiveThe third piece — edge data centers — is coming along nicely, and we should be in a position to share an update on that around Q2. Once we complete the initial sites and run them through all the testing, which is going extremely well, things will accelerate quickly when it comes to how many data centers we can construct, beginning in Europe.
Dario Maglione
analystAlright, that's very clear. Thanks, Juan. Thanks, Dario.
Operator
operatorAmal Patel, you have the next question — go right ahead.
Amal Patel
analystHello, Juan, and thanks a lot for the presentation. I have three questions, if I may. First, on the Turner order intake excluding data centers, what are you seeing for the rest of US non-res? There are clearly some economic worries, and the Middle East impact on inflation is affecting starts. Which pockets of the market do you think are speeding up, and which ones perhaps aren't performing as well? Second, on Dragados, the EBITDA margins: we saw a 60 bps expansion year-over-year, yet operational PBT margins were basically flat. Could you help me understand what's behind that, and what EBITDA margins should we expect for Dragados for the remainder of the year? Then my third question, if I may, is just on the capital contributions to Abertis: what can we expect for 2026, and I guess through the end of the decade? Thank you.
Juan Santamaría Cases
executiveThanks a lot, Amal. I’ll begin with the first question, which is specifically about Turner and the US economy. Data centers really are expanding a lot, correct? Take backlog alone: it rose 132.5%, and I realize you didn’t request that figure, but I’ll lead with it anyway. On order intake, it increased 114.9% compared with the prior quarter. What about the other parts of the business? Looking at backlog, we’re seeing commercial improve. It was up 65.3%. Around that, commercial accounts for roughly 11.6% of total backlog. As you may recall, that share stood far, far, far higher several years back. It used to be a major piece of Turner, and today it sits at 11.6%, which isn’t much, yet we do see a modest rebound from a market that was near 50% and fell all the way to 11.6%, and now it is rising. We’re also seeing plenty of aviation projects broadly. That area is up 15.8% to $2.7 billion in backlog, roughly 6.5% of the total. Then hotel and sports are somewhat flat, slipping a little.
Juan Santamaría Cases
executiveCertain government buildings are holding steady, up slightly, the same pattern as convention and conference centers. Moving on to biopharma, healthcare, and education: healthcare and biopharma remain strong, expanding roughly 20%, more or less — 17.4% for healthcare, 22% for biopharma. Healthcare accounts for 15.4% of our backlog, making it a significant piece of that backlog. Turning to semiconductors: this is an activity that keeps taking off. We're growing substantially. Even so, it was higher previously; at present it stands at 1.2%, though we think this is a space set to expand considerably over the coming years, correct? We're quite optimistic on that one. That's more or less the picture from a backlog standpoint, but it aligns with the analysis from an order intake standpoint. Dragados. Dragados, you're right. Looking at Dragados on an EBITDA basis, there was a 35 basis point expansion to 6.6% in EBITDA versus the PBT level, which rose 40 basis points. This was essentially — give me one second. I just want to confirm I have the correct figures. What I had in front of me was the Engineering and Construction. I needed to go specifically to Dragados on a standalone basis. Let me walk through Dragados isolated.
Juan Santamaría Cases
executiveSales rose 10.8% on an FX-adjusted basis. EBITDA climbed 23.1% FX-adjusted versus the prior year, and gross margin widened to 6.2%. Now, what happens with PBT — that's your question, correct? A few factors were at play. The first, chiefly, came via consolidating Flatiron-Dragados: several one-off impacts essentially got reversed. These aren't structural effects. They're one-offs, and they don't stem from projects or from project-related problems. They arise, quite specifically, from the Flatiron-Dragados consolidation. Then the final question concerned Abertis. Before I get into capital expansions — Abertis keeps developing extremely well, right? Our focus is always on those same metrics, though I believe they're worth restating. The net debt to EBITDA ratio moved from 6.6 to roughly 5.2. The EBITDA backlog — if you recall what I told you when we last spoke, at the end of last year in February — went from 3.4 times to 5.9 times against net debt. That was when we last spoke. EBITDA backlog against net debt, 3.4 times to 5.9 times — so that marked an enormous increase. Now, after FARAC, we see 10.4 times EBITDA backlog against net debt.
Juan Santamaría Cases
executiveThat figure is post-FARAC, post all the Brazil negotiations, and post some other organic renegotiations as well. All of this was accomplished with no additional equity, correct? More specifically on the FARAC extension, RCO's EBITDA backlog rose by 78%, and the average concession — I mentioned this in the presentation — moved from 13 to 15 years, and that covers the whole of Abertis. If we look at EBITDA by 2033 post Sanef, we're currently seeing something between €4.5 to €4.7 billion, which is an improvement over the €4 billion figures we provided the last time we updated Abertis at the CMD. That's broadly speaking. Now let's turn to additional equity. There are a few opportunities we're examining, okay? Ultimately, Abertis is progressing very, very well with some help from capital improvements, but more importantly through organic growth. That said, each year we review two, three transactions, right? If they make sense, we'll inject equity. If they don't make sense, we won't. Obviously, we always need a balance between how much we put into Abertis versus Greenfield managed lanes that deliver better returns versus data centers that deliver better returns, and all the M&A and bolt-on acquisitions we've completed in Engineering and Construction have delivered very good returns over the last four years, right?
Juan Santamaría Cases
executiveJust Flatiron tripled, but the experience has been more or less the same across the rest of the bolt-on acquisitions. As for Abertis, they really need to contribute in the right way and enhance these features. Do I believe there are opportunities over the next two years that we can take on and put additional equity into? Yes, I think so, but it's a bit too soon to walk through them.
Amal Patel
analystThanks a lot.
Operator
operatorMarcin Wojtal from Bank of America has the next question. Go ahead. Yes.
Marcin Wojtal
analystThank you. Good afternoon. I have three questions. First, if you'll permit me, I'd like to follow up on that €2.40 dividend. Could you clarify just what kind of formula was applied to set that exact level? And, more importantly, looking ahead, should we expect ACS to adopt perhaps a payout ratio or another formula for setting its yearly dividend? Or will it be decided case by case each year? My second question concerns your US exposure — obviously Turner and other businesses. I believe that accounts for over 60% of net profit. I was wondering whether you have any plans to step up engagement with US investors. And specifically, would you consider an additional listing of the ACS Group in the US at any point down the road? My third question, very quickly: could you remind us whether a capital markets day is planned for this year, and when that might potentially take place? Thank you.
Juan Santamaría Cases
executiveThank you, Marcin. Turning to the dividend: the €2.40 per share works out to roughly a 65% payout ratio. That ratio has always been one we were comfortable with, and we believe that level is reasonable. Obviously we're growing a great deal, and we have to weigh growth against dividend yield — it's a balance. We consider every opportunity. We look at, as I mentioned earlier, the cash flow coming in today and the investments, and we feel comfortable returning to this 65% payout ratio this year, as we did in the past. Yes, we're dealing with US investors. Yes, we see that the more we generate in the US and the more we invest in the US, the more appetite we get from US investors, especially as we keep growing across all the high-growth areas — not only data centers, but digital in general, critical metals, energy, defense, etc. Obviously the listing is in the US; it's always an option. We haven't reached any decision, and we'll continue to analyze as we keep expanding our presence in the US, which remains and continues growing very, very strong. On the Capital Markets Day, we are planning to hold a Capital Markets Day on November the 12th this year, but we will confirm the day within the next days and we'll publish it, and everyone has the official date reserved.
Operator
operatorWe'll take the next question from José Manuel Arroyas at Grupo Santander. Go ahead, please.
José Arroyas
analystThanks for giving me the chance to speak. If I may, I have 2 questions. My first concerns the HOCHTIEF stake. Has ACS raised its holding since the start of the year, or is there a plan under consideration, or that might come under consideration, to add to that stake? My second question relates to net operating cash flow and growth. I'd like a clearer picture of whether the prepayments that Turner obtains on individual data center orders are larger or smaller than, say, the ones the E&C segment could be getting when it signs orders. Thank you.
Juan Santamaría Cases
executiveThanks, José Manuel. To begin with the HOCHTIEF stake, no further shares in HOCHTIEF have been bought by us — there's no news on that front. Are we hoping to buy? Like I've said before, we'll stay opportunistic: should the chance arise, we'll take it; if it doesn't, we'll think it over. Turning to net operating cash flow, Turner's prepayments aren't larger, and that comes down to how its contracts are structured. It's also fair to say that within construction, we've increasingly stepped back from EPCs and lump-sum projects, which usually carry very large advance payments — and at present we hold none of those. What we get instead is a far better risk profile on those projects. No — where Turner is concerned, I wouldn't claim there's any meaningful prepayment or advance payment tied to the projects.
Operator
operatorDario Maglione has another question for us, so please go ahead.
Dario Maglione
analystAppreciate you fitting in one more question. This one's really about the bigger picture. There are investors involved in AI and data centers who are specifically concerned about the bottlenecks involved in getting these data centers built. So what are you observing — perhaps focusing on the US, where you obviously have a substantial presence. What are you seeing? Where do the bottlenecks lie? And how worried are you about them? Thank you.
Juan Santamaría Cases
executiveDario, it's true that lead times for electrical equipment have gone up, particularly in '23 and '24, to the point where certain items were becoming a genuine bottleneck. Take high-voltage transformers — back then, I think we could expect 120 to 140 weeks to get those orders. With UPSs and battery systems, typically during '23 and '24, the wait could be between 35 to 45 weeks, and for switchgear, it was around 55 weeks, right? That was probably the worst period during '23, '24. Since then, the market in general has been improving, right? Now, one reason we always talk about the backlog we have, but then we mention the projects that we've been awarded, but they're not in the backlog, is because those projects — and the $15 billion data centers that we are talking to clients about right now, but are not in our backlog — that's precisely to make sure that we're going through all this planning phase on the design, on the ordering of all the electrical equipment, cooling systems, CPUs, GPUs, etc., etc., to make sure that by the time we start, everything goes very, very smooth, right?
Juan Santamaría Cases
executiveThat's why we do all of that design work and all of that upfront planning: labor, permitting, and every piece of equipment. I'd mention a couple of things. First, the market is getting better in that regard. Because of how we work with our clients, this is built into our process — we're evaluating many different data centers, and we emphasize planning ahead. Then, obviously, having Source Blue with us, which is becoming a huge force right now when it comes to handling logistics and warehousing critical elements and all of those mechanical components, right, to the point that we even stock with sufficient lead time, and we're handling all of it very, very well. The modularization we're beginning to do shortens schedules and reduces execution risk. We've significantly expanded our self-performance capabilities so we don't depend on particular items. Then, obviously, we have a massive local footprint, right? I think execution — not only the market, but the client relationships as I described — execution is a major differentiator, right? As these data centers increase in size and increase in complexity, it matters more that the company delivers.
Juan Santamaría Cases
executiveIt isn't solely a matter of overseeing the build itself. You also have to handle procurement, coordinate the MEP, make things modular, and bring industrial-style execution plus specialized manufacturing experience or a proven track record. Many different elements go into making these projects succeed, and that is exactly why I think Turner is doing so well compared with some of the newcomers, who don't have the scale needed to coordinate every supplier, correct, and to oversee how all those components get delivered, right? Volume matters enormously, extremely so, when you are running all of these supply chains across the globe. I believe that, yes, I believe that addresses the question.
Dario Maglione
analystAlright, thanks, Juan.
Juan Santamaría Cases
executiveThanks, Dario.
Operator
operatorOur following question is from Nicolas Mora at Morgan Stanley. Please proceed.
Nicolas Mora
analystTo revisit Turner, the revenue step-up you'd anticipate largely from advanced technology would have to come from data centers. That aspiration of $17 to $19 billion in revenue for 2026 rests entirely on data center orders already in hand, but past that point, what sort of visibility do you have—say, 12 months out or 18 months out? You often mention a degree of information asymmetry—what your clients are after, the conversations you hold. What do you have past '26, where the market, I think, is already pretty optimistic? How do you reassure people that growth won't stumble right into '27? My second question: you've mentioned all your efforts at industrializing the process. I just wanted to check in on what your scale delivers, particularly with Source Blue, on the logistics front, and especially modularization. We've watched some competitors—at least certain players in the supply chain and services—investing heavily and doing more and more. Do you intend to put substantially more investment, let's say, into warehouses, industrial warehouses, so you can handle a surge in capacity? One last point, perhaps on the semis opportunity.
Nicolas Mora
analystYou’ve been enthusiastic about this opportunity for some time. We aren’t observing a great deal of newness or substantial momentum. What lies ahead for you? Which opportunities do you see that could contribute, essentially, to data center, say, from '27 and '28 onward? Thank you.
Juan Santamaría Cases
executiveThank you, Nicolas. When it comes to Turner, we have—or at least we always believe we have—strong visibility into what lies ahead, since we're already working with our clients on data center plans stretching all the way to 2029, beginning with 2028 and 2029. The reason is that many of the components for these data centers must be ordered well ahead of time, particularly chips, GPUs, CPUs, and similar items. You have to make sure you get into the queue early enough. That's the source of our visibility. That's why back in November, when we stated we were at $10 billion in revenues and would grow to $25 billion in revenues, we had an extremely clear path. Essentially all of it was committed, correct? It wasn't built on any guess about what might materialize; it was already on our books, right? The issue is that growth is happening so fast that whatever estimate we produce always ends up too low. We assumed the move from 10 to 25 would unfold in a very linear fashion, and then suddenly, as we're about to close out this year, we find ourselves already at $17 to $19 billion in revenues, right?
Juan Santamaría Cases
executiveNo matter how much we try to forecast, the market essentially beats whatever estimates we make on the upside, correct? That's the difficulty—attempting to keep pace with this enormous data center expansion, and it's far beyond what any of us expected, even though we felt quite optimistic at the start. When it comes to industrializing the process, we've been putting money into modularization. The initial piece of what we've been doing is essentially leveraging our own—we have plenty of workshops worldwide where we used to produce prefab, lots of precast pieces like beams, girders, the ring segments for tunnels, every sort of precast component. We're converting some of them into data centers, some into nuclear, some into biopharma, and so on. We are investing, but clearly since we already have the workshop and it was up and running, the organic investment isn't all that large, right? So far it's largely covered within the CapEx. For instance, in the most recent data center project we completed, we built 3,500 modules, right? At present, we have a standard 50 MW modularized data center, and through that—through those modules—we're able to assemble 50 MW modules and build 1 GW or 2 GW data centers, and we're moving extremely, extremely quickly.
Juan Santamaría Cases
executiveThat's expanding a lot. Beyond that, we're considering possibly pursuing some M&A — extra bolt-on acquisitions, you know, not just the organic efforts I just referenced — and certain opportunities exist. Right now we're collaborating with two hyperscalers on two very large data centers that are 100% modularized, correct? That is expanding extremely rapidly. That is expanding extremely rapidly. In fact, we established XPL off-site last year, which is essentially a dedicated platform for prefab and modular delivery, correct? It's already demonstrating execution at a few data centers in the US. XPL sits within Turner, yet it drives and leads our worldwide operational and modular strategy, correct? There's a large group, a worldwide group, where we're essentially sharing processes, quality, shop drawings, everything related to this modularization so we can replicate globally, not only in the US. We're witnessing faster schedules. We're witnessing better productivities and quality. We lessen site congestion. We gain greater certainty regarding schedule and regarding cost. We boost production capacity. I believe that's a key differentiator for Turner.
Juan Santamaría Cases
executiveAnd then regarding semiconductors — on semiconductors, we're doing work on fabs in the States, correct? Let me step back. We've always — and this formed part of the Capital Markets Day, though it was underscored at our investor day in November — we aim to be involved in the whole AI chain, right? The single piece of the AI chain we won't join is the training of the languages, the models, all of that portion. Everything upstream of that, running from semiconductors and semiconductor fabs through data centers, fiber, and the energy for those data centers — we skip the language piece, or the training of the AI model itself, and then we carry on into applications, where we're working on a handful of applications, and then robotics, where we're very much already looking toward the future when it comes to robotics tied to infrastructure. We want a role in all of it, and that's where semiconductor fabs come in. We have experience in the US. We were recently awarded — and it's well, not yet in our backlog — a semiconductor fab in India. We're working on a couple of them in the US, and we believe fabs will keep being a business, and we're examining additional opportunities in that semiconductor fab space.
Nicolas Mora
analystLet me ask a couple of quick follow-ups, if I can. First, some investors have mentioned that you might be leaning too heavily on Meta—particularly during the first quarter, on that big Indiana project. Could you speak to that, and to how you view your client base in terms of diversification? The other question concerns inflation within the data center supply chain. How are you navigating it? What are you actually seeing on the ground? Are we talking 5%, 10%, 15%, 20% year-on-year inflation? I'm just trying to get a sense of, well, essentially, the lift that might also flow through to your revenues from that. Thank you.
Juan Santamaría Cases
executiveAll right. I think at this moment, if you look specifically at the US, this shifts things quite a bit, okay, because at times right now you get peaks with one hyperscaler versus another. I really do think that at this moment we have a peak with Meta, which accounts for 37% of our revenue breakdown in 2025, right? So 37% of our revenues in the US — just in the US — in 2025 came from Meta. Before that, Microsoft held the top spot, and we've had years when Google was on top, right? We have other hyperscalers. Last year, we had 20%, 15%, sorry, 15%, 4%, 10% coming from the other hyperscalers. That was specifically '25, and it shifts a lot, right? It shifts a lot. Then we do have roughly 23% from DC developers, platforms in general, and then about 9% from other colo enterprises, right — corporations, etc. — not a specific developer, not a specific hyperscaler. It's very much diversified, and it shifts a lot. Outside the US it's super diversified, right? When you look at all the data centers across Asia, that's hyperscalers, developers, and and and there's a mix, and in Europe we're seeing a mix as well.
Juan Santamaría Cases
executiveI — I wouldn’t assume that. Yes, last year a substantial amount of work came to us from Meta, and they’re an enormous and excellent client for us, but that shifts constantly.
Operator
operatorThat brings us to the end of the question-and-answer session. With that, I'll turn things over to the ACS management team. Please proceed.
Juan Santamaría Cases
executiveI appreciate all of you taking the time to join us today. Should you have any additional questions, as always, don't hesitate to reach out directly. Thanks very much.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete ACS, Actividades de Construcción y Servicios, S.A. transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →This call discussed
For developers and AI pipelines
Programmatic access to ACS, Actividades de Construcción y Servicios, S.A. earnings transcripts and 132,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in ACS, Actividades de Construcción y Servicios, S.A. or any ticker on your watchlist.
StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.