JSW Energy Limited (533148) Earnings Call Transcript & Summary

July 14, 2023

BSE Limited IN Utilities Independent Power and Renewable Electricity Producers earnings 49 min

Earnings Call Speaker Segments

Operator

operator
#1

Good day, everyone, and welcome to the Q1 FY ’24 Earnings Conference Call for JSW Energy, hosted by JM Financial. Just a reminder that every participant line is in listen-only mode, and once the presentation wraps up, you’ll have a chance to ask questions. <<operator_script>> Kindly be aware that this conference is being recorded. At this point, I’ll pass the conference to Mr. Sudhanshu Bansal of JM Financial. Thank you, and the floor is yours.

Sudhanshu Bansal

analyst
#2

Thank you, Yashashri <<inaudible>>. Good evening, everyone. Speaking for JM Financial, I'm glad to welcome all of you to JSW Energy Limited's conference call, where we'll be discussing the 1Q FY’24 results. Joining us is the leadership team from JSW Energy: Mr. Prashant Jain, Joint Managing Director and CEO; Mr. Pritesh Vinay, Director Finance and CFO; and Mr. Bikash Chowdhury, Head, Investor Relations and Treasury. Many thanks, sirs, for being here and for letting JM Financial host this call. That said, I'll now turn things over to Mr. Prashant Jain for his opening remarks and to carry the call forward. Over to you, sir.

Prashant Jain

executive
#3

Thank you. Good evening, ladies and gentlemen. In the quarter that just passed, power demand was quite subdued at 1%, mainly because during April and May we had unseasonal rains. And demand was roughly flat or negative. But demand picked up in June, reaching 4.5%. And in July it is still going strong at 5.5%. Total installed capacity in this sector now stands at 422 gigawatt. In the quarter, capacity addition totaled 5.8 gigawatts, of which 4.5 gigawatts was renewable capacity, including 1.1 gigawatt of wind and 3.3 gigawatt of solar. In the quarter that just ended, total energy generation for the company rose 14%. After that, 911 million units came from the Mytrah portfolio, another 106 million units from Group Captive and SECI X portfolio. And an additional 421 million units came from Ratnagiri. However, there was no fresh water at any of our hydro power plants across the country, where there has been an issue, and we saw a drop of 428 million units from our hydro business, and at the Barmer plant there was scheduled maintenance, because of which 136 million units were down.

Prashant Jain

executive
#4

So, overall, the company generated 6.7 billion units during the quarter. On EBITDA, which rose 18%, an additional INR370 crores came from the Mytrah portfolio. The pro rata pro forma EBITDA for Mytrah this quarter was actually INR370 crores, but two of our SPVs were consolidated later in April, so INR30 crores isn't showing up here. Also, as I said, we had lower generation because of Barmer and hydro, though both of those assets sit under long-term PPAs. There's an INR80 crore EBITDA — lower EBITDA versus the prior year — but that entire INR80 crore will be captured in the following quarter. That's because under the two-part tariff PPA at our Barmer plant, the capacity charge is based on 80% availability, and we will hit that 80% availability, so it will be included. Likewise, the energy generation beyond design energy, which we've achieved in all these years and will achieve this financial year too, means the INR66 crore EBITDA reduction versus last year in hydro and INR14 crores in Barmer will both be recouped during this financial year.

Prashant Jain

executive
#5

That INR91 crore hit stemmed from weaker merchant sales, which reflected soft demand during April and May. Even so, we feel very confident that the tariffs remain quite robust and the spreads are very good as well, and over the remainder of this financial year we will deliver what we budgeted and planned for in terms of merchant sales. Within the country, we have been observing a favorable trend for solar generation. The CUF <<inaudible>> for the country overall has been improving consistently. Our facilities at both Vijayanagar and Mytrah did exceptionally well. Against the P90 level, the Vijayanagar solar plant produced 145 million units, compared with P90 generation of 134 million units. The trend at Mytrah was similar — we lifted our plant availability by 70 basis points. And at Mytrah, for the first time, it generated 216 million units in the first quarter, compared with 193 million units of P90 generation, so both the integration of the Mytrah plant and its performance are better than what we had planned earlier. The same trend holds in wind. At Mytrah, when we took over the assets on 29th of March, total machine availability stood in the range of 85%, which has improved, and as I speak machine availability is 97.5%.

Prashant Jain

executive
#6

So by the middle of next month, we'll hit 99% availability, and that's something we've planned for. Total machine availability went up 680 basis points during the quarter. And we produced 695 million units. Altogether, 80 turbines were out of order. At this point, just two turbines remain out of order, and we're fairly confident that the plan we've laid out for Mytrah — both on EBITDA improvement and on overall generation improvement — has us on track and ahead of schedule. On the planned EBITDA of INR1,650 crores that we've guided for next year, we're already seeing a very encouraging trend in the current financial year itself, and we'll build on that trend and accelerate the improvement quickly. On project updates: Ind-Barath's performance on project integration is quite encouraging and quite good. We had been planning to start units by the end of the financial year. I'm glad to share that we opened up the turbines for maintenance as well as the boiler, and we were very pleasantly surprised by the plant's condition, and we're on course to put the unit on bar within this month, and with that transmission line and other items, we expect that by October, or perhaps within the current quarter itself, we'll commission the first unit.

Prashant Jain

executive
#7

We expect the second unit to be commissioned during this same financial year as well. So for one 350 MW unit, we anticipate generation coming in the latter half of the year, and that should lift both our generation and our EBITDA profile as we move ahead. We've already begun taking part in the auctions in East Valley <<inaudible>> and NCL. Part of the coal has already been secured, and the remainder we are securing over the course of time. Our Kutehr update is quite positive. Tunneling is already 98.5% or 99% complete, and powerhouse erection has begun and is proceeding according to schedule. The recent rains in Himachal Pradesh caused disruption owing to some landslides in and around the Kutehr project, but conditions are returning to normal, and within the next seven days we will be back to normal, and at our operating assets in Himachal as well, there was no effect from the rains apart from a preventive shutdown we had to take because of a higher silt level present in the basin and — but both the plant and the people are absolutely safe and there was no impact whatsoever.

Prashant Jain

executive
#8

Regarding our SECI projects, right now 150 MW has been fully commissioned. We're on track with the guidance we gave, and across all three sites — Karnataka and the two in Tamilnadu — erection and commissioning work is proceeding at full pace. Turning to the merchant market, which I mentioned in my opening remarks and which looks quite appealing, the rates are appealing as well. Through the quarter, prices were very strong at close to INR5.5, volumes rose 34% in that quarter, and looking ahead, based on the demand trend and the pricing we're observing — speaking now during the monsoon months — we're seeing prices near INR5 to INR5.5 on an RTC basis, which are fairly remunerative for our company. So we stay quite optimistic about recovering what was a small blip relative to last year in Q1. For the remainder of the year, our merchant volumes should be quite healthy, and the spread should follow suit. Now I'll ask Pritesh to take over and walk through the financial performance.

Pritesh Vinay

executive
#9

Thanks, Prashant. Good evening, everyone on the call. I might also pick up on what Prashant said regarding overall generation. So, looking at total net generation for the quarter, it rose 14% to roughly 6.7 billion units. Total revenues for the quarter came in at slightly above INR3,000 crores, which was in fact lower by 3% Y-o-Y versus a higher net generation, mainly because, as you know, for our common businesses the fuel cost is a pass-through. So year on year, coal prices have fallen sharply, and from a pass-through perspective that shows up as lower tariffs and hence lower realization. That said, it's largely EBITDA neutral. So that covers the revenue side. Prashant has already covered EBITDA for the quarter, which stood at INR1,307 crores. I'd like to add a bit more on that. If you have our results presentation, which was uploaded a while ago. And if you turn to slide number eight, where we've provided an EBITDA bridge, it captures the various moving parts. Prashant mentioned that, looking at the Mytrah portfolio as a whole, for the quarter the Mytrah assets actually delivered an EBITDA of INR400 crores.

Pritesh Vinay

executive
#10

But looking at it from a consolidation standpoint, one of the SPVs was acquired on 6th of April, and the second 150 MW SPV was acquired on 15th of June. So it's only there for the final 15 days of the quarter. As a result, on a pro-rated basis under consolidation accounting, we've reported INR370 crores, though the underlying performance is actually INR400 crores. The extra EBITDA we received from the new solar project of 225 MW and the SECI project of 150 MW, both of which ran through the quarter, came to INR30 crores. Prashant spoke about how weaker hydrology at Hydro affected generation. Hydro generation fell 27% Y-o-Y. In EBITDA terms, though, that was a drag of INR66 crores. Still, if you look at our historical record, provided you can hit the design energy — which we've done consistently each and every year across the 20-year and the 12-year operating track record at both Baspa and Karcham Wangtoo — we're able to make this up in later quarters. As it happens, even with lower PLFs, plant availability for the quarter came in at a very healthy 108%, versus the normative requirement of 90% needed to recover the full capacity charge.

Pritesh Vinay

executive
#11

On Barmer as well, planned shutdowns meant lower availability, so we did not get full recovery of the capacity charge. That said, as we have done each year previously, this item hinges on availability across the whole fiscal year, and we are quite confident that, as in every prior year, over the remaining nine months we will reach overall availability, so I would view those INR50 <<inaudible>> crores as mainly timing mismatches that are likely to be recovered during the other nine months of the year. And naturally, Prashant mentioned the effect of weaker merchant sales, which came to roughly INR90 crores. Plus fees and O&M expenses and so on. That was the bridge on the EBITDA side. I would also like to spend a minute explaining finance cost for the quarter. On the headline, INR193 crores last year in Q1 has come in at INR486 crores. So on slide number nine, where we provide a detailed bridge explaining that impact, INR170 crores is the incremental interest attributable to the tax on the Mytrah portfolio, which, as we explained previously, was done at the time of acquisition.

Pritesh Vinay

executive
#12

Because of the highly attractive refinancing and debt sizing we completed, we prepaid the older lenders on the Mytrah portfolio, and that produced a onetime prepayment charge tied to the refinancing of roughly INR40 crores. That item occurs once and won't repeat in the quarters ahead. Then there's the effect of the extra debt from the Ind-Barath acquisition, plus the levering up of the common balance sheet that we're doing to fund growth projects through sponsors equity contribution — together those came to about INR80 crores. So on a recurring basis, with everything else held the same, summer should come in closer to INR445 crores going forward, unless we lever up the thermal assets somewhat further, which would add again. That covers the finance cost bridge, and moving all the way down to profit-after-tax for the quarter, on a headline basis, Q1 of last year saw profit after tax of INR560 crores. However, in last year's first quarter we received repayment of a loan made to a third party in earlier years, and so that gave an exceptional gain of INR120 crores; taking that out, underlying profit-after-tax for last year's first quarter was INR440 crores — and again, on this same slide number nine, if you check the bottom portion, the PAT bridge lays out in detail how the Mytrah assets and the new renewable assets we're adding contributed about INR85 crores at the PAT level on a combined basis.

Pritesh Vinay

executive
#13

We had a drag of roughly INR55 crores to INR60 crores from the timing mismatch on full capacity charge recovery at hydro and Barmer, which is likely to be recouped over the rest of the year, plus the impact of Ind-Barath and the one-time refinancing impact. On the merchant side — lower merchant sales and profitability hit our PAT year on year by almost close to INR100 crores. So that's the PAT bridge. The next figure I want to discuss is leverage and our leverage profile. I'd ask you to turn to slide number 11, which presents net debt movement sequentially, so what has happened from March to June. You'll see that on the operating assets, the dark portion at the bottom of the chart, net debt stood at over INR10,100 crores, up by almost INR160 crores quarter on quarter because of additional debt on the operating businesses. On the Mytrah portfolio, net debt has actually declined by about INR350 crores quarter on quarter, since, as Prashant was saying, all the higher generation from better machine availability translated into higher EBITDA, along with some working capital release through liquidation of receivables.

Pritesh Vinay

executive
#14

As a result, cash levels have risen, and there's also been some debt repayment. Now, for the blue section — that's the debt tied to capital work-in-progress expected to generate revenue and EBITDA in the years ahead — it increased by roughly INR920 crores quarter-on-quarter, reaching just above INR4,500 crores. So, net debt. Looking at the operating businesses, roughly INR18,400 crores of debt sits there, serviced on a normalized cash flow of nearly INR5,300 crores, which works out to net-debt to EBITDA for the operating business of 3.5x. That aligns with the guidance we previously shared with the markets under our Strategy 2.2, namely that as we pursue growth, we'd anticipate our sustained normalized net-debt to EBITDA landing in the 3.5 to 4 times range. Turning to slide number 12. It presents a number of metrics, but I want to highlight just two, and the first is the chart at the top right, where we monitor cash returns on the underlying business. So we've kept tracking at over 17% cash returns on adjusted net worth across the last several quarters.

Pritesh Vinay

executive
#15

Now, turning to the weighted average cost of debt: excluding the Mytrah portfolio, that figure was just about 8.5%, and with the Mytrah portfolio included, it comes to roughly 8.7%. The final number I want to address before opening things up for questions concerns receivables. If you turn to slide number 13, on a year-on-year basis — sorry, on a quarter-on-quarter basis — headline receivables have declined by 20%, yet in terms of days sales outstanding, the picture is broadly the same: 60 days in March, and about 58 days as of the end of June. What is encouraging, though, is that the overdue proportion is trending downward. The share of overdues is lower. In fact, during the first two weeks following the close of the quarter, collections have been strong. We have already brought in close to INR240 crores. And as of today, while we are speaking, overdues stand at nil. Similarly, for the Mytrah portfolio, I would just ask you to look at slide number 60 — six zero — where we have laid out what is happening with the Mytrah receivables cycle, and there we have seen a very encouraging trend.

Pritesh Vinay

executive
#16

When you examine the lower section, each month the amount we're gathering compared with what we're invoicing consistently falls in the range of 125% to 200% of tax. So the pattern of turning receivables into cash remains sound. With that said, I'll stop here, and operator, we'd ask you to open the line for questions, please.

Operator

operator
#17

Many thanks. At this point we'll open it up for questions. <<operator_script>> Our first question comes from Mohit Kumar at ICICI Securities. Your line is open.

Mohit Kumar

analyst
#18

Good evening, sir, and congratulations on the substantial headway with the strong — with the assets still under construction. My first question concerns Mytrah's EBITDA. As I understand it, this portfolio is mainly wind, and the first quarter looks like a decent figure. What I'd like to ask is whether you believe we remain on track to hit INR16 billion of EBITDA in FY ’24, or whether that is more likely to come through in the full year of FY ’25?

Prashant Jain

executive
#19

Thank you. Thank you for your question. So there are two aspects to it: one is getting the turbines on track and improving asset availability. What was envisaged was to grow and reach up to 99% availability by December 2023. Against that, I have already given guidance that, as we speak, we see the turbines now and then, and by 15th of August, we will be at 99% availability. So what we planned, we will be achieving five months or six months — five months ahead of schedule. So that's part A. The same situation applies in terms of solar, and we had given guidance that we will be achieving INR1,650 crores of EBITDA in FY '25. So our guidance still remains INR1,650 crores for FY '25. This current year, we are expecting that the — since the majority of the wind season is up — or a part of the wind season will also be captured during this year, we will be doing better than what we had planned originally. I think by if I — we have talked about <<inaudible>> months' time-frame EBITDA improvement, but I think we are reaching on the achievement side close to a six to seven months time frame, but some of the rain season is going away by the time all these things are there, but we will be doing better than what we had planned.

Mohit Kumar

analyst
#20

The second question concerns the PSP. So, on that project, have you reached financial close? And have you broken — I mean, have you begun work on that particular project? As for PSP sites, how many are under our control, in the sense that the sites have been handed over to us?

Prashant Jain

executive
#21

We’ve already been allocated close to 9,000 MW of Pumped Storage Projects. And out of that, for 80% of the projects we’ve already prepared the DPR, and they’re at various stages of approval. And for two of the projects we’ve already received the terms of reference. For one project we’ve already completed EIA E&P, and the public hearing is also done, and then forest land accrual is in process, and we expect that in the current financial year at least one project we’ll be starting construction on — for which we’ll be taking the necessary approval and entering into a final PPA, and thereby the financial closure — and next year we expect two projects should get into that position by the end of next financial year. So that’s how it stands — each project is at a different stage, but one project will achieve all approvals and PPAs as well as other things to begin construction. And that will be the project that we’ll be building for our Group Captive and which is within our steel plant, where most of the land and other things are also in place, and there all EIA and E&P has been completed.

Prashant Jain

executive
#22

For the second project, we've already locked in LOIs with the Government of Karnataka, so to speak. As for the third one, it's currently in the bidding phase as well as going through various approvals.

Mohit Kumar

analyst
#23

The final thing I want to ask is this: since a lot of new projects — a lot of new tenders from SECI — are coming as RTC hybrid, we haven’t seen solar bids being participated in. Do you think our participation has increased materially under hybrid RTC, given that we have a portfolio of projects that are ideally more competitive?

Prashant Jain

executive
#24

We're examining every bid as well as what it costs to carry out the project, and right now we're in the middle of constructing the pipeline for beyond December 2025, since every one of the projects currently under commissioning will be finished by December 2025 — so at this point we're building that pipeline. We're assessing the Group Captive requirement, for which we have a decarbonization strategy for the JSW Group, and we've gotten inbound queries from our JSW Group to evaluate and work on that, plus SECI bids. And within that framework, we'll be finalizing that pipeline over the coming one or two quarters, which will fill up project execution for FY 25, ’26, ’27.

Mohit Kumar

analyst
#25

Got it, sir. Thanks very much, and good luck to you, sir. Thanks.

Operator

operator
#26

Thanks. <<operator_script>> Our following question comes from Karan Gupta at <<inaudible>> Capital, who is on the line. Go right ahead.

Karan Gupta

analyst
#27

Thanks for the chance to ask. I just wanted to check — with the seasonal rains we're seeing now, what does that mean for how much water will be available for your hydro projects in the quarter ahead?

Prashant Jain

executive
#28

Every one of their projects is operating at 110%.

Karan Gupta

analyst
#29

All right, that's helpful. Now, turning to merchant power tariffs and where coal prices stand right now — they've fallen quite sharply — what's your outlook for the coming year?

Prashant Jain

executive
#30

We're getting a solid spread right now, since coal prices have dropped quite a bit as well, let's say. But when do you figure that once the monsoon is behind us and demand picks back up, things will be pretty healthy? And even through the monsoon itself, the tariffs at present are really strong.

Karan Gupta

analyst
#31

Can you talk at all about how coal prices convert into the margins we earned on merchant power — is that something you're able to share along those lines?

Prashant Jain

executive
#32

No. What I’m getting at, I think, is that with the coal prices we’ve actually executed at and the merchant power prices currently in effect, there’s a positive spread. So in that <<inaudible>> respect, I’d say we aren’t worried. Our bigger concern is really demand itself, so we can move more volumes. Once demand gets better, there’s good money to be made in the merchant market.

Karan Gupta

analyst
#33

Okay, that's reasonable. And one final thing — word came out not long ago that the UP government is building a new coal power plant. I believe it's roughly 1.6 gigawatt. The price attached to it is genuinely startling. It came in above INR11 crores per megawatt. So I just wanted to hear your take on that.

Prashant Jain

executive
#34

That part is mine to address. We aren’t part of anybody’s plan, though I’d note that at present it takes anything from INR4.5 crore to INR4.8 crores to INR5 crores per megawatt, with FGD cost included and inflation taken into account. As for power prices, every new project we’ve joined is also going to come in close to north of INR4.5, and if you look at the recent tender that was done and concluded for the medium-term, the tariffs discovered fall in the range of INR5.20 to INR5.50 at best.

Karan Gupta

analyst
#35

Much appreciated.

Operator

operator
#36

Thanks. Our following question comes from Anuj Upadhyay at Investec, on the line. Go ahead, please.

Anuj Upadhyay

analyst
#37

Yes, thank you for the chance to ask, sir. Could you go into more detail about the green hydrogen project, and also about the module manufacturing side of things? And I believe we've moved the base from Odisha to a different state — could you shed some light on that, sir?

Prashant Jain

executive
#38

This project is going to be built in the State of Rajasthan. We've already identified the land, and the proposal with the Government of Rajasthan for the necessary incentives and other matters is in the final stages of approval. Negotiations on the plant and machinery are also underway. The project remains on track for commissioning by March 2025. As for the hydrogen project, preliminary work has already begun. Detailed engineering is in progress, and the ordering of electrolyzers and commercial negotiations are — that's ongoing. We're on track to commission that project in the quarter ending March ’25. So both of these projects will be commissioned by that time.

Anuj Upadhyay

analyst
#39

All right, sir — and the offtaker for our green hydrogen would be our group company. Or we’re also looking for someone —

Prashant Jain

executive
#40

We've already made the disclosure and declaration following Board approval, covering the arrangement between JSW Steel and JSW Energy. That arrangement will serve the production of green steel. It operates on a cost-plus basis, at a 15% ROE for the project, under a seven-year contract, with the total project cost amortized across a period of seven years. And after that, it will be materially disbursed.

Anuj Upadhyay

analyst
#41

Alright sir, finally regarding the battery project we have, I believe 40% of that capacity remains open. So is there any guidance on that, sir — whether we're seeking another long-term arrangement for it, or have we identified the short-term market?

Prashant Jain

executive
#42

No — at this moment we're deliberately holding that capacity in the short-term market, since we're seeing a fair amount of arbitrage there. I'm not sure whether you're noticing what's happening in the market right now. The spread between off-peak and peak power prices runs anywhere from INR4, and there's also a separate ancillary market for <<inaudible>> management where battery projects get certain incentives. Our view is that — give it some more time and there will be a substantial chance to make money in this segment. That said, we're also keeping an eye out in case any great opportunities come along that we could pursue in that capacity, though we see things staying quite <<inaudible>> at this point. It's a similar situation to Ind-Barath — I get so many inbound calls about signing long-term PPAs from Ind-Barath, but we don't want to commit to a PPA right now. We want to keep that capacity open in the merchant.

Anuj Upadhyay

analyst
#43

Much appreciated, sir. If you don’t mind, I’d like to add one more question, sir. It concerns the new capacity. We already have quite a bit — I mean SECI <<inaudible>> X, which is due to be scheduled here — but given that the government has mandated roughly 50 gigs of renewable capacity to be <<inaudible>> the current fiscal, are we pursuing this side of the project aggressively, or for the time being are we focused mainly on the pump hydro <<inaudible>>?

Prashant Jain

executive
#44

So, I think you're familiar with our Strategy 2.0, where we've been very explicit about how we're hitting our capital expenditure each year, and we also discuss capacity additions. In my response to an earlier caller, I explained that around December ’24, we're now building the book across Group Captive as well as various other opportunities. There's only a certain amount we can do as capex annually, given capital availability and the execution that's feasible because of connectivity and the resources we have on hand. So we're trying to balance things with an eye on maximizing our returns. That means we're carefully picking options and opportunities so we achieve the best possible ROEs and equity IRRs. That's what we're doing. And over the next one or two quarters, you'll see we're building the book beyond December ’24, and you'll get visibility into another 4 to 6 gigawatts being built over the next three years beyond December ’24 and March ’25, so we'll have visibility through ’27, ’28.

Anuj Upadhyay

analyst
#45

That's a fair point, sir. I appreciate the chance, and I wish you the best of luck.

Operator

operator
#46

Thanks. <<operator_script>> Our following question comes from Shreyans Daga at Barclays. Kindly proceed.

Shreyans Daga

analyst
#47

Hi, thanks, and thank you for taking my question. I know you already addressed a question about hydro projects, but specifically, a media report said that Karcham Wangtoo and Baspa two were shut down because of the floods in Himachal. So could you shed some light on those two projects?

Prashant Jain

executive
#48

So no flooding occurred. Essentially, you have to realize that each year around this period, whenever rainfall or a cloudburst takes place — since these specific basins draw from <<inaudible>> — and if you've visited that site, it's really all about those mountains of sand. That causes the sand or silt level to rise into the water, and as a precaution there's a significant buildup; once the sand movement exceeds 5,000 to 6,000 <<inaudible>>, every plant opens its gates and enters auto flush mode, so the turbine isn't affected. This occurs regardless of whether the rains are heavy — it always happens at this time. So the units were offline for roughly 72 hours. Then, once the silt level dropped back to the permissible limit, they all resumed operating, and every one of them is running at full load, at 110% load. And as I mentioned, the asset is in good shape and everyone is safe, with no disruption of any kind, temporary or permanent. In Kutehr's case, due to the landslide, there's a small amount of disconnectivity, which has been restored — some of the connectivity is back, and the remainder will return to normal within the next three to five days.

Pritesh Vinay

executive
#49

To be specific, Shreyans — if I may add — as Prashant said, the Baspa units reached full load as of 3:30 PM yesterday, and all four units at Karcham and Wangtoo went to full load at 5 PM yesterday. Before that, for 72 hours, from an upgrade and safety standpoint, they had been shut down because of high silt levels. Yeah.

Shreyans Daga

analyst
#50

Right, right, thank you — that covers everything.

Operator

operator
#51

Thanks. Our following question comes from Manas Arora at Dinero Wealth, who is on the line. You may proceed.

Manas Arora

analyst
#52

Good evening, and thanks — I've got a question about wind energy. Sir, I'd like to know whether we're planning any additional capex in wind energy beyond the projects we currently have under construction?

Prashant Jain

executive
#53

As I mentioned, our plan is to develop roughly 1.5 to 2.2 gigawatts of projects annually, and past December ’24, we need to build a book — we’re in an absolutely comfortable position to build that book. As I said, there’s a group captive requirement of approximately 5 to 6 gigawatts to be constructed across a timeframe of the next three, four years, and there are also other opportunities we’re pursuing when it comes to hybrid and other SECI bids. So we’re carefully evaluating and looking at equity IRRs where we can maximize our return, and in the next two quarters, we will build a book beyond ’25, and you will see that happening, and there will be complete visibility of that book, which will be executed. You know we have always said that we don’t build the book well in advance when it cannot be executed over a timeframe of the next 24 to 30 months. We build the book only when we can execute immediately. So this is how we have been, because most of the time, if you build the book ahead of schedule, then you are forced to compromise on your returns, and that’s what we have not been doing, and we had been very picky and choosy about it, so there will be a book you’re going to be seen to build in the next one or two quarters.

Manas Arora

analyst
#54

Sure sir, my next question is whether we're going to take part in the SECI 2.5 gigawatt tenders, the build ones?

Prashant Jain

executive
#55

We’re certainly keeping the tariffs in mind. Tariffs have looked encouraging lately, and module prices are coming down as well, which is quite encouraging too, so we’ll balance things out, since what we’re after is returns in the mid-teen to high-teens range, and that’s what we always aim for.

Manas Arora

analyst
#56

Alright, thank you very much. And that’s everything from me.

Operator

operator
#57

Thanks. Our final question comes from Chirag Kachhadiya, an individual investor.

Chirag Kachhadiya

analyst
#58

Hello there. Given the disruptions over on the Northeast side, what kind of effect on generation are we anticipating?

Prashant Jain

executive
#59

The impact is nowhere now. What was meant to occur has already occurred. Demand is also improving at this point, and relative to last year, July demand as it stands right now, for the full month, is up close to 5.5%.

Chirag Kachhadiya

analyst
#60

Okay, sir. I'd like to get a clearer picture of the battery and storage business that we recently entered. So could you give me some basic understanding of what it will mean for our company going forward? And what potential does that business hold?

Prashant Jain

executive
#61

Storage represents a major opportunity to build on, according to CEA projections for 2030. To manage the grid, we will have 500 gigawatts of renewable capacity in place. We need 320 gigawatt hours of present storage capacity, which will be met by both the assets as well as GST on storage projects, and that refers to 320 gigawatt-hours, or six hours of storage, meaning we are talking about close to 50,000 MW of capacity. So we see this as a great opportunity for JSW Energy, and we have ventured into both the BSS and TFC segments, and both segments with what the first standard with us. So it's quite encouraging, and we have got a large resource pool, and we will be growing our company in this particular segment going forward.

Chirag Kachhadiya

analyst
#62

And sir, how much capex did we incur for this venture?

Prashant Jain

executive
#63

It really hinges on the capacity — if you're putting up a full storage project, the range is roughly INR3.85 crores per MW up to INR7 crores per MW, and that depends on how the project is configured, how big it is, where it's located, and the amount of storage capacity. That's basically how these projects get built, and typically you're looking at 5.5 hours to 8 hours of storage capacity with 75% to 85% efficiency. As for the battery project, it comes down to battery prices. Right now, the system cost runs anywhere from USD300 to USD400 per kilowatt-hour, and that will certainly fall to USD150 to USD300 going forward over a period of time as battery prices come down.

Chirag Kachhadiya

analyst
#64

Thanks a lot. Wishing you the very best.

Operator

operator
#65

Thanks. At this point I’ll pass the conference to Mr. Sudhanshu Bansal of JM Financial for closing remarks.

Sudhanshu Bansal

analyst
#66

We really appreciate JSW Energy’s management letting JM Financial host this call. And thanks to everyone on the line for joining this conference call. Sir, would you like to offer any closing remarks?

Prashant Jain

executive
#67

Thanks, Sudhanshu, and thanks to all of you. If any follow-up questions come up, don't hesitate to reach out to our Investor Relations team — they'll be glad to clear up anything you need. Thanks once more.

Sudhanshu Bansal

analyst
#68

All right, thanks a lot, and I hope everyone has a great weekend. Thank you. That brings the call to a close.

Operator

operator
#69

<<operator_signoff>>

Read the full transcript via the API

You're viewing the first half of this call. Get the complete JSW Energy Limited transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

This call discussed

For developers and AI pipelines

Programmatic access to JSW Energy Limited earnings transcripts and 132,000+ others is available through the EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research

OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in JSW Energy Limited or any ticker on your watchlist.

StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.