Thanks, operator, and good morning to all of you. It's a pleasure to welcome you to the Bitdeer second quarter 2025 earnings conference call. With me today are Jihan Wu, our Chairman and CEO, Matt Kong, Chief Business Officer, Haris Basit, Chief Strategy Officer, and Jeff LaBerge, VP of Capital Markets and Strategy. Haris is going to kick things off by giving a high-level overview of Bitdeer's second quarter 2025 results, and after that he'll walk through the company's strategy along with a detailed business update. Following him, Jeff will go through Bitdeer's second quarter financial results in more depth, and then we'll open up the call for questions. Alongside today's earnings call, we've made a supplemental investor presentation available. You can find this presentation on the Bitdeer investor relations website under "Webcasts and Presentations." Before management delivers their formal remarks, we want to remind everyone that during today's call, we may make certain forward-looking statements. Such statements rest on management's current expectations and are subject to risks and uncertainties, which could cause actual results to differ materially. For a complete discussion on forward-looking statements and the risks and uncertainties related to Bitdeer's business, please refer to its filings with the SEC. Additionally, beyond discussing results calculated in accordance with International Financial Reporting Standards, or IFRS, we will also reference certain non-IFRS financial measures, such as adjusted EBITDA and adjusted profit or loss; for more detailed information on our non-IFRS financial measures, please refer to our earnings release that was published earlier today, which can be found on Bitdeer's Investor Relations website. Thank you. I'll now hand the call over to Haris. Haris?

Haris Basit

executive
#2

Thank you, Yujia, and hello, everyone. I appreciate you being here for our earnings call covering the second quarter of 2025. We have achieved considerable advancement on every one of our strategic priorities since the previous call, and I'm glad to share those developments with you today. First, I'll give a quick summary of how we performed financially in Q2, after which I'll point out what we're concentrating on for the rest of the year and offer some insight into what lies ahead past 2025. Beginning on slide three, total revenue for Q2 came in at $155.6 million, which represents a 122% rise from Q1 on a sequential basis and a 57% gain compared with the same period a year earlier. Gross profit reached $12.8 million, while adjusted EBITDA stood at $17.3 million, a substantial increase over Q1. This notable enhancement in our results stems from robust execution within our self-mining operations and commercial sales of our SEALMINER ASICs. Once mass production of our SEALMINER ASICs got underway, we were able to raise our average operating hash rate by 46%, reaching 14.2 exahash for the quarter, compared with 9.7 exahash in Q1. Beyond that, we sold and shipped 5.3 exahash of our SEALMINER A2 mining rig to outside customers, which let us recognize $69.5 million in revenue during Q2. By the close of July, we had further expanded our self-mining hash rate to 22.3 exahash, a 162% jump relative to the start of the year; we also sold and recognized revenue on another 0.6 exahash of SEALMINER A2s in July. Reflecting on the first half of the year, we see Q1 as having been both the bottom and a crucial inflection point. Strong momentum now has us turning the corner, driven by our vertically integrated, technology-focused growth strategy. Our choice to invest heavily in chip design, supply chain, and manufacturing established a solid base that is now letting us quickly scale our own self-mining operations while putting us in position to claim a meaningful portion of the Bitcoin mining ASIC market. Through combining our proprietary technology, in-house hardware manufacturing, and extensive global power portfolio, we have built a highly advantaged and defensible platform for long-term growth. Going forward, our SEALMINER ASICs keep coming off the production line, and we expect our self-mining hash rate to continue growing rapidly for the rest of the year; we remain on track to hit our earlier goal of 40 exahash of self-mining hash rate by the end of October. On top of that, wafer supply allocation at our foundry has gotten better, and we anticipate surpassing this target by year-end. That will place us alongside the largest publicly traded Bitcoin miners globally. As we keep scaling, energy efficiency across our fleet will improve as well, producing better mining margins and operating leverage. As we exit this year, we expect record results on a run-rate basis, which sets a strong foundation for 2026 and beyond. When we set out on our aggressive ASICs roadmap last year, we recognized that developing chips by itself would not be enough. To succeed in this market, we must attain industry leadership in both performance and energy efficiency. At this point, we're quite proud that the committed R&D group has carried out this strategy with accuracy, bringing in three of the four chips as planned and to specification. Thanks to our newest SEALMINER A3, we currently hold one of the strongest mining machines available on the market, and it's constructed on top-tier process nodes while being tuned for highly efficient large-scale deployment. Every validation metric at the machine level has either reached or surpassed the internal targets we set, and we're getting ready to begin mass production. We anticipate the initial shipment of SEALMINER A3 units to become available in October; through 2026, we look for SEALMINER A3 to add to our revenue via self-mining as well as sales to outside parties. Turning forward, our R&D work has shifted focus to the SEAL04 chip. For SEAL04, we're pursuing a two-pronged strategy involving two entirely separate designs to help guarantee success. The initial SEAL04 chip, which relies on a more conventional circuit design, has already completed tape-out, and we anticipate the first sample wafers returning during Q3 2025. A second SEAL-04 chip of ours will employ an entirely novel, next-gen architecture aimed at a breakthrough in efficiency of roughly 5 joules per terahash at the chip level. This chip represents a total redesign that leverages fresh digital circuit architectures allowing dramatic gains in energy efficiency. We think the digital chip architecture our SEAL04 chip employs will establish a new benchmark for Bitcoin mining and additionally apply to a wider set of high-performance, energy-heavy compute use cases. We've started the patent filing process for our technology. In addition, during July, we achieved significant headway by successfully creating custom silicon design software that's required to completely leverage this new architecture; we've likewise grown our senior engineering and software team within the U.S. to aid SEAL04 chip development, and brought in senior positions for legal and IP licensing; we couldn't be more thrilled about SEAL04. Alongside our SEALMINER A3 mining rig, we're confident these two chips will solidify Bitdeer's standing as a top supplier offering the industry's most energy-efficient mining rigs, greatly strengthening our competitive edge and unlocking considerable worth for our customers and shareholders alike. Now, I'd like to give a brief update regarding our energy infrastructure, which is featured on slides eight and nine in our supplemental investor presentation. During Q2, we kept up our swift expansion of power and data center infrastructure worldwide. By July 2025, we had energized 361 MW of data center capacity for self-mining, with 126 MW located at our site in Tydal, Norway, plus 235 MW at Jigmeling, Bhutan, pushing our total available electrical capacity to about 1.3 GW; we anticipate the remaining 49 MW at Tydal and 265 MW at Jigmeling will be energized during Q3, lifting our total available power capacity to close to 1.6 GW. In May, we hit a crucial milestone by signing the letter of agreement with AEP Ohio covering the second phase of power at the Clarington site. This LOA moves the contracting process into its final phases for the entire 570 MW of capacity. Importantly, we signed this document prior to a ruling from the Public Utilities Commission of Ohio that placed data centers into an industry-specific billing category. Under that new category, collateral requirements and minimum demand charges would have been considerably greater. By securing our position before this enormous regulatory change, we can move forward with plans to fully build out this strategic data center at a meaningfully lower cost structure. Turning to our HPC AI initiative in Clarington, Ohio, we are now in advanced negotiations with a development partner possessing deep expertise and strong customer relationships. We feel optimistic about sharing additional details next quarter. Finally, please turn to slide 10 in our supplemental investor presentation, where we want to restate our guidance concerning our self-mining hash rate. Thanks to the steady rollout of our SEALMINER A2 mining rig, we continue to expect reaching 40 exahash by October. In addition, as I noted earlier, wafer supply has gotten better for our SEAL02 and SEAL03 chips, which leads us to believe we will exceed that target by year-end. Because we have such a large amount of power capacity coming online, our near-term approach is to direct our current ASIC production first toward self-mining; in short, we are happy with how our team has executed across every strategic priority. We have hit our initial targets for our aggressive ASIC roadmap, for our self-mining infrastructure and deployment plan, and for our entry into the enormous ASIC market opportunity. We have likewise achieved major progress in our HPC AI strategy. As we enter the second half of 2025, we anticipate these efforts will show up in our financial results, and we are eager to provide updates on our progress. I will now hand things over to Jeff LaBerge, our Vice President of Capital Markets and Strategy, who will walk through our detailed financial results for the quarter.

Jeff La Berge

executive
#3

Thanks, Haris. Before I walk through Bitdeer's second quarter financial results, I want to remind everybody that every figure I mention today is denominated in U.S. dollars. Consolidated revenue for Q2 came in at $155.6 million, which is up from $99.2 million in Q2 2024 and $70.1 million in Q1 2025 — that works out to a 56.8% increase year-over-year and 121.9% sequentially. Self-mining revenue reached $59.3 million, compared with $41.6 million in Q2 2024 and $37.2 million in Q1 2025, representing growth of 42.5% year-over-year and 59.4% sequentially; these results were mainly attributable to a 103.3% year-over-year and 45.5% sequential rise in self-mining hash rate, along with higher Bitcoin prices. Those gains were partly offset by the April 2024 halving event and increased mining difficulty. SEALMINER sales revenue totaled $69.5 million, against $0 in Q2 2024 and $4.1 million in Q1 2025. Cloud hash rate revenue was $0, versus $12.2 million in Q2 2024 and $0.1 million in Q1 2025; that decrease stemmed from long-term cloud hash rate contracts expiring and the resulting reallocation of that hash rate into our self-mining operations. General hosting came to $9.3 million, versus $20.6 million in Q2 2024 and $9.6 million in Q1 2025. Membership hosting revenue was $14.6 million, versus $22.1 million in Q2 2024 and $16.3 million in Q1 2025. Two factors were chiefly responsible for this year-over-year drop in hosting revenue. First, we shifted 100 MW of hosting capacity at our Texas facility over to self-mining, which has been fitted with SEALMINER hydro-cooled mining rigs. Second, following the April 2024 halving event, some hosting customers pulled out less efficient mining rigs. New hosted mining rigs are currently replenishing a portion of that extra capacity. Total gross profit for the quarter was positive $12.8 million, versus $24.4 million in Q2 2024 and — $3.2 million in Q1 2025. Gross margin came in at 8.2%, versus 24.6% in Q2 2024 and — 4.6% in Q1 2025. The year-over-year decline in our gross margin was mainly driven by the April 2024 halving event's effect on self-mining, greater mining difficulty, and reduced hosting and cloud hash rate revenues. On a sequential basis, our gross margin improved thanks to the rise in our self-mining hash rate, gains in our fleet efficiency, and commercialization of our SEALMINER ASICs. Looking ahead, we anticipate gross margin will improve across the coming quarters as our hash rate ramps up and our overall fleet efficiency gets better. Total operating expenses for the quarter were $42.3 million, versus $26.1 million in Q2 2024 and $75.8 million in Q1 2025. The year-over-year rise was mainly driven by R&D costs tied to our SEALMINER roadmap and higher G&A. The sequential decline was mainly driven by our R&D costs, owing to the absence of the tape-out costs for SEAL03 that were incurred in Q1 2025. Other operating income was $3.7 million, primarily due to the reversal of non-cash impairments of Bitcoin. Just to recap, according to IFRS, Bitcoin falls under the category of an intangible asset, carried at cost minus any cumulative impairment charges, and you're not allowed to write it up afterward. Other net gain for this quarter came in at negative $108.5 million, compared with — $15.5 million in Q2 2024 and positive $503.1 million in Q1 2025. That net loss stemmed from the non-cash derivative loss tied to the convertible senior notes we issued in August 2024, November 2024, and June 2025, and I'll get into that more when we reach the liability section. IFRS net income landed at — $147.5 million, against — $17.7 million in Q2 2024 and — $409.5 million in Q1 2025. Adjusted profit came to — $24.4 million, versus +$3.2 million in Q2 2024 and -$89.8 million in Q1 2025. Adjusted EBITDA reached + $17.3 million, compared with + $23.5 million in Q2 2024 and -$56.1 million in Q1 2025. The improvement this quarter, both year over year and sequentially, in top-line and non-GAAP bottom-line results, was largely attributable to a higher self-mining hash rate, SEALMINER sales, and stronger Bitcoin prices; those gains were mostly counterbalanced by a higher global network hash rate, reduced hosting and cloud mining revenue, and increased R&D costs plus G&A expenses, as covered earlier. Net cash consumed by operating activities totaled $334.9 million, chiefly from $230 million in payments for SEALMINER wafers and associated production costs, along with $27 million for the initial tape-out of SEAL04. The rest came from electricity costs in the mining business and general corporate overhead. Keep in mind that a substantial share of that $27 million SEAL04 tape-out expense is anticipated to hit Q3. Net cash consumed by investing activities was $12.6 million, stemming from $106.5 million in capital expenditure, $76 million of which went toward data center infrastructure and related construction. Proceeds from disposable cryptocurrency tied to our primary business amounted to $100.1 million. Net cash produced by financing activities during the quarter reached $431.5 million, mainly from $364.3 million in net proceeds on the convertible senior notes issued in June 2025, $180 million borrowed from a related party, and $50 million in proceeds from share issuance connected to the tether warrants exercise. Partially offsetting that were $129.6 million spent on a zero-strike call option tied to the convertible senior notes issued in June 2025, plus a $33.8 million payment related to extinguishing part of the convertible senior notes issued in August 2024. No shares were issued through our ATM this quarter. Turning to our 2025 Bitcoin mining infrastructure spend, we still anticipate CapEx for continuing to build out our global power and data center infrastructure will fall in the range of $260 million- $290 million for calendar year 2025. That range factors in reported infrastructure CapEx of approximately $118 million across Q1 and Q2. Looking ahead, the rest of our planned capital expenditures should cover getting our data centers in Tydal Norway, Jigmeling Bhutan, Massillon, Ohio, and Ethiopia finished or almost finished, plus partially finishing the 101 MW gas-fired power plant in Alberta, Canada. Just keep in mind this guidance accounts only for power and data center spending tied to Bitcoin mining, and it leaves out any CapEx for SEALMINERs. Turning to the balance sheet, we closed out the quarter financially strong, holding $299.8 million in cash and cash equivalents, $169.3 million in cryptocurrencies, and $533.1 million in borrowings, not counting derivative liabilities. Keep in mind that the $169.3 million in cryptocurrencies gets accounted for under IFRS rules and right now sits beneath its market value. Derivative liabilities came to $438 million, tied to the August 2024, November 2024, and June 2025 convertible notes, which marks a $181.2 million rise from the prior quarter. That's a non-cash fair value adjustment pushed up by our climbing stock price, and it has no effect on our liquidity or operations. IFRS requires certain derivative instruments, like warrants and convertible debt, to be revalued at fair market value every reporting period. When our stock price climbs, the fair value of those instruments goes up too, which produces a larger reported liability, and the reverse holds as well. Eventually that recorded liability gets netted out at settlement, whether through conversion to equity or expiration, so it isn't an actual cash outflow. Back in June, we wrapped up a $375 million convertible senior note via an oversubscribed private placement offering. That note carries a 4.875% interest rate and matures in 2031. Last, on our outstanding ATM facility, no additional shares were sold by us in Q2 2025. Thanks, everyone. That wraps up the prepared remarks portion of our earnings call. Operator, please open the call for questions.

Greg Lewis

analyst
#4

Yeah, hi. Thanks. Morning, afternoon, evening to you all, and I appreciate you fielding my questions. I wanted to ask about the prepared remarks concerning the data center opportunity. I get that it sounds like active negotiations are underway there, so I understand there are limits on what you can share. Just curious — as we look at this, one thing the market seems to be trying to grasp, as you go after this with a partner, is how Bitdeer views the construction risk. In the past, it sounds like we discussed financing being handled with a partner when it comes to bringing in general contractors for the work. Can you give any color on that? Since this is the Clarington site, are we doing something similar at — I know previously we talked about possibly Rockdale and even Norway. With this partner, do we think it could involve multiple partners across multiple sites, or could this be a one-off?

Haris Basit

executive
#5

Hey, thanks, Greg, for the question. Right now the focus is the Clarington site. That said, as we've reported previously, we've received inbound requests regarding both the Norway and Rockdale sites, and discussions are happening there, though they're far less advanced than what's going on with Clarington. Our present thinking regarding the Clarington site is that our capital needs would be quite minimal, that the partner would supply it, and then naturally construction loans would sit on top of that. Does that answer your question?

Greg Lewis

analyst
#6

Yeah, that's really useful. My next thing was, when we consider Bitcoin ASIC manufacturing growing in significance for the business, it seemed like perhaps your sales pricing got somewhat better. Does that suggest some market momentum, or is it more about you moving more efficient machines? Could be a mix of both.

Jeff La Berge

executive
#7

My sense is pricing held pretty steady versus the prior quarter. We're witnessing stronger demand, clearly gaining momentum from a hash price that's climbing. The Bitcoin price has clearly contributed to that too. Demand has certainly risen, and we believe appetite for SEALMINER A3 will clearly be far greater as well.

Greg Lewis

analyst
#8

Okay, thank you.

Haris Basit

executive
#9

Thanks, Greg.

Dylan Heslin

analyst
#10

Hi there, good morning, and thank you for letting me ask. Following up on a few of the HPC remarks regarding Clarington, have you and your partner settled on the strategy you'll pursue in terms of how that might shape up? Would it end up being a colocation arrangement, the way many peers have structured theirs? Might you aim for a powered shell, or, since you have experience operating GPU clusters, might you lean toward something closer to a full stack? How exactly are you viewing that opportunity?

Haris Basit

executive
#11

The Clarington property is really big — 570 MW of gross power, as you know. At this point a full stack isn't something we're considering. What we're actually trying to do is concentrate on build-to-suit. That said, the key point to keep in mind is our flexibility, and going forward, a great deal will hinge on which tenant we ultimately sign, who turns out to be the site's final customer; answering those questions with certainty is difficult, except that our aim is build-to-suit.

Dylan Heslin

analyst
#12

Understood. Thanks. To build on the wafer availability question, when do you expect to gain more certainty about the chips or wafers you'll be allotted?

Haris Basit

executive
#13

We're basically talking with TSMC all the time, and pinpointing precisely when we'll receive allocations of additional wafers is tough, plus we don't actually announce our wafer allocations beforehand. Once a quarter or month wraps up, we disclose how many machines we've built and consumed in-house or sold, but we never do so early.

Dylan Heslin

analyst
#14

Thanks a lot.

Mike Colonnese

analyst
#15

Hello, and good morning, everyone. I appreciate you fielding my questions today. To start things off — Jeff, you touched on part of this regarding demand — could you share additional detail about the initial interest you're observing for the SEALMINER A3, and how that lines up with the manufacturing capacity you expect to have? Haris, I believe you said the initial batch would be set to ship at some point in October.

Jeff La Berge

executive
#16

Yes, that's right. Our plan is to make the first batch ready during this year. Once more, we haven't provided any forecast regarding the overall hash rate that will be on hand; what we can share is that a substantial share of it will probably be consumed by us in-house, though we also intend to offer a portion for sale.

Haris Basit

executive
#17

Right now, we aren't really promoting the SEALMINER A3, or at least we're not doing so on a large scale for outside purposes.

Mike Colonnese

analyst
#18

Understood. I appreciate the clarification, everyone. For my follow-ups, I'd simply like to hear your overall view on ASIC pricing, given where the Bitcoin market stands today and the competitive picture more broadly at this moment. Specifically, how will that SEALMINER A3 chip, or ASIC, compare on price against what certain competitors of yours charge for the most efficient ASICs they currently offer in the marketplace.

Haris Basit

executive
#19

Well, as you know, we must always stay competitive when it comes to price. The A3, you know, is an excellent product. It brings meaningful efficiency gains. Pricing hasn't been decided by us. Like I mentioned, we aren't really going out there promoting it for external sales at this point. The majority of the first batches are intended by us for internal consumption. Honestly, I'm unable to state what our price for external customers would be. It's going to beat the A2. Naturally, it will exceed the A2 in price, since it's a far more efficient unit. That figure hasn't been finalized by us, and it's likely too early.

Mike Colonnese

analyst
#20

That's all for me. Thanks.

Haris Basit

executive
#21

Thanks, Mike.

Mark Palmer

analyst
#22

Good morning, and thanks for taking my questions. Looking ahead at how the various SEALMINER units get produced, how do you weigh using them for self-mining against selling them externally? What factors come into play there—clearly the Bitcoin price is one, but also the demand for those units is another?

Haris Basit

executive
#23

Like we've told you, internal use comes first for us. The reason is we don't want capacity sitting idle, self-mining margins are actually pretty strong, and we believe this Bitcoin boom cycle is still in its early days. That's definitely something we're putting at the top of our list. As our own available capacity gets used up over the next several months and quarters, you'll see a shift happen on its own — we'll move from running these mining rigs ourselves toward increasingly selling them to outside buyers. Down the road, naturally, the aim is for us to become a significant supplier of these to the broader market, rather than keeping them solely for our own operations.

Jeff La Berge

executive
#24

Yes, Mark, I'd simply like to build on that point — you know, our goal is to remain in a position where our strategy can always be highly market-driven, so that each and every ASIC we produce will have a place to go, and we can determine its true highest and best use, whether that means consuming it internally or offering it to third parties. At this moment, given that a substantial amount of capacity is being brought online, we clearly don't want it to sit unused. That's what we're putting first. Going forward, we'll have the ability to take that far more market-driven approach.

Mark Palmer

analyst
#25

In a similar vein, regarding the choices available to us, what are your present thoughts on whether or not to utilize the Bitcoin held on the company's balance sheet — specifically, accumulating it versus liquidating it and directing those proceeds toward building out the company's platform? Thank you.

Jeff La Berge

executive
#26

Yeah, I believe we began — our approach had been to sell the majority or all of the Bitcoin we mine until, I'd say, close to the end of last year, when we did begin holding. Clearly, we do perceive there's value in keeping Bitcoin on the balance sheet; we hold a very bullish view on it over the long term. I don't think this is something we're necessarily idealistic about. Jihan, any further thoughts on that?

Jihan Wu

executive
#27

So, really, we're following a fairly balanced strategy. A portion gets sold, and a portion stays with us. Some Bitcoin has to be sold so that, from an accounting standpoint, our balance sheet in U.S. dollars can stay balanced over the long term, correct? The reason is that we take on debt — we'll borrow in U.S. dollars — and then we bring in U.S. dollars by issuing equity. Either way, at some point the capital has to go back to our investors, whether through equity or through our debt. Selling a bit of the Bitcoin is, in my view, necessary, while also keeping Bitcoin for the long term. I think that's a solid move, a solid use of capital, since I'm confident that within 80 years, Bitcoin could climb to roughly $1 million. That works out to about 10x from where we are now. It's an investment with an IRR of nearly 30%. I'd say that's also something beneficial for investors. With the market going through this type of turbulence, we have to stick with a fairly balanced strategy. That's the philosophy we follow here.

Mark Palmer

analyst
#28

Appreciate it.

Kevin Cassidy

analyst
#29

I'm grateful for the chance to ask something. I have to admit, the volume of SEALMINERs you moved to outside customers caught me off guard. Is there any detail you can give on the regions those went to? Did tariffs play any part at all?

Jeff La Berge

executive
#30

Regarding geography, we haven't shared that level of detail about where those units went; what I can tell you is that sales spanned the globe, with a portion in the U.S. and a portion clearly outside the U.S. Neither the identities of the purchasers nor the specific locations have been made public.

Haris Basit

executive
#31

What was the last part of your question, Kevin? Was what involved?

Kevin Cassidy

analyst
#32

Yeah, regarding U.S. tariffs, what if steep duties were placed on equipment sold into the United States?

Jeff La Berge

executive
#33

Throughout the past 90 days, those tariffs have remained paused. In any case, we would not anticipate meaningful tariff exposure, certainly not during the most recent quarter.

Kevin Cassidy

analyst
#34

Alright, that's helpful. My understanding is that the plan involves directing more of the equipment toward internal purposes. Should we be treating that as a steady quarterly pace for equipment sales?

Jeff La Berge

executive
#35

That's not necessarily the case. What it ultimately depends on is the allocation we receive from TSMC, plus simply how quickly our power gets brought online. We anticipate a substantial amount of power becoming available during this quarter, and we're looking to scale up to the 40 exahash goal we've established, and potentially past it, by the time the year ends. As we move into the first half of 2026, we anticipate bringing on the site in Massillon, Ohio; that adds another 221 MW. We'll have a meaningful amount of fresh capacity that we'll be looking to fill using SEALMINERs, and again, allocation will be the deciding factor. My sense is we'll always aim to maintain some degree of balance between using units ourselves and selling them. Over this near-term window covering, say, two to four quarters, or two to three quarters, the balance will probably tilt toward a larger share, or greater allocation, going to self-mining.

Haris Basit

executive
#36

Even though those figures remain fairly modest at this point, the amount sold to outside parties is going to swing around more. Once you look beyond 3 or 4 quarters out, though, you'll find it settles into something steadier and easier to forecast.

Kevin Cassidy

analyst
#37

Okay, thanks for that clarification.

Haris Basit

executive
#38

Thank you.

Mike Grondahl

analyst
#39

Hi, everyone. When it comes to Clarington, how would you characterize demand conditions and pricing, based on what you heard through the summer? Did things accelerate? Did they cool off? I'm just a bit curious about the pace.

Haris Basit

executive
#40

We've observed no drop whatsoever. It's difficult to gauge, you know, the extent to which it has accelerated. The entire period has been strong, in my view. That's a reasonable way to put it.

Jeff La Berge

executive
#41

Yeah, I believe we've observed quite a few people coming back into the market across these past several months — at minimum, the previous 2 months. From a demand perspective, the market has certainly strengthened. On the whole, yes, we haven't experienced any kind of slowdown whatsoever.

Mike Grondahl

analyst
#42

Rockdale and Norway came up. When you look at those two, is there one you'd put ahead of the other for development next?

Jeff La Berge

executive
#43

I wouldn't say that. What we'll do is watch how the market develops. Norway strikes us as a really compelling opportunity, since from an adoption perspective the EU lags quite far behind where the U.S. stands. That opportunity, in our view, could stretch out over a longer tail. We see it simply as something in our favor. The more price discovery that occurs, the better. Given that it runs on 100% hydropower, we do believe this will be a really interesting asset. From a latency standpoint, Norway has excellent interconnection, with good fiber running directly next to our property, and clearly the climate there suits cooling well. That opportunity has us very bullish.

Mike Grondahl

analyst
#44

Alright, I appreciate it.

Brett Noblock

analyst
#45

Hey everyone, I appreciate you letting me ask something. Regarding how the SEALMINER A2 has performed — both the units you've already sold and the ones you're using yourselves — how is it measuring up against what you were hoping for when it comes to uptime and general availability?

Haris Basit

executive
#46

I'd say uptime and reliability look pretty solid, and it lines up with what we anticipated given those initial results. Perhaps I should turn it over to Jihan — he deals with the customers more directly, so he may want to chime in.

Jihan Wu

executive
#47

I'd call it really good, honestly.

Brett Noblock

analyst
#48

Okay, nicely put. Perhaps regarding that development partner in fairly advanced talks — what comes next in that sequence, I suppose? Would it be putting an agreement in place with them? Or possibly seeking a JV partner following that? For Clarington, what pace ought we to expect?

Haris Basit

executive
#49

Do you mean the site in Clarington, Ohio?

Brett Noblock

analyst
#50

Yes.

Haris Basit

executive
#51

Yeah, getting that agreement with the development partner set down formally is what comes next.

Brett Noblock

analyst
#52

And what comes after that?

Haris Basit

executive
#53

Our very next move is to find a tenant and get a lease signed with them. Some work will happen during that period, but this would rank as our top priority. At the same time, we might also see horizontal construction taking place on the property.

Brett Noblock

analyst
#54

Great. Thanks, everyone.

John Todaro

analyst
#55

Hi, everyone, thanks for fielding my question. I’m not certain whether I overlooked this. Regarding SEALMINER sales, can you give us the number of units? Is the pricing unchanged from what we were previously guided toward? Did anything shift in that regard? I have a follow-up concerning the HPC portion of the business.

Jeff La Berge

executive
#56

Yeah, no, pricing is still fairly steady compared with last quarter. I believe from the—you know, clearly sales went up. The hash rate volume we sold was significantly greater, but pricing stayed quite steady.

John Todaro

analyst
#57

Understood. Appreciate that, Jeff. Regarding the HPC side of things, the contract with the development partner still has to be completed. As for that development partner, I wouldn't take it for granted that they're providing financing too. You secure the tenant, you secure some debt financing, yet you also bring in a JV partner for an equity component. Should we expect that some equity gets given up during this process?

Jeff La Berge

executive
#58

With the development partner we're aiming to collaborate with, we wanted a partner who would in fact contribute the project equity as well. Our aim is to fund all or most of the project at the project level, covering project equity, clearly, plus project financed debt.

John Todaro

analyst
#59

All right, that makes sense. Thanks for explaining. I appreciate it.

Jeff La Berge

executive
#60

Sure, and we appreciate you asking.

Brian Kinstlinger

analyst
#61

Thanks, that helps. I want to ask a bit more about Clarington. Once we've got an agreement signed with a development partner, are there other steps that have to be finished before a tenant can begin negotiating on its own?

Haris Basit

executive
#62

Completed or not, additional steps are going to happen on our end. Some engineering work gets done, and we'll place orders for items with long lead times. There's also what people call horizontal work, that kind of thing. Much of that is independent of which end tenant comes in and doesn't cost much, so chances are we'll kick it off right away, at the same time as we search for and secure the tenant. Pinpointing and securing a prospective renter isn't a lengthy process, though getting that renter to sign on the dotted line often drags on, simply because these agreements are usually pretty intricate.

Jeff La Berge

executive
#63

Sure, if everything lined up perfectly, we'd wrap up a deal, kick off the site work going sideways across the land, and then, once a tenant was locked in, we'd be set to build upward.

Brian Kinstlinger

analyst
#64

Thanks. Haris, one thing you said was that things would improve quarter over quarter. Did you mean that about all revenue plus EBITDA, or only about self-mining, since it sounds like external sales won't be as big in Q3?

Haris Basit

executive
#65

Broadly put, clearly we're now expecting a far larger run rate of 40 exahash as we enter Q4, compared with the nine we had at the start of this year. On the self-mining side, I believe that run rate has established a fresh benchmark. Like Haris mentioned before, the sales side could be somewhat more uneven, simply because how much goes to self-mining instead of external sales will shift somewhat more across the coming two to four quarters. Beyond that, as we've said, we'd anticipate it leaning more heavily, possibly, toward sales afterward.

Brian Kinstlinger

analyst
#66

Okay, thank you.

Haris Basit

executive
#67

Absolutely.

Fedor Shabalin

analyst
#68

Thanks a lot, operator, and good morning to all of you. Fedar Shabalin here with Nick Giles. My initial question concerns Clarington. You brought it up — could you give us additional detail about what being at an advanced stage of negotiation actually involves, and when might we hear an incremental update regarding the purchase? Thank you.

Haris Basit

executive
#69

Being at advanced stages refers to, you know, the last legal paperwork and the last due diligence, that sort of thing. Our hope is that during this quarter, Q3, we'll have something to share.

Fedor Shabalin

analyst
#70

I appreciate that. One more thing on the SEAL-04 chip: how probable is it that this design gets picked up for uses outside of Bitcoin mining? And if that kind of pickup is possible, which particular applications or use cases would fit best? Thanks.

Haris Basit

executive
#71

Today the A4 has been divided into a pair of A4s. If the one you mean is the version built on the new technology, a great deal more validation work remains for us, though what we're seeing so far suggests it ought to perform really well across plenty of digital applications involving very heavy energy consumption. Chips with a great deal of compute relative to others stand to gain. When a chip leans heavily toward I/O intensity and the bulk of its power runs through I/O, the benefit shrinks. Where compute intensity is high, that's precisely where this technology delivers the greatest advantage. This is, in a sense, a longer-horizon matter. To bring this technology to other chips that aren't Bitcoin-related, you're looking at no less than a couple of years before other applications take it up. I simply want to be certain that timeline is clear to you.

Fedor Shabalin

analyst
#72

Thanks a lot, Haris. Jeff and the crew, keep wishing you the best of success.

Haris Basit

executive
#73

Appreciate it.

Bill Papanastasiou

analyst
#74

Morning, and thanks for fielding my questions. Congratulations on those impressive equipment sales figures for the quarter. Could you perhaps discuss who your buyers are as you move the various SEALMINER series? Are many of them coming back to buy again, picking up some of the newer series, or does that business spread out among fresh purchasers? I'd love to hear how things are going and what you anticipate. Thanks.

Jeff La Berge

executive
#75

Hi, Bill. Appreciate you asking. We haven't actually shared the precise makeup or any customer identities. That said, what I can tell you is the split has been healthy, spanning public and private miners alike, big and small alike. Getting the SEALMINER A2 into as many end users' hands as possible was really our aim, so we could gather more market feedback. Some of the bigger PUBCOs, in our view, will probably lean toward the SEALMINER A3, yet we've managed to place a number of the A2s for testing too.

Bill Papanastasiou

analyst
#76

Excellent. That added context is much appreciated. Anything else I had was covered already. Thank you.

Jeff La Berge

executive
#77

Thank you, Bill.

Operator

operator
#78

We appreciate everyone joining us. That wraps up the question-and-answer portion. You're free to end the call now. Wishing all of you a pleasant day.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete Bitdeer Technologies Group transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

This call discussed

For developers and AI pipelines

Programmatic access to Bitdeer Technologies Group earnings transcripts and 132,000+ others is available through the EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research

OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Bitdeer Technologies Group or any ticker on your watchlist.

StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.